A natural gas pipeline blast in eastern Venezuela is having far-reaching impact on the country's crude and petrochemical operations, highlighting the role of gas in sustaining the fragile national oil industry.

By knocking out the Pigap 2 gas compression complex, the 20 March blast shut in around 20,000 b/d of Venezuelan state-owned PdV's Santa Barbara light crude production for up to six weeks, according to multiple incident reports seen by Argus.

The blast took down up to 1bn cf/d of associated gas production as well.

One of Venezuela's legacy grades, 39°API Santa Barbara crude is used for blending with extra-heavy crude from the Orinoco oil belt to produce 16°API Merey for export.

The incident took place within a dense grid of crude and gas pipelines and valves that transports gas to Pigap 2 where it is compressed and reinjected into oil fields.

The grid connected to the blast-damaged 36-inch gas pipeline also directs light crude and associated gas to Orinoco heavy crude blending, upgrading and petrochemical plants at the Jose complex on the coast of Anzoategui state. Among the plants that have been shut down or curtailed for lack of gas are Mitsubishi-led methanol producer Metor, Eni-led Supermetanol and fertilizer producer Fertinitro led by state-owned Pequiven.

A senior PdV eastern division official describes the gas and crude pipeline grid where the blast occurred as "critical to the company's upstream crude and gas operations in Monagas."

A preliminary damage assessment of the ruptured gas pipeline said repairs could take up to six weeks, but the PdV manager said repairs could be completed in less than a month. "We hope to restart the 36-inch gas pipeline by 15 April," he said.

The accident is the latest setback for PdV, which had tentatively recovered its production to more than 500,000 b/d in recent weeks. The government of President Nicolas Maduro routinely blames US sanctions and sabotage for industrial accidents.


Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

25/04/24

Indonesia's Pertamina to complete gasoline unit in Aug

Indonesia's Pertamina to complete gasoline unit in Aug

Singapore, 25 April (Argus) — Indonesian state-controlled refiner Pertamina aims to finish building its new 90,000 b/d residual fluid catalytic cracker (RFCC) in the Balikpapan refinery in August, the firm said. The RFCC is a gasoline production unit, which typically uses residual fuel as a feedstock. The unit will be able to produce propylene, LPG and 92R gasoline that will meet the Euro V specifications, said Pertamina last week, without disclosing further details such as the start-up date. The newly built RFCC unit will be the largest in Indonesia, with the second-largest being the 83,000 b/d RFCC in Balongan and the third-largest the 54,000 b/d RFCC in Cilacap. The new RFCC will also help reduce Indonesia's reliance on gasoline imports. Indonesia currently imports around 9mn-11mn bl/month of gasoline, making it the largest gasoline buyer in the Asia-Pacific. The new RFCC will increase Pertamina's gasoline production by a conservative estimate of 45,000 b/d or 1.3mn bl, or around 10pc of Pertamina's current import demand, according to estimates from an oil analyst. The installation of the new RFCC is part of Pertamina's Refinery Development Master Plan (RDMP), which will take place in two phases. The first phase includes revamping existing units at the Balikpapan refinery, such as the crude distillation unit, vacuum distillation unit, and hydrocracking unit. It also involves building new units, such as the aforementioned RFCC, a gasoline hydrotreater, diesel hydrotreater, and naphtha hydrotreater. The second phase includes building a new residue desulphurisation unit. The RDMP also includes expanding the capacity of the Balikpapan refinery from 260,000 b/d to 350,000 b/d, said Pertamina's chief executive officer Nicke Widyawati. The Balikpapan expansion is expected to be completed in May. By Aldric Chew Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

India’s Gail to shut Dabhol LNG terminal for monsoon


25/04/24
25/04/24

India’s Gail to shut Dabhol LNG terminal for monsoon

Mumbai, 25 April (Argus) — Indian state-controlled gas distributor Gail is planning to shut its 5mn t/yr Dabhol LNG terminal on the west coast from 15 May, ahead of monsoon rains. Gail will also stop importing LNG from mid-May at the terminal, a company official told Argus . This is because of the lack of a breakwater facility at the terminal, which prevents it from anchoring ships in turbulent seas. The breakwater facility was expected to be completed in January, but the cause of the delay is unknown. The terminal is likely to resume operations from the end of September, similar to its plans in 2023 , as this shutdown over the monsoon season is routine. Gail is set to receive a total of 139,635t LNG at the Dabhol terminal in May, which will arrive in two separate shipments from the US' 5.75mn t/yr Cove Point export facility. Both cargoes will be the last that the terminal will receive before it shuts in mid-May. It has received 583,326t of LNG at the terminal since the beginning of the year, lower by 4pc on the year, data from market analytics firm Kpler show. The Dabhol terminal only receives about 2.9mn t/yr of LNG, despite having a nameplate capacity of 5mn t/yr, because it is not used during the monsoon season. Gail intends to gradually increase the capacity of the Dabhol terminal to 12mn t/yr by April 2030–March 2031. By Rituparna Ghosh Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

EU plastics law clears parliament with mixed reaction


24/04/24
24/04/24

EU plastics law clears parliament with mixed reaction

Brussels, 24 April (Argus) — The European Parliament has adopted the EU's Packaging and Packaging Waste Regulation (PPWR) that requires reductions in plastics and other packaging, ahead of formal approval by the bloc's ministers. The regulation had been provisionally agreed between EU diplomats in March. The regulation, adopted with 476 votes in favor and 129 opposed, obliges packaging reductions of 5pc by 2030, 10pc by 2035 and 15pc by 2040. EU countries must specifically cut plastic packaging waste. Starting on 1 January 2030, the regulation also bans single-use plastic packaging for unprocessed fresh fruit and vegetables, and for foods and beverages filled and consumed in cafés and restaurants. Other bans from 2030 affect individual portions for condiments, sauces, creamers and sugar, as well as very lightweight plastic carrier bags. The rules require all packaging to be recyclable, with exemptions for lightweight wood, cork, textile, rubber, ceramic, porcelain and wax. Plastics Europe's managing director Virginia Janssens said the adopted text is "ambitious" and needs practical implementation. "We need a careful review of the impact of the reuse targets and affected formats, especially in transport packaging," Janssens said. The plastics manufacturers' association said a lack of material neutrality undermined the aims of the PPWR to reduce packaging waste. European paper industry association Cepi pointed to a phase out of "fossil-based materials" and called for timely compliance with the new regulation. Cepi urged EU member states to endorse the agreement when voting. European farmers association Copa-Cogeca noted "discriminatory" treatment for the fruit and vegetable sector, adding that the European Commission, EU member states and parliament have so far "ignored" arguments to amend the text to exempt single-use packaging for fresh fruit and vegetables. EU ministers also voted on an objection approved last week by the EU environment committee regarding mass balance accounting rules, which did not get the majority needed to be confirmed. By Dafydd ab Iago Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Brightmark to build Georgia pyrolysis plant


24/04/24
24/04/24

Brightmark to build Georgia pyrolysis plant

Houston, 24 April (Argus) — Chemical recycler Brightmark plans to build a 400,00t/yr pyrolysis plant in Thomaston, Georgia, two years after the company terminated its plan to build a similar plant in a nearby Georgia community. Pyrolysis is a form of chemical recycling that breaks down used plastic into pyrolysis oil, which can then be reprocessed into new plastics at virgin polymers facilities. The 2.5mn ft² plant will cost $950mn, including infrastructure such as roads and rail access, Brightmark said. A previous plan to build a chemical recycling facility in Macon, Georgia, ended in 2022 after Mayor Lester Miller withdrew his support, citing "long-term safety concerns" from Brightmark's "unproven process". The company finished construction of its first chemical recycling plant in Ashley, Indiana, in 2022. Brightmark said it has recycled 2,000t of plastic waste so far at its Indiana plant, well behind its anticipated volume of 100,000 t/yr. By Zach Kluver Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Cepsa supplies HVO bunker fuel in Algeciras


24/04/24
24/04/24

Cepsa supplies HVO bunker fuel in Algeciras

London, 24 April (Argus) — Spanish refiner and bunker fuel supplier Cepsa has recently delivered 150t of 100pc hydrotreated vegetable oil (HVO) by truck to the Ramform Hyperion at the port of Algeciras. The supply follows market participants reporting firmer buying interest for HVO as a marine fuel from ferry lines in the Mediterranean in recent sessions. The supplied HVO is said to be of class II, with used cooking oil (UCO) as the feedstock. Cepsa added that the supply was completed in cooperation with Bunker Holding subsidiary Glander International Bunkering, and could bring about a greenhouse gas (GHG) emissions reduction of up to 90pc compared with conventional fuel oil. Cepsa will also look to obtain capability to supply marine biodiesel blends exceeding 25pc biodiesel content by the end of the year, delegates heard at the International Bunker Conference (IBC) 2024 in Norway. This also follows plans by Cepsa to build a 500,000 t/yr HVO plant in Huelva , set to start production in the first half of 2026. Argus assessed the price of class II HVO on a fob Amsterdam-Rotterdam-Antwerp (ARA) basis at an average of $1,765.54/t in April so far, a premium of $906.41/t to marine gasoil (MGO) dob Algeciras prices in the same month. By Hussein Al-Khalisy Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.