CEE gas operators begin binding capacity offer process

  • : Natural gas
  • 24/05/02

Gas transmission system operators (TSOs) across central and eastern Europe have launched the start of binding incremental capacity processes aimed at facilitating larger gas flows from south to north.

Romanian, Bulgarian, Hungarian, Moldovan and Ukrainian operators have published joint documents outlining the necessary conditions for participating in the upcoming annual auctions on 1 July.

Bulgarian and Romanian TSOs Bulgartransgaz and Transgaz will offer an additional roughly 123 GWh/d of capacity from Bulgaria to Romania at Negru Voda 1-Kardam on top of existing available capacity of 126-142 GWh/d depending on the year (see BG-RO table). In the event of a successful auction and subsequent economic test, the TSOs hope to reach a final investment decision (FID) in the third quarter of this year and commission the upgrades in the third quarter of 2026. Commercial operations could begin in the fourth quarter, aligning with the start of the 2026-27 gas year. This timeline has been moved forward by one year from the original proposals earlier this year.

Transgaz, along with Hungary's FGSZ, will offer up to 73 GWh/d of additional capacity from Romania to Hungary at Csanadpalota on top of existing available capacity of 5-71 GWh/d depending on the year (see RO-HU table), but maintained its three-tiered approach elaborated in an earlier market consultation. Depending on the level of capacity to which firms commit at the auction, capacity could increase by 9.5 GWh/d, 47.3 GWh/d or 72.5 GWh/d. The smallest project could start commercial operations in the first quarter of 2028, the middle level in the third quarter of 2028, and the highest level in the third quarter of 2029. These timelines are pushed back by roughly one year from the originally-proposed dates in the February consultation.

And Transgaz, along with Ukraine's GTSOU, will offer an additional 77 GWh/d of capacity from Romania to Ukraine at Isaccea 1-Orlovka 1 on top of existing available capacity of 97-109 GWh/d depending on the year (see RO-UA table). The TSOs aim to reach FID in the third quarter of this year and commission the project in the fourth quarter of 2028. Commercial operations could begin in October 2028.

GTSOU and its Moldovan counterpart Vestmoldtransgaz will offer 173 GWh/d towards Moldova from Ukraine at Kaushany starting from the 2027-28 gas year, while simultaneously offering 159 GWh/d of capacity from Moldova towards Ukraine at Grebenyky.

Available and incremental capacity at Negru Voda/KardamGWh/d/yr
Gas yearAvailable existing capIncremental capTotal
2024-25141-141
2025-26141-141
2026-27142123265
2027-28142123265
2028-29142123265
2029-30-2042126123249
Available and incremental capacity at CsanadpalotaGWh/d/yr
Gas yearAvailable existing capIncremental capTotal
2024-2543-43
2025-2646-46
2026-2771-71
2027-2813-142
2028-2913-13
2029-3057378
2030-313473107
2031-323473107
2032-33-20396373136
Available and incremental capacity at Isaccea/OrlovkaGWh/d/yr
Gas yearAvailable existing capIncremental capTotal
2024-25109-109
2025-26109-109
2026-27109-109
2027-28109-186
2028-2910977186
2029-30-20399777174

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more