Battery storage stands out in Japan clean power auction

  • Spanish Market: Battery materials, Electricity
  • 02/05/24

Japan's first auction for long-term zero emissions power capacity has attracted strong bidding interest with a plan to install battery storage, as investment in the power storage system is gaining momentum in line with expanded use of fluctuating renewable energy sources.

Japan launched the clean power auction system from the April 2023-March 2024 fiscal year, aiming to spur investment in clean power sources by securing funding for fixed costs in advance to drive the country's decarbonisation by 2050.

The first auction, which was held in January, has awarded 1.1GW capacity for battery storage, or 27pc of total contract capacity for clean power sources, excluding gas-fired generation that has been temporally included in the auction system to help ensure stable power supplies, nationwide transmission system operator Organisation for Cross-regional Co-ordination of Transmission Operator (Occto), which manages the auction, said on 26 April.

Bidding capacity for battery storage totalled around 4.6GW, the highest volume among any other clean power sources. This means the contract ratio for storage batteries was 24pc compared with the 100pc ratio for ammonia co-firing, hydrogen co-firing, biomass dedicated and nuclear capacity, along with gas-fired capacity.

Awarded capacity for battery storage as well as pumping-up electric power facilities reached 1.67GW, exceeding the 1GW sought by the auction.

Japan has secured a total of 9.77GW of net zero capacity through the 2023-24 auction. Contract volumes covered 1.3GW of nuclear, 199MW biomass, 577MW of pumping-up electric power, 770MW for ammonia co-firing and 55.3MW hydrogen co-firing, as well as 1.1GW of battery storage. This also included 5.76GW of gas-fired projects.

All winners under the auction can generally receive the money for 20 years through Occto, which collect money from the country's power retailers, although they need to refund 90pc of other revenue. The first auction saw total funding of ¥233.6bn/yr ($1.51bn) for decarbonisation power sources and ¥176.6bn/yr for gas-fired capacity.

Japan's battery requirements are expected to continue rising, with uncertainty over future nuclear availability likely to spur Tokyo to accelerate the roll-out of renewable energy to meet a 46pc greenhouse gas emissions reduction by 2030-31 against 2013-14 levels — a target still far above the 23pc recorded in 2022-23. Japan will need to install 38-41GW of renewable capacity, nearly triple actual output of 14GW in 2019.

Japan is looking to establish lithium-ion battery production capacity of 150GWh/yr domestically and 600GWh/yr globally by 2030. The trade and industry ministry projects the latter target will require 380,000 t/yr of lithium, 310,000 t/yr of nickel, 600,000 t/yr of graphite, 60,000 t/yr of cobalt and 50,000 t/yr of manganese.


Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

20/05/24

Japan’s FEPC calls for clearer nuclear policy stance

Japan’s FEPC calls for clearer nuclear policy stance

Osaka, 20 May (Argus) — Japan's Federation of Electric Power Companies (FEPC) has called for a clarification of the country's nuclear power policy, to ensure stable electricity supply and alignment with its net zero emissions goal. The call comes as the government reviews its basic energy policy , which was formulated in 2021 and calls for the reduction of dependence on nuclear reactors as much as possible. But Japan's guidelines for green transformation, which was agreed in February 2023, states that Japan should make the most of existing nuclear reactors. Tokyo should clearly state in its new energy policy that it is necessary to not only restart existing nuclear reactors, but also build new reactors, said FEPC chairman Kingo Hayashi on 17 May. Hayashi is also the president of utility Chubu Electric Power. Hayashi emphasised that to utilise reactors, it would be necessary to have discussions regarding financial support, policy measures that would help ensure cost recovery, address back-end issues in the nuclear fuel cycle and conduct a review of nuclear damage compensation law. Japan's current basic energy policy is targeted for the April 2030-March 2031 fiscal year, when the country's greenhouse gas (GHG) emissions is forecast to fall by 46pc from 2013-14 levels. To achieve this, the power mix in the policy set the nuclear ratio at 20-22pc, as well as 36-38pc from renewables, 41pc from thermal fuels and 1pc from hydrogen and ammonia. Japan typically reviews the country's basic energy policy every three years. Nuclear, as well as renewables, would be necessary to reduce Japan's GHG emissions, although thermal power units would still play a key role in addressing power shortages. But Japan has faced challenges in restarting the country's reactors following safety concerns after the 2011 Fukushima nuclear disaster, with only 12 reactors currently operational. Japan's nuclear generation in 2023 totalled 77TWh, which accounted for just 9pc of total power output. Tokyo has made efforts to promote the use of reactors, after the current basic energy policy was introduced in 2021. The trade and industry ministry (Meti) has updated its nuclear policy, by allowing nuclear power operators to continue using reactors beyond their maximum lifespan of 60 years by excluding a safety scrutiny period in the wake of the 2011 Fukushima nuclear disaster. This could advance the discussion on Japan's nuclear stance, especially if the new basic energy policy includes more supportive regulations. The trade and industry ministry started discussions to review the energy policy on 15 May, aiming to revise it by the end of this fiscal year. It is still unclear what year it is targeting and what ratio will be set for each power source in the new policy. But the deliberation would form a key part of efforts to update the GHG emissions reduction goal, ahead of the submission of the country's new nationally determined contribution in 2025, with a timeframe for implementation until 2035. By Motoko Hasegawa Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Japan’s Jera to handle 35mn t/yr LNG until FY2035-36


17/05/24
17/05/24

Japan’s Jera to handle 35mn t/yr LNG until FY2035-36

Osaka, 17 May (Argus) — Japan's largest LNG importer Jera plans to maintain its LNG handling volumes at no less than 35mn t/yr until the April 2035-March 2036 fiscal year. Rising renewable power supplies and the possible return of more nuclear reactors are likely to pressure LNG demand from Japan's power sector. Jera consumed 23mn t of LNG in 2023-24, down by 3pc on the year, although it handled 35mn t through its global operations during the same year. But Jera needs to secure sufficient LNG supplies to adjust for imbalances in electricity supplies and ensure power security, through more flexible operations. It is also looking to further promote LNG along with renewable electricity in Asian countries, while helping to reduce their dependence on coal- and oil-fired power generators. The 2035 target for LNG is part of Jera's three pillars of strategic focus, along with renewables as well as hydrogen and ammonia , which was announced on 16 May to spur decarbonisation towards its 2050 net zero emissions goal. The company plans to invest ¥5 trillion ($32bn) for these three areas over 2024-36. Jera also aims to retire all supercritical or less efficient coal-fired units by 2030-31 . This would help achieve the company's target of cutting CO2 emissions from its domestic business by at least 60pc against 2013-14 levels by 2035-36. By Motoko Hasegawa Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Biomass start-ups lift Japan's Renova April power sales


17/05/24
17/05/24

Biomass start-ups lift Japan's Renova April power sales

Tokyo, 17 May (Argus) — Japanese renewable power developer Renova's electricity sales doubled on the year in April, following the start-up of three biomass power plants in the past six months. Renova sold 199,601MWh of electricity — including solar, biomass and geothermal — in April, double the 99,857MWh a year earlier, the company announced on 13 May. The 75MW Sendai Gamo plant in northeastern Miyagi prefecture started operations in November 2023 and produced 40,753MWh in April. The 74.8MW Tokushima Tsuda plant in western Tokushima prefecture, which was commissioned in December 2023, generated 10,870MWh in April. The 75MW Ishinomaki Hibarino plant in Miyagi began normal runs in March and supplied 49,495MWh in April. Renova plans to add 124.9MW biomass-fired capacity in the April 2024-March 2025 fiscal year, with the 75MW Omaezaki plant in central Shizuoka city scheduled to begin commercial operations in July, followed by the 49.9MW Karatsu plant in southern Saga city in December. Omaezaki is currently conducting trial runs and Karatsu is under construction. The additions will increase Renova's biomass-fired capacity to 445MW. By Takeshi Maeda Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Trade curbs spur Chinese battery firms to look overseas


17/05/24
17/05/24

Trade curbs spur Chinese battery firms to look overseas

Beijing, 17 May (Argus) — An increasing number of Chinese battery firms have accelerated their expansions outside China, to meet buoyant overseas demand and to tackle escalating geopolitical curbs. These curbs include the US' newly announced tariff hikes on China's electric vehicles (EVs) and batteries from 2024 or 2026, and the EU's potential punitive duties on battery EVs originating from China. The US' Inflation Reduction Act (IRA) and the EU's Critical Raw Material Act have also prompted many Chinese battery material producers to step up their overseas expansions. China's battery material manufacturer Hunan Zhongke Electric has unveiled a plan to invest no more than 5bn yuan ($692mn) to build a production plant for battery anode material in Morocco, in which some other Chinese firms have also invested in similar projects. The plant has a designed capacity of 100,000 t/yr and will be developed in two phases with 50,000 t/yr each. The firm aims to complete plant construction for each phase in 24 months. Zhongke is a major battery anode material producer in China with 210,000 t/yr of capacity as of the end of 2023. Its output of anode materials rose to 143,513t in 2023, up by 14pc from 125,460t a year earlier, driven by the country's rising EV sales. It aims to expand overseas sales in the coming years. Major Chinese copper producer Zhejiang Hailiang also outlined a plan to build a 25,000 t/yr production plant for copper foil used in lithium-ion batteries in Morocco. Construction will take 36 months. "The layout of the Morocco project can help us penetrate into the European and US markets as soon as possible as exports from Morocco are duty free to these markets," Hailiang said. "This will help us avoid any international trade barrier." Morocco is one of the main destinations for Chinese companies to invest in and build overseas battery component plants given its abundant resources for phosphate, a main chemical compound in a lithium iron phosphate battery, and its free trade agreement (FTA) with the US. It is also a major cobalt metal producing country outside China, with cobalt being a critical mineral used in the manufacturing of lithium-ion batteries. Major Chinese battery material producer EVE Energy is on track to develop a production project for energy storage batteries in Malaysia. It will establish a subsidiary EVE Energy Malaysia Energy Storage to develop this project to meet Malaysia's energy storage battery demand, although it has not disclosed the capacity, construction schedules and launch dates. The plant is the second phase of EVE's new energy products development in Malaysia. It in August 2023 started building a plant for cylindrical batteries mainly used in electric two-wheelers and electric tools in the southeast Asian country. The firm said the US' new tariff hikes will not affect its business because it had planned the Malaysia projects for consumer batteries and energy storage in advance, and these projects will support shipments to US consumers by 2026. New US tariff hikes US president Joe Biden's administration announced on 14 May that the tariff on lithium-ion EV batteries will immediately increase to 25pc, while the tariff on all other lithium-ion batteries is set to increase to 25pc in 2026, both from the current rate of 7.5pc. This is likely to trigger more Chinese battery companies to increase their overseas investments to avoid the tax, according to industry participants. The US' tariff hikes have drawn strong criticism from China. "Politicising and instrumenting economic and trade issues is typical political manipulation," said the country's ministry of commerce. "The Section 301 tariff hikes goes against President Biden's promise of 'not seeking to contain China's development' or 'not seeking to break the chain of decoupling from China'. The US should immediately correct its wrongful actions and cancel the tariffs. China will take 'resolute" measures to safeguard its own rights and interests'." Chinese battery firms' investments in Morocco Company Products Capacity Launch dates CNGR CAM precursors, LFP, black mass 120,000 t/yr, 60,000 t/yr, 30,000 t/yr 4Q, 2024 BTR CAM 50,000 t/yr N/A Hunan Zhongke Anode material 100,000 t/yr in 24 months Huayou Cobalt/LG LFP 50,000 t/yr in 2026 Huayou Cobalt/LG Lithium salts 52,000 t/yr N/A Sichuan Yahua/LG Lithium hydroxide N/A N/A Hailiang Li-ion battery copper foil 25,000 t/yr in 36 months Source: Company releases Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Mexican power outages enter fourth day


10/05/24
10/05/24

Mexican power outages enter fourth day

Mexico City, 10 May (Argus) — Mexican power grid operator Cenace issued its fourth consecutive day of operating alerts amid the heatwave gripping the country. Net electricity demand reached 47,321MW early today, with deployed electricity capacity slightly below at 47,233 MW, according to Cenace. Since 7 May, Cenace has declared emergency operating alerts as demand exceeded generation capacity during peak evening hours, prompting the grid operator to preemptively cut electricity supply across different states to maintain grid integrity. Power outages have lasted up to several hours in Mexico City and in major industrial states as power demand has outstripped supply by up to 1,000MW. Peak demand this week hit 49,000MW, just below last year's historic peak of 53,000MW during atypical temperatures in June. "We are very concerned about the unprecedented outages detected across 21 states, a situation that affects the normal functioning of Mexican companies," national business chamber Coparmex said. Peak electricity demand typically rises in June-July but temperatures this week have risen as high as 48°C (118° F) across some states. Mexico City reported a record high of 34.3°C on 9 May and high temperatures are forecast to continue into next week, Mexico's national weather service said. The inability of Mexico's grid to respond to increased demand is because of insufficient power generation capacity, non-profit think-tank the Mexican institute for competitiveness (Imco) said this week. "Despite the energy ministry's forecast that 22,000MW of new power capacity would enter service by 2026, only 1,483MW had entered service as of 2022" since late 2018, Imco said. President Andres Manuel Lopez Obrador's administration pledged to build new generation capacity, including five gas-fired, combined-cycle plants, but recognized this week that delays had contributed to the power outages. "We have an electricity generation deficit because some of the combined-cycle plants were delayed, but we are working on it and it will soon be resolved," Lopez Obrador said on 9 May. Lopez Obrador's government has also curtailed private sector power development during his administration. Mexico needs to upgrade and expand its transmission network, industry associations say. "In order to resolve this problem, we believe that a reopening of the electricity market to the private sector is imperative," Mexico's wind energy association, Amdee, said. Mexico has 87,130MW of installed capacity, with 39.5pc from combined-cycle gas-fired power plants and 31pc in renewable power, including wind, solar, hydroelectric, geothermal and biomass, according to the latest statistics from the energy ministry. By Rebecca Conan Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more