A group of Europe's gas system operators have substantially expanded a proposal to build a continent-wide hydrogen network using repurposed natural gas pipelines and new infrastructure.

Industry association European Hydrogen Backbone (EHB) has proposed building a 11,600km hydrogen transportation network by 2030, which would expand to 39,700km across 21 European countries by 2040. This is enlarged from last year's proposal for a 6,800km network by 2030 and 23,000km by 2040, connecting 10 European countries.

The previous plan was concentrated in the Netherlands, Germany, Belgium and France, but the newly-proposed network widens the project's reach to the UK and Ireland, much of central and eastern Europe, Finland, Estonia and Greece.

About 69pc of the proposed network would consist of repurposed existing natural gas infrastructure, with the remainder consisting of newly-built pipelines used to connect new offtakers and located in countries with small gas grids, EHB said. This is down from 75pc in the previous version of the proposal. A dedicated network is needed to integrate planned renewable electricity generation and to develop a liquid cross-border hydrogen market, EHB said (see planned pipelines table).

The network would eventually incorporate major existing gas infrastructure, including salt caverns and aquifer storage sites across the continent (see country-level table).

BBL or Interconnector to link UK

The UK's network would be connected to mainland Europe by retrofitting the Interconnector — which connects to Belgium — or the BBL, which connects to the Netherlands. And one of the two pipelines connecting Ireland and the UK at Moffat could be converted to carry hydrogen. The plan foresees four of the UK's five major industrial hubs connected to hydrogen production clusters by 2030 through a phased re-purposing of existing infrastructure.

EHB also proposed converting a number of pipelines that connect EU markets with gas exporters, including at least one of the five parallel lines that compose the Transmed route which connects Italy and Libya, the two undersea connections between Algeria and Spain, one of the pipelines used to deliver Norwegian gas to mainland Europe and the Trans-Adriatic Pipeline (Tap) — which only started up this year and delivers Azeri gas sent to Europe through Turkey. But this would likely require suppliers to produce hydrogen domestically for delivery to Europe, either through steam reformation of methane or through electrolysis, primarily powered by renewable electricity sources.

Major existing gas transit routes are also included in the proposal. The large-diameter Tag pipeline passing to Italy from Slovakia as well as connections through the Czech Republic and Slovakia could be repurposed if gas flows "drop significantly", freeing up one of two parallel lines, EHB said.

A "much more dynamic picture" has emerged for Germany compared with the previous proposal, the association said. Natural gas and hydrogen may compete for the same pipeline infrastructure by 2035, with decisions to depend largely on political support for the scale-up of hydrogen and general market developments of hydrogen and natural gas, EHB said.

Some operators mentioned Russia as a possible hydrogen source. The country yesterday said it plans to achieve a 20-25pc share of global hydrogen trading by 2035.

The proposal also incorporates new infrastructure, including hydrogen produced by excess renewables output on "energy islands" offshore the Netherlands, Germany and Denmark and a new subsea pipeline connecting Germany, Sweden, Finland and Estonia.

The expanded network would allow pipeline imports from Europe's eastern and southern neighbours — including Ukraine — as well as imports of liquid hydrogen at Europe's main ports, EHB said. And extending the network through central and eastern Europe would allow renewables to play a larger role in a largely coal-based power mix and enable hydrogen to decarbonise heavy industry concentrated in the region.

But the design of the network and timeline depend on market conditions for hydrogen and gas, as well as the introduction of a "stable hydrogen framework", the group said. Hydrogen supply and demand and its increasing integration in the energy system may lead to alternative or additional routes, as well as a shift in the timeline forward or backward, EHB said.

Investment costs down, transport costs up

The envisaged hydrogen network by 2040 would cost €43bn-81bn, EHB said. While up from the €27bn-64bn previously anticipated, the cost per kilometre is lower as the proposal now incorporates smaller diameter pipelines which are cheaper to repurpose.

But smaller diameter pipelines have higher operating costs, increasing the average transport cost to €0.11-0.21/kg hydrogen. This is attractive and cost-effective for long-distance transportation, taking into account an estimated future production cost of €1-2/kg, EHB said (see investment costs, project costs tables).

Country-level, selected proposed H₂ commitments
CountryEmission commitments / H₂ plans or possible outcomes
AustriaBy 2030, 100pc renewable electricity
By 2030, blending to/from existing cross-border infrastructure
By 2035, bi-directional repurposing of one TAG string
By 2040, additional interconnector to Germany for Ukrainian H₂
By 2040, carbon neutrality
BelgiumBy 2040, demand expected to exceed production
Czech RepublicBy 2035, possible transit to Germany from Slovakia
By 2035, possible transit to Germany from Germany via Gazelle pipeline
DenmarkBy 2030, 70pc emisssions reduction
In 2030, two "energy islands" of 2GW each
In 2030, 3GW electrolysis capacity
By 2040, one island expanded to 10GW, offshore H₂ production
FranceIn 2030, 6.5GW electrolysis capacity
By 2040, "mature" network with three interconnectors with Spain
Most pipelines would be repurposed
GermanyIn 2030, H₂ demand of 90-110TWh
Imports from Netherlands, Czech Republic
UKBy 2030, 5GW H₂ production capacity
By 2030, 40GW offshore wind capacity
By 2030, four low-carbon industrial clusters
By 2035, all five industrial clusters potentially connected
By 2040, repurposed connection to Ireland
Most pipelines would be repurposed
GreeceBy 2040, two main industrial clusters connected by new H₂ pipelines
Plans for 7GW of wind capaciy and 8GW of solar capacity
Possible export connection via TAP or south-east Europe
HungaryBy 2030, 6GW solar capacity
By 2035, possibility of mature work with six interconnections
By 2035, a transit country for Ukrainian H₂
By 2050, carbon neutrality
IrelandBy 2030, 5GW offshore wind capacity
By 2040, reconfiguration of Dublin gas network
ItalyBy 2030, repurposing of pipelines enabling import via Tunisia
By 2035, onward connnection to Austria, Slovenia
By 2040, possible interconnection with Switzerland
NetherlandsBy 2027, first 'backbone' of repurposed pipelines available
By 2030, 10-15GW network capacity
By 2050, 180GW offshore wind capacity
PolandBy 2030, 2GW electrolyser capacity
By 2030, 5.9GW offshore wind capacity
By 2040, 11GW offshore wind capacity
Post 2040, all industrial clusters connected
Repurposing of existing pipelines difficult due to gas demand projections
SlovakiaTransit market for Ukrainian-sourced supply
By 2035, repurposing of one existing pipeline from Ukraine
SpainBy 2030, 4GW electrolyser capacity
Long-term H₂ production and supply ambition
By 2035, connection to France, north Africa
By 2040, additional connection to France
Estimated project costs
Cost scenarios
CapexLowMediumHigh
Pipeline capex (small, new)€mn/km1.41.51.8
Pipeline capex (medium, new)€mn/km2.02.22.7
Pipeline capex (large, new)€mn/km2.52.83.4
Pipeline capex (small, repurposed)€mn/km0.20.30.5
Pipeline capex (medium, repurposed)€mn/km0.20.40.5
Pipeline capex (large, repurposed)€mn/km0.30.50.6
Compressor station capex€mn/MWe2.23.46.7
Assumptions
Weighted average cost of capital%5-75-75-7
Operations and maintenance (ex. electricity)€/yr as % of capex0.8-1.70.8-1.70.8-1.7
Electricity price€/MWh405090
Depreciation (pipelines)yrs30-5530-5530-55
Depreciation (compressor stations)yrs15-3315-3315-33
Planned hydrogen infrastructure, EHB*km
RepurposedNew
Pipeline diameter
Small (<28in, <700mm)3,172.01,586.0
Medium (28-37in, 700-950mm)11,498.55,154.5
Large (>37in, >950mm)12,688.05,551.0
Total27,200.012,450.0
*Total differs from elements due to rounding
European Hydrogen Backbone costs, 2040 bn
LowMediumHigh
Pipeline cost33.041.051.0
Compression cost10.015.030.0
Total investment cost43.056.081.0
Operational expenditure (/yr)0.81.11.8
Electricity costs (/yr)0.91.12.0
Total operatonal cost1.72.23.8

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

02/05/24

FTC clears Exxon-Pioneer deal but bars Sheffield

FTC clears Exxon-Pioneer deal but bars Sheffield

New York, 2 May (Argus) — US antitrust regulators signaled they will clear ExxonMobil's proposed $59.5bn takeover of Pioneer Natural Resources but banned the shale giant's former chief executive officer from gaining a seat on the board. A proposed consent order from the Federal Trade Commission seeks to stop Scott Sheffield, Pioneer's former chief executive, from taking part in "collusive activity" that would potentially raise crude prices and cause US consumers to pay more at the pump. The order paves the way for ExxonMobil to close its blockbuster deal for Pioneer, which will make it the leading producer in the prolific Permian shale basin of west Texas and southeastern New Mexico. It is also the top US oil producer's biggest transaction since Exxon's 1999 merger with Mobil. ExxonMobil's Permian output will more than double to 1.3mn b/d of oil equivalent (boe/d) when the acquisition closes, before increasing to about 2mn boe/d in 2027. The FTC, which has taken a tougher line on mergers under the administration of President Joe Biden, has paid close attention to oil deals announced during the latest phase of shale consolidation. Only this week, Diamondback Energy said it had received a second request for information from the regulator over its $26bn proposed takeover of Endeavor Energy Resources. And Chevron's planned $53bn acquisition of US independent Hess has also been held up. The FTC alleged in a complaint that Sheffield exchanged hundreds of text messages with Opec officials discussing crude pricing and output, and that he sought to align production across the Permian with the cartel. His past conduct "makes it crystal clear that he should be nowhere near Exxon's boardroom," said Kyle Mach, deputy director of the FTC's Bureau of Competition. ExxonMobil said it learnt about the allegations against Sheffield from the FTC. "They are entirely inconsistent with how we do business," the company said. While Pioneer said it disagreed with the FTC's complaint, which reflects a "fundamental misunderstanding" of US and global oil markets and "misreads the nature and intent" of Sheffield's actions, the company said it would not be taking any steps to stop the merger from closing. By Stephen Cunningham Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

CEE gas operators begin binding capacity offer process


02/05/24
02/05/24

CEE gas operators begin binding capacity offer process

London, 2 May (Argus) — Gas transmission system operators (TSOs) across central and eastern Europe have launched the start of binding incremental capacity processes aimed at facilitating larger gas flows from south to north. Romanian, Bulgarian, Hungarian, Moldovan and Ukrainian operators have published joint documents outlining the necessary conditions for participating in the upcoming annual auctions on 1 July. Bulgarian and Romanian TSOs Bulgartransgaz and Transgaz will offer an additional roughly 123 GWh/d of capacity from Bulgaria to Romania at Negru Voda 1-Kardam on top of existing available capacity of 126-142 GWh/d depending on the year ( see BG-RO table ). In the event of a successful auction and subsequent economic test, the TSOs hope to reach a final investment decision (FID) in the third quarter of this year and commission the upgrades in the third quarter of 2026. Commercial operations could begin in the fourth quarter, aligning with the start of the 2026-27 gas year. This timeline has been moved forward by one year from the original proposals earlier this year . Transgaz, along with Hungary's FGSZ, will offer up to 73 GWh/d of additional capacity from Romania to Hungary at Csanadpalota on top of existing available capacity of 5-71 GWh/d depending on the year ( see RO-HU table ), but maintained its three-tiered approach elaborated in an earlier market consultation . Depending on the level of capacity to which firms commit at the auction, capacity could increase by 9.5 GWh/d, 47.3 GWh/d or 72.5 GWh/d. The smallest project could start commercial operations in the first quarter of 2028, the middle level in the third quarter of 2028, and the highest level in the third quarter of 2029. These timelines are pushed back by roughly one year from the originally-proposed dates in the February consultation. And Transgaz, along with Ukraine's GTSOU, will offer an additional 77 GWh/d of capacity from Romania to Ukraine at Isaccea 1-Orlovka 1 on top of existing available capacity of 97-109 GWh/d depending on the year ( see RO-UA table ). The TSOs aim to reach FID in the third quarter of this year and commission the project in the fourth quarter of 2028. Commercial operations could begin in October 2028. GTSOU and its Moldovan counterpart Vestmoldtransgaz will offer 173 GWh/d towards Moldova from Ukraine at Kaushany starting from the 2027-28 gas year, while simultaneously offering 159 GWh/d of capacity from Moldova towards Ukraine at Grebenyky. By Brendan A'Hearn Available and incremental capacity at Negru Voda/Kardam GWh/d/yr Gas year Available existing cap Incremental cap Total 2024-25 141 - 141 2025-26 141 - 141 2026-27 142 123 265 2027-28 142 123 265 2028-29 142 123 265 2029-30-2042 126 123 249 — Bulgartransgaz, Transgaz; numbers rounded Available and incremental capacity at Csanadpalota GWh/d/yr Gas year Available existing cap Incremental cap Total 2024-25 43 - 43 2025-26 46 - 46 2026-27 71 - 71 2027-28 13 - 142 2028-29 13 - 13 2029-30 5 73 78 2030-31 34 73 107 2031-32 34 73 107 2032-33-2039 63 73 136 — FGSZ, Transgaz; numbers rounded Available and incremental capacity at Isaccea/Orlovka GWh/d/yr Gas year Available existing cap Incremental cap Total 2024-25 109 - 109 2025-26 109 - 109 2026-27 109 - 109 2027-28 109 - 186 2028-29 109 77 186 2029-30-2039 97 77 174 — GTSOU, Transgaz; numbers rounded Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Shell's 1Q profit supported by LNG and refining


02/05/24
02/05/24

Shell's 1Q profit supported by LNG and refining

London, 2 May (Argus) — Shell delivered a better-than-expected profit for the first quarter of 2024, helped by a strong performance from its LNG and oil product businesses. The company reported profit of $7.4bn for January-March, up sharply from an impairment-hit $474mn in the previous three months but down from $8.7bn in the first quarter of 2023. Adjusted for inventory valuation effects and one-off items, Shell's profit came in at $7.7bn, 6pc ahead of the preceding three months and above analysts' estimates of $6.3bn-$6.5bn, although it was 20pc lower than the first quarter of 2023 when gas prices were higher. Shell's oil and gas production increased by 3pc on the quarter in January-March and was broadly flat compared with a year earlier at 2.91mn b/d of oil equivalent (boe/d). For the current quarter, Shell expects production in a range of 2.55mn-2.81mn boe/d, reflecting the effect of scheduled maintenance across its portfolio. The company's Integrated Gas segment delivered a profit of $2.76bn in the first quarter, up from $1.73bn in the previous three months and $2.41bn a year earlier. The segment benefited from increased LNG volumes — 7.58mn t compared to 7.06mn t in the previous quarter and 7.19mn t a year earlier — as well as favourable deferred tax movements and lower operating expenses. For the current quarter, Shell expects to produce 6.8mn-7.4mn t of LNG. In the downstream, the company's Chemicals and Products segment swung to a profit of $1.16bn during the quarter from an impairment-driven loss of $1.83bn in the previous three months, supported by a strong contribution from oil trading operations and higher refining margins driven by greater utilisation of its refineries and global supply disruptions. Shell's refinery throughput increased to 1.43mn b/d in the first quarter from 1.32mn b/d in fourth quarter of last year and 1.41mn b/d in January-March 2023. Shell has maintained its quarterly dividend at $0.344/share. It also said it has completed the $3.5bn programme of share repurchases that it announced at its previous set of results and plans to buy back another $3.5bn of its shares before the company's next quarterly results announcement. The company said it expects its capital spending for the year to be within a $22bn-$25bn range. By Jon Mainwaring Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

US Fed signals rates likely to stay high for longer


01/05/24
01/05/24

US Fed signals rates likely to stay high for longer

Houston, 1 May (Argus) — Federal Reserve policymakers signaled they are likely to hold rates higher for longer until they are confident inflation is slowing "sustainably" towards the 2pc target. The Federal Open Market Committee (FOMC) held the federal funds target rate unchanged at a 23-year high of 5.25-5.5pc, for the sixth consecutive meeting. This followed 11 rate increases from March 2022 through July 2023 that amounted to the most aggressive hiking campaign in four decades. "We don't think it would be appropriate to dial back our restrictive policy stance until we've gained greater confidence that inflation is moving down sustainably," Fed chair Jerome Powell told a press conference after the meeting. "It appears it'll take longer to reach the point of confidence that rate cuts will be in scope." In a statement the FOMC cited a lack of further progress towards the committee's 2pc inflation objective in recent months as part of the decision to hold the rate steady. Despite this, the FOMC said the risks to achieving its employment and inflation goals "have moved toward better balance over the past year," shifting prior language that said the goals "are moving into better balance." The decision to keep rates steady was widely expected. CME's FedWatch tool, which tracks fed funds futures trading, had assigned a 99pc probability to the Fed holding rates steady today while giving 58pc odds of rate declines beginning at the 7 November meeting. In March, Fed policymakers had signaled they believed three quarter points cuts were likely this year. Inflation has ticked up lately after falling from four-decade highs in mid-2022. The consumer price index inched back up to an annual 3.5pc in March after reaching a recent low of 3pc in June 2023. The employment cost index edged up in the first quarter to the highest in a year. At the same time, job growth, wages and demand have remained resilient. The Fed also said it would begin slowing the pace of reducing its balance sheet of Treasuries and other notes in June, partly to avoid stress in money markets. By Bob Willis Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

FERC OK’s Virginia Transco gasline expansion


01/05/24
01/05/24

FERC OK’s Virginia Transco gasline expansion

New York, 1 May (Argus) — The US Federal Energy Regulatory Commission (FERC) today gave Williams the green light to expand natural gas capacity to Virginia by 101mn cf/d (2.9mn m3/d) on its Transco pipeline. The project, called the Commonwealth Energy Connector, involves the construction of 6.3 miles of new pipeline within Transco's existing right-of-way in southeast Virginia, near the border with North Carolina. The project also includes adding horsepower at compressor station 168, west of the new pipeline segment. Williams plans to begin construction this winter and put the project into service by the end of 2025. Environmental advocacy group Sierra Club opposed the project, arguing FERC failed to assess its potential greenhouse gas emissions, rendering its National Environmental Policy Act analysis moot. FERC disagreed, conceding that although the project's final Environmental Impact Statement demonstrated it would contribute to greenhouse gas emissions, the effects of those emissions on the environment could not be measured because FERC lacks the methodology to do so. The US south-Atlantic gas market has become more volatile in recent years as gas and power demand have soared, outpacing pipeline capacity expansions in the region. The combined gas consumption of Virginia and North and South Carolina in 2022 averaged 4.7 Bcf/d, up by 69pc from a decade earlier, US Energy Information Administration data show. Regional gas and power consumption is widely expected to continue climbing through the end of the decade on a massive build-out of data centers , especially in Virginia. By Julian Hast Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more