US midstream company EnLink expects the addition of new processing capacity to fill its 120,000 b/d Cajun-Sibon pipeline system in Louisiana by the second quarter of 2017.
During the third quarter, EnLink expanded the processing capacity at its Chisholm I plant in central Oklahoma from 100mn cf/d to 120mn cf/d and began construction of the Chisholm II plant.
The addition of Chisholm II will increase the company's processing capacity in central Oklahoma to 800mn cf/d, up from 350mn cf/d in 2015.
EnLink said it could add two more gas processing plants in Oklahoma in the next two to three years.