Latest market news

German utilities doubt 25GW gas plant additions by 2030

  • Market: Electricity, Hydrogen
  • 11/10/23

Germany is unlikely to be able to add 25GW of new gas-fired capacity by 2030, several German utilities have told Argus.

Uniper assumes only around 20GW of new gas-fired capacity could be built by 2030, based on the framework for hydrogen-ready plant tenders outlined by the economic affairs and climate action ministry (BMWK) in August. And the utility highlighted that even 20GW was an "ambitious target" as it would assume additions of 3 GW/yr, and rates of new construction have tended to be in the 1-2 GW/yr range.

Steag said that under the given framework, plant operators are "unlikely" to put up large sums of money to build new gas-fired power plants as there is too little planning certainty. Vattenfall told Argus that fuel use itself should be supported to increase demand and ensure the ramp-up of hydrogen production and availability, which it said is "the only way" to keep prices at a "tolerable" level in the long term.

EnBW concurred on the lack of clarity, with more concrete information needed on the government's plans and particularly surrounding to what extent combined heat and power plants (CHPs) will be included in the tenders. Vattenfall also said that in order to achieve a rapid ramp up, the hydrogen "starter grid" should take CHPs into account.

The utilities generally agreed that both greater clarity around the specifics of the tenders and their timely implementation is essential, with Michael Muller, chief executive of RWE — which holds a dominant position in the German power market — particularly highlighting that the additions are "crucial" to enable a coal phase-out by 2030.

A total of 11.9GW of conventional capacity is expected to be decommissioned by 2025, and renewable additions have been consistently below the pace required to reach the country's 2030 targets, raising concerns about supply as the industry-heavy country tries to decarbonise.

BMWK estimates that demand will rise to around 750TWh by 2030, which the country's transmission system operators expect to see particularly in the demand-heavy southern and western areas of Germany. Southern utility EnBW said that the "decisive factor" for it is whether the specifics for southern Germany will be taken into account, as the demand-heavy part of the country will see later availability of hydrogen.

But in combination with other measures such as increased use of batteries and lower electrification than assumed by BMWK, the addition of 15GW of new gas-fired capacity by 2030 could be sufficient to meet the supply crunch, according to Erfurt University of Applied Sciences professor for energy economics Konstantin Lenz.

Utilities Steag and Leag told Argus they are planning to build 3GW of gas-fired capacity each by 2030, and EnBW said it is implementing 1.5GW of fuel-switch projects, while Uniper is planning "gigawatt scale" new flexible plants. RWE and Vattenfall did not disclose planned capacity additions. Together, RWE, EnBW, Leag, Vattenfall and Uniper's portfolios account for over half of Germany's installed capacity outside the renewable energy act.

Both Uniper and Steag called for the creation of a capacity market in Germany, which Steag argued would help to close the looming supply gap. Uniper also highlighted that it is uncertain whether the targeted gas-fired additions would be sufficient to cover peak load requirements in the future, and that a capacity market would combine the security of supply instruments Germany has available such as its grid, capacity and lignite reserves and take greater account of measures such as batteries or load management.

Earlier this week, Germany's monopolies commission recommended the creation of a capacity market to replace the country's capacity reserve, which is due to expire in 2025. The capacity market proposed by the commission would comprise three stages and combine decentralised and centralised capacity market elements.


Sharelinkedin-sharetwitter-sharefacebook-shareemail-share

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

News
06/12/24

US H2 hopes at risk with 45V uncertainty: Industry

US H2 hopes at risk with 45V uncertainty: Industry

Houston, 6 December (Argus) — US hydrogen industry developers need more clarity on federal production tax credits (PTC) before moving forward with projects but are hopeful they can convince the incoming administration of the benefits they represent. A raft of hydrogen projects were announced in the US after President Joe Biden announced billions of dollars in federal funding and tax credits for hydrogen within the 2022 Inflation Reduction Act. But much of that euphoria fizzled after the US Treasury last December proposed rules mimicking European standards that some in the industry argue are too stringent and would make many projects, especially those using natural gas, uneconomical. "Everyone looked at the US as a very promising market but the reality is that as time goes by uncertainty is growing," said Ana Quelhas, managing director of hydrogen at EDP, on a panel this week at the Reuters EnergyLive conference in Houston, Texas. "There's a big question mark related to the implementation of 45V and that's very bad for investors." The US still has the opportunity to be a leader in hydrogen if it can implement rules around how the 45V credit is applied correctly, said Tomeka McLeod, vice president of hydrogen at BP. If so-called blue projects — which make hydrogen from natural gas — can get the full $3/kg credit, "... it would make our projects some of the most competitive globally," McLeod said. Rules related to the use of renewable and certified natural gas in hydrogen production still need to be "hammered out," she said. BP aims to have 5-10 projects online by the end of decade but McLeod says they will be evaluated by the same internal standards of any other project. "We need to make sure that the economics of those projects work, they need to be able to compete within our portfolio," she said. BP is part of the Midwest Alliance for Clean Hydrogen (MachH2) that recently received $1bn in Department of Energy (DOE) funding and plans to produce hydrogen from natural gas with carbon capture to power its Whiting refinery in Indiana. Christmas gift or lump of coal Many of those gathered at the conference in Houston this week said they hoped further guidance would arrive "like a Christmas present" in the waning weeks of the year, and the Biden administration would sew up any lingering details before leaving office. Nonetheless, they still expect to be subjected to further scrutiny under the Trump administration, which has made clear its disdain for clean-energy mandates. Learning to speak to the concerns of the new administration will be crucial to success, industry leaders said, including explaining hydrogen's role in promoting national security and job creation. "We need to educate this incoming administration and collaborate and make sure that the momentum that is already here continues, and [show] that we can actually do the right thing from a national energy security perspective," said Sanjay Shrestha, president of Plug Power, a company that develops hydrogen fuel cells to replace conventional batteries. Keystate Energy chief executive Perry Babb, whose company is looking to produce clean hydrogen in Pennsylvania, said aligning with the administration's goals as well as a solid business case will be key to survival. "We will need to speak the language of the administration," Babb said. By Jasmina Kelemen Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Find out more
News

Denmark's wind tender flop linked to H2 network doubts


06/12/24
News
06/12/24

Denmark's wind tender flop linked to H2 network doubts

London, 6 December (Argus) — Denmark's failure to attract bids in an offshore wind tender was partly caused by the country's lack of firm commitment to a hydrogen pipeline network, according to Danish and European hydrogen associations. For Denmark's hydrogen industry the failed tender is raising concerns that Copenhagen might resort to state aid for offshore wind, which could jeopardise renewable hydrogen production that is compliant with EU rules. Denmark unsuccessfully offered three areas totalling 3GW in a first part of the auction that ended on 5 December, and will offer another 3GW in a second part ending in April 2025. The "very disappointing" result will now be investigated by the Danish Energy Agency to discover why market participants failed to bid, energy minister Lars Aagaard said. Wind project developers may have worried that low electricity prices in an increasingly saturated power market and inadequate export routes — either via power cables or as hydrogen via pipeline — would deny a return on investments, industry participants said. Ample offshore wind potential could allow Denmark to generate power far in excess of its own needs. But in order to capitalise on this the country would need to find a way of getting the energy to demand markets. Turning offshore wind into renewable hydrogen for export was "a very attractive solution" for developers, Hydrogen Europe chief policy officer Daniel Fraile said, but would rely on timely construction of a network "all the way from the coast to Germany's hydrogen-hungry industry." Denmark's hydrogen network was recently pushed back to 2031-32 from an initial 2028, partly because of an impasse over funding that provoked anger from industry. The government has said it will only help fund the hydrogen transport network if there are sufficient capacity bookings guaranteeing its use. But this approach increases risks for developers, according to Fraile. "You need to handle the risk of winning the offshore tender, finding a hydrogen offtaker in Germany and commit to inject a large amount of hydrogen over several years. Then deliver the project on time and on cost," he said. "This is a hell of an undertaking." Industry association Hydrogen Denmark's chief executive Tejs Laustsen Jensen agreed, calling the failed tender "a gigantic setback". "The uncertainty about the hydrogen infrastructure has simply made the investment too uncertain for offshore wind developers," he said. "Now the task for politicians is to untie this Gordian knot." "Of course, the tender must now be re-run, but if the state does not guarantee in that process the establishment of hydrogen infrastructure, we risk ending up in the same place again," he said. The booking requirement as a prerequisite for funding the network "must be completely removed," Jensen said. Green energy association Green Power Denmark said "there is still considerable uncertainty about the feasibility of selling electricity in the form of hydrogen," but pointed to other factors that may have led to the tender failing to attract bids. Wind turbines and raw materials have become more expensive because of inflation while interest rates have risen sharply, reducing the viability of such projects, the group's chief executive Kristian Jensen said. Unlike some other countries, Denmark does not intend to fund grid connections or provide other subsidies, he said. Unwanted help Hydrogen Denmark's Jensen warned against the government resorting to subsidies to help get offshore wind farms built. "State support for offshore wind would be the death knell" for the hydrogen sector and would "de facto kill all possibilities for a green hydrogen adventure in Denmark," he said. Granting state support for offshore wind farms would mean these assets would not comply with the additionality requirement of the EU's definition for renewable fuels of non-biological origin (RFNBO), which are effectively renewable hydrogen and derivatives. EU rules state renewable assets are only considered 'additional' if they have "not received support in the form of operating aid or investment aid," although financial support for grid connections is exempt from this. "If state aid is provided for the offshore wind that is to be used to produce the hydrogen, we will lose the RFNBO stamp, and the Danish hydrogen cannot be used to meet the green EU ambitions for, among other things, industry and transport, and the business case is thus destroyed," Jensen said. By Aidan Lea and Stefan Krumpelmann Geographical divisions of Denmark's H2 network plan Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Newly agreed EU, Mercosur FTA faces uphill battle


06/12/24
News
06/12/24

Newly agreed EU, Mercosur FTA faces uphill battle

Montevideo, 6 December (Argus) — The EU and South America's Mercosur closed a free-trade agreement (FTA) nearly 25 years in the making, but there is still a long road to ratification. Uruguayan president Luis Lacalle and European Commission president Ursula von der Leyen announced the deal at a Mercosur summit in Montevideo, the Uruguayan capital. The presidents of the three other Mercosur founding members — Argentina, Brazil and Paraguay — were present. The FTA will remove tariffs on more than 90pc of goods among the members. Von der Leyen called the agreement a historic milestone that would benefit 700mn consumers. She said the agreement "is not only a trade agreement, but also a political necessity." Lacalle said "an agreement of this kind is not a magical solution, but an opportunity." Leaders recognized that the agreement still has major hurdles to clear as it requires approval from member states. The agreement will go to legal review and translation in the next month in view of its future signing, according to the Mercosur-EU declaration. While the Mercosur countries are in favor of the agreement, opposition is strong in France, Poland and several smaller EU states. Argentinian president Javier Milei, who supports the agreement, criticized Mercosur as a block. "Mercosur, which was born with the idea of deepening our commercial ties, ended up like a prison that does not allow its members to take advantage of their comparative advantages or export potential," he said. Van der Leyen said that more than 60,000 businesses, half of them small, export to Mercosur. The EU exported $59bn to Mercosur in 2023, while Mercosur's four founding members shipped $57bn to the EU. She also stressed the importance of EU investment in Mercosur, including in sustainable mining, renewable energy and sustainable forestry. Brazilian president Luiz Lula da Silva said during the summit that the region had to take advantage of its resources, including agriculture and energy. The four Mercosur countries are major food producers, including crops such as corn, soy and sugarcane, used for biofuels. Brazil is the world's top soy producer, while Argentina is third, Paraguay sixth and Uruguay in the 14th spot. Bolivia, which joined Mercosur in July, is the 10th producer. Brazil is a major mineral producer and Argentina is slowly beginning to strengthen its mining sector. It has the world's second-largest lithium resources. Argentina is also beginning to monetize its unconventional gas formation, Vaca Muerta, the second largest in the world with 308 trillion cf of reserves. It is working on different LNG projects, with a focus on exports to Europe. The Mercosur countries also have in common plans for low-carbon hydrogen production, which also see the EU as an export market for value-added products, such as fertilizers. By Lucien Chauvin Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

UK fuel mix disclosure ‘no longer fit for purpose’


05/12/24
News
05/12/24

UK fuel mix disclosure ‘no longer fit for purpose’

London, 5 December (Argus) — UK company Smartest Energy presented a paper at today's RECS-led UK Rego Day seminar in London, calling for urgent reform of the electricity certification scheme to support decarbonisation goals. Smartest Energy is calling for a shift to full production and consumption disclosure, with generators receiving a certificate of origin for every MWh they send into the grid — regardless of the fuel source. This would allow renewable and non-renewable generation to be tracked and enable consumers to make informed decisions, the paper argues. Another proposal is to gradually move away from the current methodology for fuel mix disclosure, which is based on annual matching — this system effectively means consumption within a specific timeframe can be matched to output in any other period during the disclosure year. The paper suggests an initial shift to quarterly matching, followed by monthly and daily matching. Closer temporal alignment would "encourage investment in grid development and deeper decarbonisation", according to Smartest Energy. It would also give a clearer picture of seasonal and daily energy demand and the physical reality of electricity flows. The paper suggests that more transparency is particularly important now that European guarantees of origin (GOOs) are no longer recognised in the UK, and while electricity continues to flow from the continent through interconnectors. Argus assessments for non-biomass Regos generated in the current compliance period 23 (CP23) — April 2024-March 2025 — averaged £4.19/MWh in November, while CP23 biomass was assessed at an average of £3.88/MWh. In Europe, full disclosure has already been implemented in Austria, Switzerland and the Netherlands. Dutch GOOs tend to trade at a premium to the rest of the continent, with consumer preference for local certificates driving demand. France moved to monthly certificate matching at the beginning of 2021. By Giulio Bajona Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Brazil's economy accelerates to 4pc growth in 3Q


04/12/24
News
04/12/24

Brazil's economy accelerates to 4pc growth in 3Q

Sao Paulo, 4 December (Argus) — Brazil's economic growth accelerated to an annual 4pc in the third quarter, led by stronger consumer spending, according to government statistics agency IBGE. The economy accelerated from 3.3pc annual growth in the second quarter and posted the fastest growth since the first quarter of 2023. Household consumption grew by 5.5pc in the third quarter from a year earlier, while government spending increased by 1.3pc. Services grew by 4.1pc. The industry sector grew by an annual 3.6pc, driven by civil construction and five-year high automotive production in July , according to the national association of vehicle manufacturers. Exports rose by 2.1pc, while imports grew by 18pc. The oil, natural gas and mining industry contracted by 1pc, thanks to lower oil and gas exploration and production. Brazil produced 4.35mn b/d of oil equivalent (boe/d) in the third quarter, down from 4.51mn boe/d in the July-September 2023, according to oil and gas regulator ANP. The electricity and gas, water and sewage management sector increased by 3.7pc from July-September 2023, favoured by higher demand despite higher power tariffs. Brazil faced a severe drought in the first two quarters of the year that lowered river levels at hydroelectric plants and increased power charges in September. But the agriculture and cattle raising sector fell by 0.8pc, with expected production of significant crops such as corn and sugarcane dropping from a year prior also because of adverse weather. Still, output of cotton, wheat and coffee increased by 14.5pc, 5.3pc and 0.3pc, respectively, according to IBGE. The investment rate — the percentage of a country's total production that is invested — grew to 17.6pc in the third quarter, an increase of 1.2 percentage points from the same period in 2023. Brazil's GDP growth in the third quarter was up by 0.9pc from the second quarter, reaching R3 trillion ($494bn). By Maria Frazatto Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Generic Hero Banner

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more