German coal plants show litte demand to restock

  • Spanish Market: Electricity
  • 09/05/19

Uptake of coal deliveries from the Amsterdam-Rotterdam-Antwerp (ARA) trading hub to south Germany continued to be lacklustre this week as the call on German coal-fired generation remains limited with the exception of sporadic increases in power sector coal burn.

This suggests that German coal plant operators might be unable to take deliveries at relaxed barge rates because their stocks are amply filled, which in turn exposes them to the risk of another dry summer period.

Water levels on the Rhine have been in range of 155-185cm at the Kaub measuring point since the end of April, data from water and shipping agency WSV show.

Kaub is the narrowest point barges travelling to south Germany have to pass. Plant operators typically pay a surcharge on top of the standard barge rate of €5/t from ARA to the south German city of Mannheim once Kaub levels move below 180cm, while levels well above that threshold can lower rates. With Rhine levels at Kaub neither significantly below nor above 180cm since the end of April, barge rates have been fairly stable.

Barge rates for that journey have not exceeded €8/t since the end of February. And coal deliveries booked from ARA to Mannheim cost around €5.70/t yesterday, when WSV put the Kaub level at 166cm, one barge operator said.

But demand for booking large vessels which can carry up to 4,500-5,000/t from ARA to south Germany continues to be lower than usual, the barge operator said. Typically, barge rates around the standard tariff provide an incentive to replenish stocks at plant sites to ease the need to take deliveries at times of lower water levels and subsequently higher transport costs.

But while German power sector coal burn has recovered this week to move well above daily average output in March and April, it remains well below the five-year average for May. Coal-fired power generation reached the lowest level for any month at least since the start of this decade in March, at a daily average of 4.8GW, as record-high wind power generation increased the share of renewable energy generation in the German electricity generation mix to a new all-time high, data from German research institute Fraunhofer Ise show. In April, coal-fired generation increased just slightly to 5.3GW, based on the Fraunhofer Ise data.

Coal vs gas

With wind power generation trailing behind output in recent weeks, the share of combined renewable energy generation — which includes output from hydro, biomass, wind and solar photovoltaic capacity — in the German electricity generation mix fell to an average of 46pc so far this week, compared with 54pc last week and 49.4pc across April, according to the Fraunhofer Ise data.

Based on price signals alone, the German short-term market has been deeply in coal-to-gas fuel switch territory since mid-April. Working day-ahead clean spark spreads for gas plants with efficiency of 55pc or higher have been consistently above clean dark spreads for coal-fired plants with efficiency of 42pc or lower. But a number of efficient gas-fired units have been off line for maintenance since the end of April.

This allowed coal-fired power generation to rise to a daily average of 8.3GW on 6-8 May from 4.9GW the previous week, while gas-fired generation rose to just 4.2GW on average so far this week from 3.1GW in week 18, which covered 29 April to 5 May, Fraunhofer data show. But with the exception of last year, German coal-fired power generation in May was higher and held above 10GW in most years, while gas-fired power generation hovered below 4GW in May 2013-18 with the exception of May 2017.

And the rise in coal-fired power generation early this week has so far failed to result in rising demand for taking coal from ARA to German plant sites.

Implications for H2

This suggests that coal stocks at power plants continue to be amply filled, with the result of German utilities being unable to benefit from barge rates hovering around the standard tariff.

In the third quarter of last year, barge rates from ARA to Mannheim rose to a high of €21/t in September after water levels at Kaub fell to as low as 60cm.

At the time, gas-fired generation had been largely non-competitive with coal burn because of strong injection demand into storage as the latter had been depleted following the 2017-18 winter season. This meant that coal burn was deeply embedded in the German generation mix in the third quarter of last year even as barge rates rose, with German forward contracts and the day-ahead market delivering over the period finding support from strong demand for power sector coal burn and the need for gas burn to meet domestic and cross-border demand.

At prevailing prices, the situation is reversed this summer. The third-quarter NCG gas hub contract yesterday closed comfortably below the level at which a 55pc-efficent gas plant would be competitive with a 42pc-efficient coal plant, and just slightly above the level at which a 55pc-efficient gas-fired unit would be able to compete with a 46pc-efficient coal-fired plant. The latter is the highest efficiency for hard coal power plants in Germany. This pushes older German coal-fired to the margin of the expected German merit order in the third quarter. Low river levels and subsequent higher barge rates would then have less of an impact on the German wholesale power price should coal-to-gas fuel switching remain firm in delivery in the third quarter, as low load factors for coal plants would translate into continued limited demand to replenish stocks.

But a repeat of a sustained period of dry weather conditions could have a more material impact on wholesale power prices in the fourth quarter when coal-to-gas fuel switch potential eases. In the fourth quarter of last year, barge rates for delivery from ARA to Mannheim hit a high of €41/t, which added €14.49/MWh to the operational costs of a 40pc-efficient coal plant. The standard tariff at €5/t adds just €1.56/MWh to the operational costs of such units.

German Q3 fuel-switch prices, gas vs coal €/MWh

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

17/05/24

Japan’s Jera to handle 35mn t/yr LNG until FY2035-36

Japan’s Jera to handle 35mn t/yr LNG until FY2035-36

Osaka, 17 May (Argus) — Japan's largest LNG importer Jera plans to maintain its LNG handling volumes at no less than 35mn t/yr until the April 2035-March 2036 fiscal year. Rising renewable power supplies and the possible return of more nuclear reactors are likely to pressure LNG demand from Japan's power sector. Jera consumed 23mn t of LNG in 2023-24, down by 3pc on the year, although it handled 35mn t through its global operations during the same year. But Jera needs to secure sufficient LNG supplies to adjust for imbalances in electricity supplies and ensure power security, through more flexible operations. It is also looking to further promote LNG along with renewable electricity in Asian countries, while helping to reduce their dependence on coal- and oil-fired power generators. The 2035 target for LNG is part of Jera's three pillars of strategic focus, along with renewables as well as hydrogen and ammonia , which was announced on 16 May to spur decarbonisation towards its 2050 net zero emissions goal. The company plans to invest ¥5 trillion ($32bn) for these three areas over 2024-36. Jera also aims to retire all supercritical or less efficient coal-fired units by 2030-31 . This would help achieve the company's target of cutting CO2 emissions from its domestic business by at least 60pc against 2013-14 levels by 2035-36. By Motoko Hasegawa Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Biomass start-ups lift Japan's Renova April power sales


17/05/24
17/05/24

Biomass start-ups lift Japan's Renova April power sales

Tokyo, 17 May (Argus) — Japanese renewable power developer Renova's electricity sales doubled on the year in April, following the start-up of three biomass power plants in the past six months. Renova sold 199,601MWh of electricity — including solar, biomass and geothermal — in April, double the 99,857MWh a year earlier, the company announced on 13 May. The 75MW Sendai Gamo plant in northeastern Miyagi prefecture started operations in November 2023 and produced 40,753MWh in April. The 74.8MW Tokushima Tsuda plant in western Tokushima prefecture, which was commissioned in December 2023, generated 10,870MWh in April. The 75MW Ishinomaki Hibarino plant in Miyagi began normal runs in March and supplied 49,495MWh in April. Renova plans to add 124.9MW biomass-fired capacity in the April 2024-March 2025 fiscal year, with the 75MW Omaezaki plant in central Shizuoka city scheduled to begin commercial operations in July, followed by the 49.9MW Karatsu plant in southern Saga city in December. Omaezaki is currently conducting trial runs and Karatsu is under construction. The additions will increase Renova's biomass-fired capacity to 445MW. By Takeshi Maeda Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Mexican power outages enter fourth day


10/05/24
10/05/24

Mexican power outages enter fourth day

Mexico City, 10 May (Argus) — Mexican power grid operator Cenace issued its fourth consecutive day of operating alerts amid the heatwave gripping the country. Net electricity demand reached 47,321MW early today, with deployed electricity capacity slightly below at 47,233 MW, according to Cenace. Since 7 May, Cenace has declared emergency operating alerts as demand exceeded generation capacity during peak evening hours, prompting the grid operator to preemptively cut electricity supply across different states to maintain grid integrity. Power outages have lasted up to several hours in Mexico City and in major industrial states as power demand has outstripped supply by up to 1,000MW. Peak demand this week hit 49,000MW, just below last year's historic peak of 53,000MW during atypical temperatures in June. "We are very concerned about the unprecedented outages detected across 21 states, a situation that affects the normal functioning of Mexican companies," national business chamber Coparmex said. Peak electricity demand typically rises in June-July but temperatures this week have risen as high as 48°C (118° F) across some states. Mexico City reported a record high of 34.3°C on 9 May and high temperatures are forecast to continue into next week, Mexico's national weather service said. The inability of Mexico's grid to respond to increased demand is because of insufficient power generation capacity, non-profit think-tank the Mexican institute for competitiveness (Imco) said this week. "Despite the energy ministry's forecast that 22,000MW of new power capacity would enter service by 2026, only 1,483MW had entered service as of 2022" since late 2018, Imco said. President Andres Manuel Lopez Obrador's administration pledged to build new generation capacity, including five gas-fired, combined-cycle plants, but recognized this week that delays had contributed to the power outages. "We have an electricity generation deficit because some of the combined-cycle plants were delayed, but we are working on it and it will soon be resolved," Lopez Obrador said on 9 May. Lopez Obrador's government has also curtailed private sector power development during his administration. Mexico needs to upgrade and expand its transmission network, industry associations say. "In order to resolve this problem, we believe that a reopening of the electricity market to the private sector is imperative," Mexico's wind energy association, Amdee, said. Mexico has 87,130MW of installed capacity, with 39.5pc from combined-cycle gas-fired power plants and 31pc in renewable power, including wind, solar, hydroelectric, geothermal and biomass, according to the latest statistics from the energy ministry. By Rebecca Conan Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Floods stress Brazil energy sector vulnerability


10/05/24
10/05/24

Floods stress Brazil energy sector vulnerability

New York, 10 May (Argus) — Record flooding in Brazil's Rio Grande do Sul state over the past week underscores vulnerabilities in the country's energy system to extreme weather, which could also slow its pace of transition to cleaner energies. Nearly one week after record rainfall began flooding the state, power outages continue to plague it, with nearly 400,000 residents still in the dark. The flooding forced companies to suspend operations of critical infrastructure for the power sector, including three substations, 25 transmission lines, six hydroelectric plants and 11 power transformers. This led grid operator ONS to import power from Uruguay to meet domestic demand. With forecasts pointing to more rain, it is increasingly clear that it will take weeks if not months for the state to start returning to normal. The Rio Grande do Sul government estimates that the floods will cost the state R19bn ($3.6bn) . The tragedy in southern Brazil comes less than a year after a record drought struck the Amazon basin, which pushed water levels of the Amazon River and its tributaries to their lowest in 120 years. The drought reduced hydroelectric output from the region's plants and interrupted transport of fuel along key river corridors, leaving many households without power, because of the lack of diesel to operate generators used in off-grid communities. These crises highlight the country's failure to prepare for extreme weather and underscore the lack of investment in critical infrastructure, including in the energy sector. A study by the World Bank from 2023warned of the need to upgrade the country's aging infrastructure and of future power supply risks. Brazil's large hydroelectric plants have been operating for an average of 55 years, according to the study, and need investments to boost efficiency and to limit the impact of extreme weather. A total of 11 hydroelectric plants in Rio Grande do Sul are being monitored, including six that present an elevated risk of rupture, such as the 28MW 14 de Julho plant that experienced a partial rupture last week because of the heavy rains. Authorities will now need to change their focus, which has been largely on limiting the impact of dry weather on the electricity sector, especially following the 2021 droughts, that resulted in expansion of thermoelectric generation. More recently, electricity regulator Aneel has been focusing on making power distribution and transmission networks more resilient to extreme weather, especially after downed power lines resulted in extended blackouts for some 4mn consumers in the city of Sao Paulo and over 1.3mn consumers in Rio de Janeiro. The sector is working to make transmission towers more resilient to high winds. Several cities and states in Brazil have launched plans to prepare for climate change, but the bulk of these plans focus on increasing investments in renewable energy and emissions reduction. Increasingly, these plans will also need to focus on mitigating risk from floods, heat waves and landslides. Brazilian energy companies are also behind the curve in their preparations for climate change. Only 13pc of executives in the energy sector that participated in a recent survey conducted by consulting firm PwC Brasil said they have assessed the impact of climate change on their financial planning. State of climate Brazil faced 12 extreme climate events in 2023, according to the World Meteorological Association (WMO). This included a tropical cyclone that hit Rio Grande do Sul last year and affected more than 340,000 people and left nearly 50 dead. The WMO blamed the extreme climate events in Brazil on the "double-whammy of El Niño and longer-term climate change." Last year, eight Brazilian states recorded their lowest July-to-September rainfall in over 40 years, it said. Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Japan’s J-Power steps up coal-fired power phase-out


10/05/24
10/05/24

Japan’s J-Power steps up coal-fired power phase-out

Osaka, 10 May (Argus) — Japanese power producer and wholesaler J-Power is stepping up efforts to halt operations of inefficient coal-fired power plants, while pushing ahead with decarbonisation of its existing plants by using clean fuels and technology. J-Power plans to scrap the 500MW Matsushima No.1 coal-fired unit by the end of March 2025 and the 250MW Takasago No.1 and No.2 coal-fired units by 2030, according to its 2024-26 business strategy announced on 9 May. It also aims to decommission or mothball the 700MW Takehara No.3 and the 1,000MW Matsuura No.1 coal-fired units in 2030. The combined capacity of the selected five coal-fired units accounts for 32pc of J-Power's total thermal capacity of 8,412MW, all fuelled by coal. While phasing out its ageing coal-fired capacity, J-Power is looking to co-fire with fuel ammonia at the 2,100MW Tachibanawan coal-fired plant sometime after 2030 and ensure it runs on 100pc ammonia subsequently. The company plans to increase the mixture of biomass at the 600MW Takehara No.1 unit, along with the installation of a carbon capture and storage (CCS) technology after 2030. The CCS technology will be also applied to the 1,000MW Matsuura No.2 unit, which is expected to co-fire ammonia, after 2030. J-Power plans to use hydrogen at the 1,200MW Isogo plant sometime after 2035. The company is also set to deploy integrated coal gasification combined-cycle and CCS technology at the 500MW Matsushima No.2 unit and the 150MW Ishikawa No.1 and No.2 units after 2035. The company aims to cut carbon dioxide emissions from its domestic power generation by 46pc by the April 2030-March 2031 fiscal year against 2013-14 levels before achieving a net zero emissions goal by 2050. This is in line with Tokyo's emissions reduction target. The company aims to expand domestic annual renewable output by 4TWh by 2030-31 compared with 2022-23, along with decarbonising thermal capacity. Its renewable generation totalled 10.4TWh in 2023-24. Tokyo has pledged to phase out existing inefficient coal-fired capacity by 2030, which could target units with less than 42pc efficiency. The country's large-scale power producers have reduced annual power output from their inefficient coal-fired fleet by 13TWh to 103TWh in 2022-23 against 2019-20, according to a document unveiled by the trade and industry ministry on 8 May. It expects such power generation will fall further by more than 60TWh to 39.700TWh in 2030-31. Global pressure against coal-fired power generation has been growing. Energy ministers from G7 countries in late April pledged to phase out "unabated coal power generation" by 2035 or "in a timeline consistent with keeping a limit of 1.5°C temperature rise within reach, in line with countries' net zero pathways". By Motoko Hasegawa Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more