Generic Hero BannerGeneric Hero Banner
Latest market news

Finnish, Baltic gas demand up by 13pc on year in July

  • : Electricity, Natural gas
  • 24/08/09

Combined Finnish and Baltic gas consumption increased on the year in July, but remained firmly below pre-2022 levels.

Combined demand in Finland, Estonia, Latvia and Lithuania last month rose to 2.37TWh from 2.1TWh in July 2023, although it was still well below the 2018-21 average of roughly 3.7TWh (see graph, data and download). This was a second consecutive month-on-month increase following demand at a near two-year low in May. Demand increasing between May and July is an unusual pattern, as pre-2022 consumption in the region tended to decline over the course of the summer before reaching a nadir in July or August.

The power sector was probably the main contributing factor to higher overall gas demand, as year-on-year increases in Latvian and Lithuanian gas-fired output more than offset lower Finnish generation (see table). In Latvia in particular, gas-fired generation jumped more than seven times compared with a year earlier, despite power demand remaining stable and hydropower output nearly doubling. Instead, Latvian gas-fired production displaced some net imports, which fell to 258GWh from 372GWh in July last year. Latvian gas demand peaked over the month at 27 GWh/d on 22-26 July, drastically above the average for other days of just 8 GWh/d. These were the same days that Latvia produced the majority of July's gas-fired power.

Prices on the regional GET Baltic exchange averaged €37.84/MWh in July, down by 5pc on the month but up by 3pc on the year. July broke the three-month trend of consecutive month-on-month increases, with prices having fallen in all four markets. Firms traded 500GWh on the exchange, up from 358GWh in July last year. Lithuania accounted for 40pc of trades, followed by the joint Latvian-Estonian market at 35pc and Finland with the remaining quarter.

Maintenance to change flows

Maintenance at the pivotal Kiemenai interconnection point on the Latvia-Lithuania border for most of August will change regional flow dynamics.

No capacity will be available in either direction at Kiemenai on the 3-25 August gas days, making it impossible to send regasified LNG from Lithuania's Klaipeda LNG terminal northward to Latvia for storage at the Incukalns facility. Klaipeda sendout consequently has dropped since 3 August, averaging 29 GWh/d on 3-8 August, compared with 101 GWh/d in July.

Despite the maintenance and demand remaining stable, an additional LNG delivery for 10 August was added to Klaipeda's schedule. This half-cargo may be mostly destined for reloads, as four small-scale reloads are planned at Klaipeda after the 10 August delivery. Some of these reloads could potentially go to Finland's off-grid terminals at Tornio and Pori, which are no longer supplied with Russian LNG after Gasum halted its purchases in late July because of sanctions.

But while maintenance at Kiemenai has started, restrictions further north on the Balticconnector have ended, enabling sendout from the Inkoo terminal to step up significantly to 85 GWh/d on 1-8 August from a much lower 32 GWh/d in July. Planned maintenance reduced capacity from Finland to Estonia on the Balticconnector to just 5 GWh/d for all of July, limiting sendout from Inkoo only to what could be absorbed by the domestic market and the small amount that could be sent southward. Maintenance also will reduce Finnish exit capacity to Estonia to zero on 14-27 October and 4-17 November.

Finnish + Baltic July gas-fired power generationGWh
Jul-24Jul-23Jun-24± Jul 23± Jun 24
Estonia22200
Latvia791136876
Lithuania7431534321
Finland2811740-89-12
Total183161982285

July consumption by country GWh

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

25/01/24

S Australia gets OK to use diesel generators for backup

S Australia gets OK to use diesel generators for backup

Adelaide, 24 January (Argus) — Australian federal energy regulator has approved a South Australian (SA) state government bid to temporarily change regulations, ordering two diesel-fired generators in the state to remain available for back-up electricity supply. French utility Engie last year said it would mothball the 63MW Snuggery and 75MW Port Lincoln generators. The SA's Labor energy minister opposed this, and last month wrote to the Australian Energy Market Commission (AEMC) to request the Australian Energy Market Operator (Aemo) be given powers to direct this capacity into the market if supply is threatened. The rule change will be enforced until 31 March, and will help secure SA's electricity supply this summer, the AEMC said on 23 January. SA could face load-shedding during cases of reliability shortfalls, especially during extreme weather, without sufficient backup reserves. No objections were received during the fast-tracked process, the AEMC said. SA is highly dependent on renewable power such as solar and wind, especially after closing its last coal plants in the last decade. Its sole connection to the national electricity market is via links to Victoria state. The 800MW EnergyConnect electricity transmission link to New South Wales is still under construction and has been delayed until July 2027, from an original guidance of 2023. About 72pc of SA's power consumption was from renewable sources last year, with gas contributing 24pc and imports from Victoria making up 10pc, leaving the state vulnerable to outages if this connection is damaged. But backup generators are costly to maintain as cheap renewable energy floods the grid, leaving governments stuck between subsidising fossil-fuelled plants or facing politically and economically damaging interruptions to supply. By Tom Major Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

Fewer, smaller shale deals in 2025: Enverus


25/01/23
25/01/23

Fewer, smaller shale deals in 2025: Enverus

New York, 23 January (Argus) — After $300bn of consolidation in the US oil and gas industry over the past two years, deal making is set to fall in 2025 while breakeven prices for acquired inventory will likely rise, according to consultancy Enverus. The rapid pace of mergers and acquisitions targeting shale-based assets has led to many of the best targets having been snapped up. As a result, the quality of newly acquired inventory is declining, averaging a $50/bl breakeven price in 2024, up from $45/bl in 2022-23, Enverus calculates. "The pool of available remaining private equity assets is largely smaller, higher on the cost curve or both," Enverus said in its annual outlook. Yet a pressing need for scale and future of location inventory will encourage smaller producers to embark upon more deals. And improved efficiencies — such as drilling longer lateral wells — will be key in boosting economics on more marginal acreage. Mergers involving public companies will ease up in 2025 from a recent average of five a year, according to Enverus. While deals involving smaller producers may offer suppressed valuations relative to private opportunities, a potential lack of a strategic fit and agreement on future management teams may pose obstacles. By Stephen Cunningham Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

N2EX at 2-week low on storm Eowyn


25/01/23
25/01/23

N2EX at 2-week low on storm Eowyn

London, 23 January (Argus) — The UK's N2EX power spot index for tomorrow cleared at its lowest in more than two weeks owing to forecast lower demand and higher wind output, likely supporting exports to France. The N2EX day-ahead spot cleared at £95.27/MWh for tomorrow, falling from as high as £261.22/MWh for Wednesday. Hourly prices cleared at a low of £34.05/MWh between 04:00-05:00 GMT tomorrow, in settlement periods 9-11. National demand — which excludes interconnector exports, as well as station load and pumped-storage pumping — is forecast to peak at 38.8GW on Friday, down from 41.1GW forecast for today and 43.1GW for yesterday. Minimum temperatures in London Heathrow are forecast to rise to 5.4°C from just 0.8°C today and above an average of 2.9°C so far in January — 2.1°C below the 10-year norm for the period. Combined metered and embedded wind output is forecast at 14.2GW, with gale force winds expected in parts of the UK as storm Eowyn hits the country. UK weather agency the Met Office has issued a red weather warning for Northern Ireland and parts of Scotland tomorrow. Wind output is expected to rise sharply from just 11.4GW expected for today and well above Wednesday. Output on Wednesday was just 836MW, the lowest since March 2022. Higher wind output is likely to support exports to continental markets, particularly during off-peak hours, while day-ahead cross-border capacity auctions indicate the UK is due to shift to being a net exporter with France across the whole day. Allocated capacity in the GB-France direction on the IFA and IFA2 links — each with 1GW available — cleared at implied premiums to the reverse direction of €26.70/MWh (£22.53/MWh) and €24.02/MWh (£20.27/MWh), respectively. The UK was a net exporter to France for much of last week, with net exports averaging 750MW on 13-18 January, when wind output in the UK averaged 10.6GW. Outages at the 1GW Eleclink with France and 1GW BritNed with the Netherlands, along with a 700MW curtailment at the 1.4GW Viking Link with Denmark, remain in place. By Timothy Santonastaso n2EX daily £/MWh Wind output vs UK-FR flows GW Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

Sardinian RES outlook bleak for 2030


25/01/23
25/01/23

Sardinian RES outlook bleak for 2030

London, 23 January (Argus) — The Italian island of Sardinia introduced restrictive measures on new renewable developments at the end of last year, probably exacerbating the projected gap between installed capacity and 2030 climate targets. Sardinia had 3.6GW of installed renewable capacity as of December, data from Italian transmission system operator (TSO) Terna show, with solar accounting for almost half. But the island will need this to rise to 6.2GW by 2030 to meet climate targets laid out in Italy's national energy and climate plan (NECP). Renewable capacity increased by around 360MW on the year in 2024. If additions continued at the same pace over the next six years, the island would fall short of targets by around 400MW. But the pace may even slow owing to Sardinia's prohibitive legal framework for new renewable developments. Terna as of last month had received around 770 requests to connect solar, onshore and offshore wind plants to Sardinia's grid for a total capacity of 52GW, well above what Rome has targeted for the island. But shortly after the Italian government approved a renewables support scheme aimed at speeding up project authorisations, Sardinia — an autonomous region — introduced an 18-month moratorium on the construction of renewable plants. This was followed by Sardinia's council limiting suitable areas for renewable plants to just 1pc of its territory, mainly by appealing to national laws on landscape protection. Under its NECP, Italy will need to reach 131.3GW of renewable capacity by 2030 to be in line with EU climate targets. The country's renewable capacity was 76.6GW as of December, with combined solar, wind and hydro generation accounting for just over 50pc of the power mix in 2024. Italy is also due to wean off coal-fired generation this year, with Sardinia's phase-out extended to 2028 owing to the island's heavy reliance on coal for power generation. Sardinia currently has two operational coal-fired plants — Italian utility Enel's 590MW Sulcis and Czech firm EP Produzione's 600MW Fiume Santo. "Based on historical data, it will not be possible to phase out coal by 2028," environmental group Legambiente president Marta Battaglia told Argus. Battaglia raised concerns about the legislation's lack of clarity in defining suitable areas for renewables, and whether projects that have already been approved but not yet started construction will be blocked. EP Produzione in March 2023 announced plans to replace the Fiume Santo plant with a 1GW renewable energy complex, which would include various low-carbon technologies and a combined-cycle gas turbine (CCGT) plant. A 100MW battery energy and storage project and a 10MW solar unit in the energy park have already been approved, but EP Produzione is currently examining the decree on suitable areas to check if these projects qualify under the new criteria, the company told Argus . Sardinia's transition to renewable sources also depends on a reliable grid connection to the Italian mainland. The island is currently connected via the 300MW Sacoi2 — which also links to the French island of Corsica — and 1GW Sapei sub-sea cables. The Italian and French TSOs recently reached a cost-sharing agreement to increase Sacoi2 to 400MW by 2029. And the European Investment Bank is supporting Terna in developing the 1GW Tyrrhenian link between Sardinia, Sicily and the Italian mainland, which is expected to be operational by 2028. Sardinia is typically a net exporter to Italy's mainland, with an average of almost 340MW directed to the central-south zone over 2024. This is owed to the significantly higher power demand in the central-south zone at 5.6GW in 2024 — with a gap of 2.5GW between demand and supply — compared with Sardinia's demand at 970MW and output at 1.4GW. Assuming the island's power demand will rise to 1.3GW by 2030 — as outlined by Terna in a possible scenario — and renewable capacity will increase at recent rates over the coming years, flows may switch after the expected shutdown of the two remaining coal-fired plants in 2028. Sardinian renewable generation would fail to meet around 425MW of its demand, assuming the average load factor recorded in recent years. By Ilenia Reale Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

Q&A: EU power imports likely subject to ETS from 2026


25/01/23
25/01/23

Q&A: EU power imports likely subject to ETS from 2026

London, 23 January (Argus) — Power exports from EU-led regulatory body Energy Community constituent states will likely be subject to a carbon cost equivalent to the EU ETS price beginning in 2026 as part of the carbon border adjustment mechanism (CBAM), as states have so far not met the requirements which would grant them exemption from CBAM until 2030, secretariat director Artur Lorkowski told Argus in a recent interview. Edited highlights follow. CBAM is a transformative EU policy designed to equalise carbon costs for embedded emissions in goods, including electricity, produced outside the EU. However the EU's neighbourhood, particularly the Energy Community contracting parties, holds a unique status. These countries are actively aligning their legal and regulatory frameworks with the EU, a critical step towards EU accession. Unlike other regions they are already implementing core EU energy and climate policies, setting them on a path toward full Union membership. This distinct trajectory sets them apart from the rest of the world in terms of policy development. Is there any path to CBAM exemption without full day-ahead and intraday market coupling? Market coupling is the main desired outcome of the overall energy market integration journey that contracting parties started 20 years ago when — together with the EU — they established the Energy Community. This priority precedes the concept of CBAM, and remains essential for accelerating their integration into the EU energy market ahead of accession. Achieving market coupling, particularly in the day-ahead market, is critical to delivering competitive prices for consumers while fostering low-carbon technologies. The CBAM regulation makes market coupling a precondition for an exemption from CBAM for electricity. As EU law, this must be implemented. However greater clarity is needed on the specific criteria to determine when a third country may be considered as having "an electricity market which is integrated with the Union internal market for electricity through market coupling". Has a mechanism been determined to separate transit flows from export volumes, and in which way would CBAM be applied? Contracting parties, particularly in the western Balkans, experience significant electricity flows as a result of trades between EU member states crossing their territories due to their geographical location, transmission system characteristics, available capacities and advanced market reforms. These flows, often labelled "transit," are a natural outcome of a properly-functioning electricity market and may involve several title transfers before reaching their destination. Unlike the straightforward transit of physical goods, such as cement or aluminium, which are merely transported from one point to another, these electricity flows reflect the integrated and dynamic nature of interconnected electricity markets. The European Commission is currently reviewing the implementation of CBAM during its transitional period, which ends this year. I hope this stocktaking will help to find a solution to how the principles of CBAM can be maintained in a way that does not impede the normal functioning and further development of interconnected electricity markets between contracting parties and member states. By what date must Energy community constituent countries meet these requirements in order to be exempt on 1 January? To meet the market coupling precondition, contracting parties must fully transpose and implement the Electricity Integration Package with their transmission system operators (TSOs) and nominated electricity market operators (Nemos) becoming operational parties in market coupling. Additionally, they must satisfy the criteria in Article 2(7) of the CBAM Regulation. Even after meeting these requirements, an administrative process is needed on the EU side to list them in the CBAM Regulation's exempted jurisdictions annex. With the slow progress in transposing and implementing the Electricity Integration Package, it is highly probable that all parties will fall under CBAM from 1 January 2026. Consequently, electricity from the region will face a carbon cost equivalent to the EU ETS price upon import into the EU, leading to substantial changes in arbitrage opportunities and trading patterns. Irish MP Barry Andrews said he "doubted" that CBAM would occur during the EC parliamentary plenum, and brought up the costs of decoupling that Ireland has experienced after the UK exited the EU. Do you believe EU countries that neighbour the western Balkans could experience higher prices if CBAM is applied? While it's challenging to predict specific outcomes, it's important to note that prices are influenced by various market dynamics, including supply and demand fluctuations, carbon pricing mechanisms and regional integration progress. The application of CBAM could create price adjustments, but these will ultimately depend on how markets adapt and respond to the new regulatory environment. Some EC constituents, such as Moldova, are perennial importers. Will CBAM be applied to the occasional export flows despite their net importing positions? The CBAM Regulation specifies that electricity imports are measured per border in time intervals no longer than one hour, with no deductions allowed for exports or transit during the same hour. As a result, all electricity exports to EU member states are subject to CBAM. However it remains unclear whether inter-TSO flows or technical flows required for system balancing will be classified as exports under CBAM, which requires further clarification. By Annemarie Pettinato Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

Generic Hero Banner

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more