Barge delays at Algiers lock near New Orleans

  • : Agriculture, Chemicals, Coal, Coking coal, Crude oil, Metals, Petroleum coke
  • 24/04/24

Barges are facing lengthy delays at the Algiers lock near New Orleans as vessels reroute around closures at the Port Allen lock and the Algiers Canal.

Delays at the Algiers Lock —at the interconnection of the Mississippi River and the Gulf Intracoastal Waterway— have reached around 37 hours in the past day, according to the US Army Corps of Engineers' lock report. Around 50 vessels are waiting to cross the Algiers lock.

Another 70 vessels were waiting at the nearby Harvey lock with a six-hour wait in the past day.

The closure at Port Allen lock has spurred the delays, causing vessels to reroute through the Algiers lock. The Port Allen lock is expected to reopen on 28 April, which should relieve pressure on the Algiers lock.

Some traffic has been rerouted through the nearby Harvey lock since the Algiers Canal was closed by a collapsed powerline, the US Coast Guard said. The powerline fell on two barges, but no injuries or damages were reported. The wire is being removed by energy company Entergy.

The canal is anticipated to reopen at midnight on 25 April.


Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more