Trinidad, BP, Shell to restructure Atlantic LNG

  • Spanish Market: Natural gas
  • 03/06/19

Trinidad and Tobago agreed with BP and Shell to discuss restructuring Atlantic LNG to try to forestall the shutdown of Train 1, which represents 20pc of capacity.

BP and Shell are the Caribbean country's leading natural gas producers and top shareholders in the 14.8mn t/yr Atlantic liquefaction facility in southwestern Trinidad. The pioneering complex, which was first established in 1999, has been hamstrung by limited domestic feedstock in recent years. And a Shell-led plan to supplement domestic supply with pipeline gas imports from Venezuela starting this year fell apart amid turmoil in the neighboring country.

The decision to restructure Atlantic was reached last week in meetings in the Netherlands and the UK between the Caribbean state's prime minster Keith Rowley and executives of the two companies.

Trinidad and BP have "scheduled the continuation of negotiations … which are expected to begin in the middle of June in furtherance of specific objectives relating to the restructuring of Atlantic, acceleration of field investigation, exploration, production as well as discussions surrounding a large number of exploration and production licenses," the government and BP said.

Rowley formally signed agreements that were first reached with BP and Shell in December 2018 to increase the state's income from Atlantic's 3mn t/yr Train 1, and to extend the life of the train by five years to 2024. Train 1 began operating in 1999. "This agreement features an enhanced revenue package for the sale of LNG," the government said. Shell has not commented on this agreement.

BP said on 11 May it may close Train 1 after 2019 because of a shortage of feedstock. The UK major said its infill drilling program targeted at the train would deliver about 300mn cf/d less output than forecast.

The other three trains of the Atlantic facility will not be affected by the gas deficit, BP said at the time.

The agreement with Shell includes the extension of production-sharing contracts for several blocks operated by the company, "and which could deliver a further 300mn cf/d to help meet the shortfall from BP's infill drilling projects," the energy ministry said.

"These agreements are intended to bring some stability to the country's LNG production, given the uncertainty created by the looming shortfall in natural gas from the BP production units targeted to supply Train 1," the ministry said. The restructuring "will aim at organizing a more flexible system of gas delivery to all four trains to cover any shortfall from any source, and to allow supply arrangement to overcome the differing shareholder structures of each train."

The different ownership structure of each of the four trains has complicated feedstock allocation since Trinidad's gas production started falling around 2010. In the case of Train 1, Shell owns 46pc and BP 34pc. Trinidad's state-owned gas company NGC and China's sovereign wealth fund CIC unit Summer Soca hold 10pc apiece.

BP said it remains committed to expanding its operations in Trinidad, upstream chief executive Bernard Looney said after meeting Rowley.

"We have been the largest investor in the country's upstream sector – investing over $6bn in the last five years," he said. "In the past two years we've started up three new major upstream projects in Trinidad and recently approved the development of another two."

Trinidad's gas production has been recovering since November 2017 following a long slide from a peak of 4.3 Bcf/d in 2010, and which suppressed output of LNG, ammonia and methanol.

Gas output in February 2019 averaged 3.956 Bcf/d, up by 8.6pc from January. Production in January-February averaged 3.798 Bcf/d, 0.7pc more than a year earlier.

The increased availability of gas led the Atlantic consortium to produce 4.96mn m³ of LNG in January-February 2019, up 2pc on a year earlier, according to the energy ministry.


Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

30/04/24

Gas-fired units win Japan's clean power auction

Gas-fired units win Japan's clean power auction

Osaka, 30 April (Argus) — A planned 10 gas-fired generation units have won Japan's first long-term zero emissions power capacity auction, with the awarded capacity totalling nearly 6GW, or auction volumes sought for the first three years of the programme. Japan launched the clean power auction system from the April 2023-March 2024 fiscal year, aiming to spur investment in clean power sources by securing funding in advance to drive the country's decarbonisation towards 2050. The auction generally targets clean power sources — such as renewables, nuclear, storage battery, biomass, hydrogen and ammonia. But the scheme also applies to a new power plants burning regasified LNG as an immediate measure to ensure stable power supplies, subject to a gradual switch from gas to cleaner energy sources. The first auction held in January saw 10 new gas-fired units with a combined capacity of 5.76GW secure the funding of ¥176.6bn/yr ($1.12bn), the nationwide transmission system operator Organisation for Cross-regional Co-ordination of Transmission Operator (Occto), which manages the auction, said on 26 April. All winners can receive the money for 20 years through Occto, which collect money from the country's power retailers, although they need to refund 90pc of other revenue. Winners with a new gas-fired project should start commissioning their plants within six years and then begin refurbishment work to introduce clean fuels and technology within 10 years after commissioning. This means all the projects selected in the 2023-24 auction need to start operations by the end of 2030-31. Hokkaido Electric Power previously planned to begin operations of its Ishikariwan-Shinko No.2 gas-fired unit in December 2034 but it has advanced the start-up to 2030-31. Japan has secured a total of 9.77GW net zero capacity through the 2023-24 auction. Contract volumes include 1.3GW of nuclear, 1.1GW of storage batteries, 770MW for ammonia co-firing, 55.3MW hydrogen co-firing, 199MW biomass and 577MW of hydroelectric power projects, along with the 5.76GW of gas-fired projects. By Motoko Hasegawa Japan 2023-24 decarbonisation power capacity auction result Winner Power plant MW* Planned start-up Hokkaido Electric Power Ishikariwan-Shinko No.2 551 FY2030 Tohoku Electric Power Higashi Niigata No.6 616 FY2030 Kansai Electric Power Nanko No.1 592 FY2029 Kansai Electric Power Nanko No.2 592 FY2030 Kansai Electric Power Nanko No.3 592 FY2030 Chugoku Electric Power Yanai new No.2 464 Mar '2030 Tokyo Gas Chiba Sodegaura Power Station 605 FY2029 Osaka Gas Himeji No.3 566 FY2030 Jera Chita No.7 590 FY2029 Jera Chita No.8 590 FY2029 Total gas-fired capacity 5,756.3 Source: Occto, Argus * Sending end capacity Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

APLNG's Jan-Mar output higher: Origin


30/04/24
30/04/24

APLNG's Jan-Mar output higher: Origin

Sydney, 30 April (Argus) — The 9mn t/yr Australia Pacific LNG (APLNG) project in Queensland state produced and sold more LNG than the previous quarter and year earlier, Australian independent Origin Energy said in its January-March results. Output rose from the final quarter of 2023 because of the power failure of a vessel docked at APLNG's terminal in Gladstone harbour in late November , which prompted upstream operator Origin to cut flows to the liquefaction plant and APLNG to defer three cargoes to 2024. APLNG exported 134PJ (2.4mn t) of LNG through 34 cargoes for January-March, 8pc up from 124PJ and 32 cargoes the previous quarter and 4pc up on the 129PJ and 33 cargoes shipped in January-March 2023. Total APLNG production for July 2023-March 2024, the first three quarters of Origin's fiscal year to 30 June, was 519PJ, 4pc higher than 498PJ a year earlier, because of effective well and field optimisation activities, fewer maintenance disruptions and the continuing benefit of reducing workover backlog resulting in more wells being on line, Origin said. The terminal will take half a train of capacity off line for 12 days in June , following a two-day maintenance period in January. APLNG's domestic gas sales were 36PJ, steady on the previous quarter but higher by 24pc from the 29PJ sold a year earlier. Gas sales volumes for Origin's energy markets business fell by 5pc to 36PJ from 38PJ in January-March 2023. Origin said it continues to negotiate a deal with the government of New South Wales (NSW) regarding the 2,880MW Eraring coal-fired power station's future . The power plant had been due to close in 2025 but insufficient new generation capacity has been completed in NSW for this to occur. "We continue to progress large-scale batteries under development at Eraring and Mortlake power stations and recently announced our first storage offtake agreement from the Supernode battery in Queensland, taking Origin's storage portfolio to around 1GW of capacity once these batteries come on line," chief executive Frank Calabria said on 30 April. By Tom Major APLNG results Jan-Mar '24 Oct-Dec '23 Jan-Mar '23 y-o-y % ± q-o-q % ± Production (PJ) 176 167 165 7 5 Sales (PJ) 168 160 158 6 4 Commodity revenue (A$mn) 2,303 2,149 2,583 -11 7 Average realised LNG price ($/mn Btu) 12.17 11.88 14.50 -15 3 Average realised domestic gas price (A$/GJ) 6.90 6.39 6.17 12 8 Source: Origin Energy Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Yara first-quarter gas consumption higher on year


29/04/24
29/04/24

Yara first-quarter gas consumption higher on year

London, 29 April (Argus) — Europe's largest fertiliser producer Yara's European gas consumption in the first quarter was up by 26pc on the year, but remained far lower than in the second half of last year. Norway-based Yara's gas consumption across Europe in January-March totalled 29.2 trillion Btu, well above the 23.1 trillion Btu a year earlier, but drastically down from 37.5 trillion Btu in the fourth quarter last year, the company's latest quarterly report shows. Yara did not report its European ammonia production for the first quarter, but the company's global output totalled 1.74mn t, up from 1.38mn t a year earlier. Yara's first-quarter European gas consumption fell from the preceding three months, despite its average European gas costs falling to $11.70/mn Btu from $13/mn Btu. The firm's European gas costs have declined sharply since peaking at $34.50/mn Btu in the third-quarter 2022, when European wholesale prices hit all-time highs ( see price graph ). Yara's quarterly spending on European gas supplies fell to $343mn in January-March, the lowest since at least summer 2021 when the company began reporting this data, and around one third the $1.08bn peak in April-June 2022. Yara's European gas consumption also fell despite a 37pc annual increase in total fertiliser deliveries in Europe . Lower curtailments, improved production economics and "volume catch-up" had supported output, Yara said. But while European deliveries improved on the year, they remained "below normal" — particularly for nitrates — and Yara sourced a larger share of its European deliveries from its global plants, the company's chief financial officer Thor Giaever said. Yara had hinted earlier this year its ammonia assets might run at 90pc or more of capacity as the company expected to boost production this year . But one explanation for the lower gas demand compared to the previous quarter is Yara may be maximising production at more efficient plants like Sluiskil in the Netherlands and Brunsbuttel in Germany, while ramping down less efficient plants, allowing the company to maintain or increase production while consuming less gas. Yara last year curtailed 19pc of its European ammonia capacity , turning towards greater imports of ammonia to replace the lower production. And that remains key to Yara's business plans , which the company said last week focused on "further strengthening operational resilience and flexibility". Argus assessed European ammonia production prices based on the TTF front-month price at roughly a $100/t discount to northwest European import prices in its last weekly assessment on 25 April, suggesting a still-significant financial incentive to produce ammonia domestically. The European fertiliser market remains under pressure by large volumes from Russia, meaning Europe has swapped an energy dependency on Russia for a food dependency, chief executive Svein Tore Holsether said, echoing previous statements . Comparing global assets Yara consumed 54.4 trillion Btu of gas globally in January-March, down from a multi-year high of 61.9 trillion Btu in October-December ( see consumption graph ). European consumption accounted for roughly 54pc of Yara's global gas demand in January-March, well down from 61pc in the previous quarter. And Yara spent $485mn on gas worldwide in January-March, 71pc for European supply, a lower proportion than at any other point since 2021. Yara's global average gas cost was $8.90/mn Btu in January-March, 24pc below its reported European cost. That discount has been a significant driver for Yara and others to increase production abroad rather than in Europe over the past two years. Yara forecasts its European gas costs at $9.70/mn Btu and $10.50/mn Btu in the second and third quarters of this year, respectively, holding well above its global average gas costs of $7.70/mn Btu and $8.40/mn Btu during those same periods. Globally, the firm aims to produce 8.6mn t of ammonia in 2025, significantly up from 7.8mn t in 2023, it said. By Brendan A'Hearn Yara European vs global gas costs $/MMBtu Yara European vs global gas consumption million MMBtu Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Service firms talk up long-term gas prospects


29/04/24
29/04/24

Service firms talk up long-term gas prospects

New York, 29 April (Argus) — Leading oil field service firms are bullish on the outlook for natural gas demand in coming years even though the fuel remains stuck in the doldrums for now, with US prices near pandemic lows amid oversupply after a mild winter. "This is the age of gas," Baker Hughes chief executive Lorenzo Simonelli says, adding that global demand for the power plant and heating fuel is due to climb by almost 20pc through 2040. "Gas is abundant, lower emission, low cost, and the speed to scale is unrivalled," he says. Halliburton also sees natural gas as the "next big leg of growth" in North America, driven by demand for LNG expansion projects, although its current plans do not envisage any comeback this year. Given a shrinking fracking fleet and lack of new equipment being built, the stage is set for an "incredibly tight market" in future, chief executive Jeff Miller says. A recovery in natural gas activity in the US may not happen until the end of this year or even 2025, Liberty Energy chief executive Chris Wright says. "Customers need to see that prices have firmed, that export volume demand actually is pulling upward at a meaningful rate," he says. On recent first-quarter earnings calls, service firms were upbeat about international growth prospects in the face of escalating geopolitical tensions in the Middle East. The backdrop remains one of growing demand for oil and gas and an "even deeper focus" on energy security, according to Olivier Le Peuch, chief executive of SLB, the world's biggest oil field service company. SLB, formerly known as Schlumberger, expects overseas growth momentum to make up for a slowdown in North America this year. "The relevance of oil and gas in the energy mix continues to support further investments in capacity expansion, particularly in the Middle East and in long-cycle projects across global offshore markets," Le Peuch says. But results in North America will be depressed by the combination of low gas prices, capital discipline and producer consolidation. International rescue Halliburton expects international revenue growth in the "low double-digits" for the full year, with some margin expansion given the tight market for equipment and labour. Steady activity levels are seen in North America after land completion activity bottomed out in the fourth quarter of 2023 and rebounded in the first quarter. "The world requires more energy, not less, and I'm more convinced than ever that oil and gas will fill a critical role in the global energy mix for decades to come," Miller says. The positive outlook is reinforced by customers' multi-year activity plans across markets and assets. Baker Hughes forecasts "high single-digit growth" when it comes to the outlook for international drilling and completion spending this year. But customer spending in North America is expected to fall in a "low to mid-single-digit range" when compared with 2023. "We continue to anticipate declining activity in the US gas basins, partially offsetting modest improvement in oil activity during the second half of the year," Simonelli says. Beyond 2024, upstream spending is seen growing further across international markets, albeit at a "more moderate" pace than seen in recent years, according to Baker Hughes. SLB paced a decline among oil service stocks at the end of January when state-controlled Saudi Aramco scrapped plans to increase crude output capacity to 13mn b/d from 12mn b/d. But Saudi Arabia has stepped up its plans to boost gas output, by 60pc by 2030. This new energy mix was not anticipated six months ago, but it will "not have a natural impact on our ambition for growth" in Saudi Arabia, Le Peuch says. And Saudi gas plans will require substantial investment in gas infrastructure, which is a "long-term net positive" for Baker Hughes, Simonelli says. By Stephen Cunningham Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

BP inks another LNG deal with Korea's Kogas: Correction


29/04/24
29/04/24

BP inks another LNG deal with Korea's Kogas: Correction

Corrects total volume of LNG supplied in paragraph 2 Singapore, 29 April (Argus) — BP has signed another long-term LNG sales and purchase agreement with South Korean state-owned importer Kogas, the former said today. BP will provide Kogas with up to 9.8mn t of LNG over 11 years from mid-2026 on a des basis. But other details regarding pricing and the origin of the contracted supplies were not available. This most recent deal is in addition to the existing long-term sales and purchase agreement between the two companies that was signed in 2022. Kogas on 22 April 2022 signed an 18-year LNG purchase agreement to buy 1.58mn t/yr of LNG from BP that will begin in 2025. Australian independent Woodside Energy and Kogas in February signed a sales and purchase deal for term supplies of LNG to South Korea. The deal for 500,000 t/yr on a des basis will start in 2026 and run for 10½ years. Kogas may be seeking more imported term supply as the firm has increased its downstream contractual supply deals. Kogas signed a series of deals to supply gas to subsidiaries of the country's state-controlled utility Kepco in December 2023. By Simone Tam Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.