Schlumberger presses to collect Ecuador oil fees

  • : Crude oil
  • 17/03/24

Oil field services giant Schlumberger is pressing Ecuador to pay more than $1.1bn in overdue fees for oil production at the mature Shushufindi field where output has been cut to comply with an Opec-related cap.

The arrears are "an issue that is causing our company considerable financial stress," according to a letter sent by the firm's chief executive Paal Kibsgaard to outgoing president Rafael Correa, asking for his "personal help" to unblock the payments.

"In this regard, Ecuador now represents approximately 12pc of Schlumberger's accounts receivable balance at December 31, 2016," according to the 14 March letter seen by Argus.

Ecuador's finance minister Patricio Rivera told Argus that Quito is negotiating with Schlumberger, seeking an agreement to pay the debt, but declined to offer further details.

In the letter, Kibsgaard also complains that state-owned PetroAmazonas "has unilaterally decided to reduce production in the Shushufindi field by up to 10,000 b/d during February 2017, putting further pressure on our financial results on top of reducing financial proceeds to the Ecuadorian state".

In 2012, a consortium made up of Schlumberger and Argentina's Tecpetrol signed a 15-year enhanced recovery contract with PetroAmazonas for Shushufindi, where production jumped from 45,153 b/d to some 80,000 b/d by the end of 2016.

After that, PetroAmazonas reduced output at Shushufindi, one of Ecuador's largest and oldest fields, to comply with a six-month Opec and non-Opec price stabilization agreement engineered in December 2016. Production at the field dropped to 69,000 b/d in the first three weeks of March, according to PetroAmazonas data.

Tiny Opec member Ecuador pledged to limit total crude production to 522,000 b/d for six months starting in January, down from an average 548,000 b/d in 2016.

In addition to the Shushufindi partnership, in December 2015 PetroAmazonas and Schlumberger signed a 20-year contract to increase production at the 70,000 b/d Auca oil field in the Amazon district. Schlumberger pledged to spend $4.9bn over the next two decades to boost Auca production by 20,000 b/d. The company agreed to receive a $26/bl fee for existing and new production.

As part of the Auca agreement, the oil services firm made an initial $1bn capital outlay, and planned to spend an additional $2.1bn in the first nine years of the contract, including $1.1bn in 2016-19, and $1.8bn to cover operating costs at the field over the life of the contract.

"We have invested more than $3bn in rejuvenating both the Shushufindi and Auca fields, pushing production to new levels," Kibsgaard says in the letter.

Ecuador's debt "has resulted in us having to raise additional external borrowings to finance our operations and fulfill our various commitments to the state and other stakeholders," according to the same document.

A Schlumberger executive told Argus that PetroAmazonas stopped paying the fees some 18 months ago.

Schlumberger's chief executive warned Correa that, although it "fully understands that the low oil price and recent natural disaster have put considerable strain on Ecuador's economy," the situation is "obviously not sustainable in the long run."

PetroAmazonas is currently focusing on a plan to reduce capital expenditures and investments. Hard hit by the 2014 oil price collapse, "in 2016 drilling was almost null," chief executive Alex Galarraga said at a conference in Quito this week. Output did not fall mainly because of the development of the controversial ITT heavy crude block.

PetroAmazonas started developing 1.7bn bl ITT last year. The complex lies in an environmentally sensitive part of Ecuador. Production at Tiputini, the first of the three ITT fields to be tapped, started at around 20,000 b/d in September 2016, reached 44,000 b/d in the first half of March and will ramp up to 60,000 b/d by April, Galarraga told Argus.

Tambococha will start production by October at 20,000 b/d and reach 70,000 b/d by mid-2018. Despite its Opec commitment, Ecuador will not consider slowing down the ITT's development, according to strategic sectors minister Augusto Espin.

PetroAmazonas is holding back its overall production to 430,000 b/d in the first half of the year to comply with its Opec quota, with reductions coming from mature fields, such as Shushufindi, Libertador and Sacha. The company plans to increase output to 450,000 b/d in the second semester.

Espin has said that Ecuador could seek an exemption for ITT if Opec decides to extend the output restraints for the rest of 2017.


Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more