Indonesian Sumsel 1 coal-fired unit eyes December start

  • Spanish Market: Coal, Electricity
  • 18/09/24

The first 300MW unit of the 600MW Sumsel 1 mine-mouth coal-fired power plant in Indonesia's south Sumatra province is scheduled to begin commercial operations in December following several years of delays.

The plant, which is located in Muara Enim regency, is being developed by China Shenhua Energy and Lion Power Energy, which have 75pc and 25pc respective stakes in the project. Once fully operational it is expected to consume around 2-3mn t/yr of coal. Lion will be responsible for sourcing the coal.

The $750mn plant is part of Indonesia's 35GW power generation roadmap developed by the Indonesian government in 2015.

The project was contracted to China Shenhua Energy in 2016. The first unit at the plant was originally scheduled for completion by 2020. But land acquisition delays and the Covid-19 pandemic and resulting restrictions on the movement of people and travel bans delayed construction, Lion said.

Construction work on the plant structure is now in the final stages and operational testing is expected to begin soon. But hitting the operational target date also depends on the completion of a 275kV high-voltage line that will connect the plant to the grid, state-owned utility PLN said. The 80km transmission line will pass through four districts in south Sumatra. The local government is pushing for the acceleration of the voltage line construction and has instructed the sub-district head and local government offices to provide support for the power line construction, PLN said.

Sumsel 1, once fully operational, will operate on a build-own-operate basis with a 25-year power supply contract with PLN, the utility said.


Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

Japan to phase out inefficient coal plants by 2030


03/10/24
03/10/24

Japan to phase out inefficient coal plants by 2030

London, 3 October (Argus) — Japan will target a phase-out of inefficient coal plants by 2030, as it continues its energy transition push, although the country is still yet to provide further details on any broader movement away from coal. "By 2030, the inefficient use of coal-fired power will be phased out," Japan's newly appointed environment minister Keiichiro Asao said at a press conference on Wednesday. Asao was appointed after Japan's new prime minister Shigeru Ishiba took office this week. Japan had earlier pledged to phase out "unabated" coal-fired plants by 2035 , or "in a timeline consistent with keeping a limit of a 1.5°C temperature rise within reach, in line with countries' net zero pathways". But inefficient, sub-critical coal plants — with below 40pc efficiency — make up only 22pc of Japan's total fleet, while 25pc is supercritical and 53pc is ultra-supercritical. The sub-critical plants probably produce less of Japan's coal-fired electricity, given the generation margins for them will fall below the majority of gas-fired generation in the merit order. This means Japan's overall coal-fired power generation is likely to be less impacted than the overall change to its coal fleet capacity. Japan has been considered a laggard in green energy transition among its G7 counterparts, but the country's coal demand could decline to some extent as a result of global divestment pressure. But coal is still key to the resource-poor country, as the government sees renewables and nuclear as insufficient to meet rising power demand driven by the growth of data centres needed to enable artificial intelligence. Japan's new government has recently announced that it will be restarting more of its nuclear reactors to help meet its power demand. Utility Shikoku Electric Power reactivated its sole nuclear reactor at Ikata on 29 September, after closing the unit for turnaround since 19 July. But the utility pushed back the restart of the 890MW Ikata No.3 nuclear reactor on Wednesday because of a technical issue during the process of resuming power generation. Japanese thermal coal imports rose by 10pc to 9.25mn t on the year in August, owing to increased deliveries from Australia. But this was 4pc lower than the past five-year August average of 9.6mn t. By Shreyashi Sanyal Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Colombia coal mining could halt with government decree


03/10/24
03/10/24

Colombia coal mining could halt with government decree

Bogota, 3 October (Argus) — Colombia's coal operations could come to a stop as the government will soon start issuing resolutions that regulate mining areas as temporary environmental reserves, Colombian Mining Association (ACM) director Juan Camilo Narino said. The decree, enacted on 30 January, states the country's environment ministry will identify, delimit and declare through administrative acts reserves of natural resources in areas that require restoration and rehabilitation. Such areas will become environmentally protected zones for five years with the possibility of extending that period for an additional five years. The decree takes away the autonomy and competence of the Regional Autonomous Corporations, which until now grants key licensing to keep coal operations running, but without those licences, coal operations could come to a halt, Narino told Argus on the sidelines of a hydrocarbon summit held in Cartagena. Narino said coal, gold, copper and other types of mining firms are extremely concerned with the potential resolutions due to be issued as they need minor licences granted by the corporations. Such licensing includes environmental licences to pour water into channels, take water from rivers and to pass over rivers. The environment ministry is likely to announce those resolutions at the CBD Cop 16 in Cali, Colombia, on 21 October-2 November. Colombia is set to champion a comprehensive and regionally inclusive approach to biodiversity conservation and climate action at this conference. "The decree clearly states that those corporations could no longer grant permits," Narino said. "As a result, the operating activity of existing licences is unfeasible as you can no longer operate without those minor licences." ACM has filed a lawsuit against the decree, while 11 industry unions, including the regional autonomous corporations, joined in suing the government in a lawsuit submitted on 6 August. They filed the lawsuits with Colombia's state council, the highest administrative court in the country, while requesting precautionary measures including halting the decree. The state council agreed on studying the lawsuit and could annul the ruling, but it could take 6-12 months to examine the case. The state council must listen to the defendants — the environment ministry — lawyer Luis Eduardo Delgado Martinez said. Environmental minister Susana Muhamad was summoned by congress to face a political control debate to explain the scope of the decree, Narino noted. Narino levelled several other criticisms against the decree, including calling the time frame of the temporary environmental reserve designations arbitrary. He also said IT bypasses other legal and constitutional norms. By Diana Delgado Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Mexico aims for 45pc renewable power by 2030


02/10/24
02/10/24

Mexico aims for 45pc renewable power by 2030

Mexico City, 2 October (Argus) — Mexico will generate 45pc of its electricity from renewable sources by 2030, new President Claudia Sheinbaum has pledged upon taking office in an immediate step-up in energy transition efforts. The government had previously committed to a 43pc share of clean energy, including nuclear and efficient natural gas-fired cogeneration. But Sheinbaum stated during her inauguration on Tuesday that the new goal will be achieved solely through renewable sources, such as solar, wind and hydropower, which will also meet growing electricity demand. In 2023, Mexico generated just 24.3pc of its electricity from clean sources, despite these holding 32pc of installed capacity, according to energy ministry (Sener) data. Low output from hydropower plans contributed to this shortfall. Wind and solar accounted for only 5.9pc and 5.1pc, respectively. Last year, the energy regulator (CRE) approved regulatory changes allowing the government to classify energy produced by natural gas-fired combined-cycle plants as clean. But international standards do not consider gas-fired generation as clean unless the plants use CO2 capture systems. Sheinbaum also pledged to introduce a new energy transition plan soon, to detail investment opportunities and projects in the electricity sector. She confirmed that state power utility CFE will maintain its prominent role, holding at least 54pc of electricity generation capacity. The president announced plans for large-scale rooftop solar panel installations for households with high electricity demand in the summer. She also committed to continuing the Sonora Plan, aimed at boosting solar generation, lithium production and electric vehicle part manufacturing in Sonora. Additionally, Sheinbaum promised to promote domestic lithium extraction technology, build 10 new recycling plants and implement air quality programs in cities like Mexico City, Guadalajara and Monterrey. She reiterated that CFE and state-owned Pemex will remain central to her administration and vowed not to sell their assets, as occurred under previous governments. By Édgar Sígler Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Mexico's Sheinbaum to present energy transition plan


01/10/24
01/10/24

Mexico's Sheinbaum to present energy transition plan

New York, 1 October (Argus) — Mexico's new president, Claudia Sheinbaum, will present a plan to attract new investments in the electricity sector and an "ambitious" energy transition strategy. Sheinbaum, Mexico's first female president, ratified the commitment made by former-president Andres Manuel Lopez Obrador of maintaining 54pc of the electricity generation in the hands of state-owned utility CFE and providing "clear rules" for private-sector companies to invest in the remaining 46pc. In her inauguration speech to congress, Sheinbaum said it was in the best interest of all Mexicans to have a strong public company in the electricity sector to provide cheap power to households. She promised that prices for electricity, gasoline and LPG will not rise faster than general inflation. The Mexican congress approved the process to change the constitution to give more power to CFE in prioritizing electricity dispatch over private-sector companies. Sheinbaum also said crude production will not go above 1.8mn b/d during her term, as it is "impossible" to reach the 3mn b/d promised under the 2014 energy reform without harming the environment. The increase in energy demand in Mexico will be met by renewable sources, she said. Among her economic priorities is attracting more international manufacturers to bring their plants to Mexico to take advantage of nearshoring — moving production closer to main markets. Her administration will also continue to implement the controversial bill to overhaul the judicial system passed in the last month . By Edgar Sigler Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more