Greek transmission system operator Desfa plans to complete nearly all the gas projects in its updated 10-year development plan (TYDP) within the next three years.

Desfa's projected spend on all projects comes to over €1.37bn, of which €1.34bn would be used within the next three years. The most important of these projects are presented below, split by category.

Interconnectors

Desfa expects the 1.5bn m³/yr Greece-North Macedonia interconnector to start commercial operations in January 2026, a delay of roughly a year from the timeline it gave in October 2023.

The pipeline will run from Nea Messimvria — where Azeri gas enters the Greek grid — to Gevgelija and will cost around €92mn.

LNG terminals

The connection of the Dioriga LNG terminal will start commercial operations in December 2026, according to the latest TYDP, 1½ years later than previously envisaged.

Desfa expects to reach a final investment decision (FID) on a metering and regulating station to connect the planned Dioriga LNG terminal in February 2025.

Developer Motor Oil Hellas recently told Argus it plans to make FID on the project by the end of this year. The project will cost Desfa around €21mn and will be financed through connection fees. The new entry point will have a capacity of around 11.8mn m³/d, or 4.3bn m³/yr.

Desfa expects a new small-scale jetty already under construction at Revithoussa to start commercial operations in December 2025. The €38mn project will enable ships with capacities of 1,000-30,000m³ of LNG to unload and reload.

And Desfa has also taken FID on a compressor station for Revithoussa, which will allow for boil-off gas to be sent into the transmission system rather than flared. Commercial operations are envisioned to start in May 2025.

No mention of grid connections for the Argo floating storage and regasification unit or Thessaloniki LNG projects were included in the TYDP, throwing their future into further doubt following recent delays.

Power plants

Desfa included multiple pipeline connections to gas-fired power plants in the TYDP.

The operator expects the 877MW Thermoilektriki Komotinis plant's connection to the grid to start commercial operations in October. It will have a capacity of around 3.4mn m³/d, or 1.24bn m³/yr. The project's operators expect test operations to begin this autumn.

Another project will connect Elpedison's planned 826MW plant near Thessaloniki, with a capacity of around 1.14bn m³/yr. Desfa envisions commercial operations beginning in November 2025.

A third project would connect to an 840MW plant at Alexandroupolis and start commercial operations in May 2027. Lastly, Desfa expects a project connecting the 873MW Larisa Thermoelectriki plant to start commercial operations in mid-2027. Pipeline capacities for these two projects were not disclosed, but would likely be similar to the first two.

Compressor stations

Several compressor station plans have been delayed, notably at Komotini and Ampelia.

The two expansion phases at Komotini have been pushed back by six months to March and June 2025, respectively, because of delays during the permitting process. The project will increase the system's "technical adequacy", as well as its capacity, according to Desfa.

And Desfa expects the compressor station at Ampelia, a crucial part of enabling higher north to south transmission, to start commercial operations only in June 2025. The nine-month delay is because of "extreme weather events" in the area in 2023.

And a booster compressor for the Trans-Adriatic pipeline at Nea Messimvria — which will enable fully bidirectional flows — is scheduled to start commercial operations in December 2025. Permitting delays have pushed back the start date by more than a year.

Domestic grid

Several large projects are also in the works to expand the domestic grid.

Desfa plans a 145km pipeline to connect the city of Patras and its industrial area to the grid, expecting FID in June 2025 and the start of commercial operations in March 2027. The pipeline will have a capacity of around 240mn m³/yr, but with the possibility to be doubled if demand is sufficient.

Desfa is also planning a 157km pipeline to connect west Macedonia and a metering station at Kardia-Kozani, with a planned capacity of around 440mn m³/yr. This project will help to enable gas supply to district heating installations in the area, Desfa said. Desfa has taken FID and expects commercial operations to start in June 2025.

And Desfa's most expensive plan, at €311mn, will duplicate the 215km main transmission line from Karperi to Komotini. This will increase capacity from north to south and aims to eliminate bottlenecks for the provision of firm capacity from new entry and exit points in the northern part of the system, as well as the provision of firm access to the VTP. This will increase liquidity and provide "equitable access to all northern exit points, and is a "priority project" for Desfa. FID is planned for June 2025, and commercial start-up in March 2027.

A related €151mn plan will duplicate the 100km Patima-Livadeia line, which will increase pressure in the system and enable firm capacity from the Dioriga Gas terminal. FID is planned for October 2025, and commercial operations in March 2027.


Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

16/05/25

Trump says US will soon set new tariff rates

Trump says US will soon set new tariff rates

Washington, 16 May (Argus) — The US will unilaterally set new tariff rates on imports from select trading partners instead of holding negotiations over import tax levels, President Donald Trump said today. In the next 2-3 weeks "we'll be telling people what they will be paying to do business in the US," Trump told a group of US and UAE business executives in Abu Dhabi today. Trump contended that more than 150 US trading partners have expressed interest in negotiating with his administration, adding that "you're not able to see that many countries." Trump's administration since 5 April imposed a 10pc baseline tariff on imports from nearly every US trading partner — with the notable exception of Canada, Mexico and Russia. Trump paused his so-called "reciprocal tariffs" until 8 July, nominally to give his administration time to negotiate with foreign countries subject to those punitive rates. The reciprocal tariffs would have added another 10pc on top of his baseline tariff for imports from the EU, while the cumulative rate would have been as high as 69pc on imports from Vietnam. Trump in April suggested that 200 deals with foreign trade partners were in the works. Treasury secretary Scott Bessent has said the US is only negotiating with the top 18 trading partners. The trade "deals" clinched by the Trump administration so far merely set out terms of negotiations for agreements to be negotiated at a later date. The US-UK preliminary deal would keep the US tariff rate on imports from the UK at 10pc, while providing a quota for UK-manufactured cars and, possibly, for steel and aluminum. The US-UK document, concluded on 9 May, explicitly states that it "does not constitute a legally binding agreement." The US-China understanding, reached on 12 May, went further by rolling back some of the punitive tariff rates but left larger trade issues to be resolved at a later date. The Trump administration would keep in place a 20pc extra tariff imposed on imports from China in February-March and a 10pc baseline reciprocal tariff imposed in April. The US will pause its additional 24pc reciprocal tariff on imports from China until 10 August. Conversely, China will keep in place tariffs of 10-15pc on US energy commodity imports that it imposed on 4 February, and 10-15pc tariffs on US agricultural imports, imposed in March. It will maintain a 10pc tariff on all imports from the US that was imposed in April, but will pause an additional 24pc tariff on all US imports until 10 August. These rates are on top of baseline import tariffs that the US and China were charging before January 2025. By Haik Gugarats Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

Kuwait's Kufpec gets OK to develop Indonesian gas field


16/05/25
16/05/25

Kuwait's Kufpec gets OK to develop Indonesian gas field

Singapore, 16 May (Argus) — Kuwait's Kufpec, a unit of state-owned KPC, has won approval from the Indonesian government for a plan of development for the Anambas gas field located in the West Natuna Sea offshore Indonesia. The Anambas field is located in the Natuna basin and has an estimated gas output of about 55mn ft³/d. Kufpec will invest around $1.54bn into the development of the field, which is planned to come on stream in 2028. The approved plan of development outlines a phased strategy to unlock the gas and condensate potential of the field, said upstream regulator SKK Migas. The regulator will encourage Kufpec to accelerate efforts and bring the project on stream by the fourth quarter of 2027, said the head of SKK Migas, Djoko Siswanto. The development of the field will include drilling production wells and installing subsea pipelines to transport gas from Anambas to existing facilities in the West Natuna transportation system. Kufpec in 2022 announced the discovery of gas and condensate at the Anambas-2X well in the Anambas block. The Anambas block was awarded to Kufpec Indonesia in 2019 through a bidding process. The company holds a 100pc participating interest in the block and has a 30-year production sharing licence, including a six-year exploration period. The approval of the plan of development marks a step towards the project's final investment decision. It also shows that the upstream oil and gas sector in Indonesia is still attractive to domestic and foreign firms, said Djoko. The field is expected to be able to transport gas to domestic and regional markets, support Indonesia's energy security, and drive economic growth, according to SKK Migas. Indonesia continues to prioritise oil and gas expansion to maintain economic growth. Investment in oil and gas rose from $14.9bn in 2023 to $17.5bn in 2024, according to the country's energy ministry. By Prethika Nair Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

Greece’s Alexandroupolis LNG off line until mid-Aug


15/05/25
15/05/25

Greece’s Alexandroupolis LNG off line until mid-Aug

London, 15 May (Argus) — Greece's 4.3mn t/yr Alexandroupolis LNG import terminal will remain off line until 15 August, after which it will return to 25pc of capacity for the remainder of the gas year, an updated urgent market message (UMM) from operator Gastrade says. The terminal has been off line since 28 January because of damage to the booster pumps on the floating storage and regasification unit, Gastrade said, and it will remain fully unavailable until 15 August, after which onward regasification services will resume capped at 25pc of maximum capacity, or about 42 GWh/d, with available redundancy for the booster pumps. This availability will be offered for 15 August-30 September only under "certain operational and commercial conditions", Gastrade specified, and several market participants were unsure of what this phrase meant or whether regasification would in fact be possible at all during this period. From the start of the new gas year on 1 October, the 25pc cap will be lifted, but "certain operation constraints may remain for a limited period of time", the operator said. The previous version of the the UMM listed the shutdown end date as 15 May, although Gastrade had already told Argus in April that it did not expect to return to full operations until October . By Brendan A'Hearn Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

SEFE sells only 900GWh of Rehden gas storage space


15/05/25
15/05/25

SEFE sells only 900GWh of Rehden gas storage space

London, 15 May (Argus) — German gas storage operator Sefe sold less than a fifth of the capacity on offer at its Rehden site in an auction on Thursday — the first capacity sold at the site for the current storage year. Sefe offered 5TWh and received bids in excess of this, but said it allocated only 900GWh, suggesting most bids were below its reserve price. German THE prices for delivery over the remainder of the summer, including the balance-of-May market, closed €2.08/MWh below the following winter price and €2.18/MWh below the first-quarter 2026 price on Wednesday. The 900GWh was the first allocated space at the site for the current storage year, after one unsuccessful auction in January and one last week. The German government last month halved the mandatory fill level at the site to 45pc by 1 November. Now there is capacity booked, there might be scope for Rehden not to be fully emptied, given that there is still 1.1TWh of gas in the 45TWh site. There is a two-month period during which capacity holders can withdraw their gas after the beginning of the storage year, and withdrawals have continued at the site since 1 April. Sefe said it will publish further details on upcoming auctions for the capacity not yet marketed "in a timely manner". Injections at Rehden would have to start by 17 August to meet the 45pc mandate, according to Argus calculations, factoring in 18.5 days of maintenance in October. Under the previous 90pc mandate, injections would have had to start before the end of May, taking Rehden's injection curve into account. By Till Stehr Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

France consults on expanded biofuels mandate


15/05/25
15/05/25

France consults on expanded biofuels mandate

London, 15 May (Argus) — France has opened consultation on the transposition of part of the recast renewable energy directive (RED III) into national law, which would replace the current system with a new one called "incentive for the reduction of the carbon intensity of fuels" (IRICC). The proposal introduces two separate sets of requirements for transport fuels. The first is for greenhouse gas (GHG) emissions reductions, broken down by transport sectors — road, aviation, maritime, LPG and natural gas for vehicles, which could be CNG or LNG (see table). In the current draft, the GHG reduction target for the road sector will start at 5.9pc in 2026, rising to 10.6pc in 2030 and 18.7pc in 2035. For aviation, the target starts at 2.5pc in 2026, rising to 5.8pc in 2030 and 18.8pc in 2035. The GHG mandate levels include a gradual phasing-in of new fuel sectors – river and maritime fuels, fuel gasses, and aviation. To meet the overall RED III target of 14.5pc emissions reduction by 2030, the national French target includes the biofuels mandates, a share for rail transport, and a share or private vehicle charging. The second set of requirements is a renewable fuel requirement by energy content, which is broken down by fuel type — diesel, gasoline, LPG and natural gas fuels and marine fuel (see table). The blending requirements for diesel start at 9pc in 2026, rising to 11.4pc in 2030 and 16pc in 2035. For gasoline, the mandates start at 9.5pc in 2026, rising to 10.5pc in 2030 and 14.5pc in 2035. Finally, the proposal includes a set of sub-mandates for advanced fuels and renewable hydrogen . The advanced biofuels mandate would start at 0.7pc in 2026, rising to 1.95pc in 2030 and 2.6pc in 2035. Users of renewable fuels of non-biological origin (RFNBOs) would not be subject to the advanced sub-mandate. In feedstock restrictions, the crop cap will rise to 7pc from 6.2pc in 2030 and 2035, while the limit for fuels made from feedstocks found in Annex IX-B of RED will be at 0.6pc in 2026, 0.7pc in 2030 and 1pc in 2035 for diesel and petrol. Aviation fuel will not have a IX-B cap until 2030, and from then it will be 6pc. Mandate compliance would be managed by a certificate system through the CarbuRe registry, with a compliance deadline of 1 March the following year. Public electric vehicle charging would also generate tickets, although the amount of tickets generated by charging light passenger vehicles would be reduced from 2031 to reach 50pc in 2035. Renewable hydrogen used in transport would also generate tickets counting towards the hydrogen sub-quota and reduce the overall GHG savings requirement. Public charging stations will start generating fewer tickets for electric passenger vehicles from 2031 to 50pc by 2035. France is also considering steep penalties for non-compliance, at €700/t CO2 not avoided for the GHG reduction requirement and at €40/GJ for the fuel targets. The penalty for not meeting hydrogen and advanced fuel sub-targets would be doubled, at €80/GJ. The consultation is open for comments until 10 June. By Simone Burgin Proposed GHG reduction by transport sector % 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 Road and non-road diesel 5.9 7.1 8.3 9.5 10.6 13.2 14.8 16.2 17.5 18.7 Aviation 2.5 3.3 4.1 4.9 5.8 8.4 10.8 13.3 15.9 18.7 RFNBO sub-target (% en.) 0.0 0.0 0.0 0.0 1.2 1.2 2.0 2.0 2.0 5.0 Maritime 2.5 3.25 4.0 5.0 6.0 7.0 8.0 10.0 12.0 14.5 RFNBO sub-target (% en.) 0.0 0.0 0.0 0.0 1.2 1.2 1.2 1.2 2.0 2.0 LPG and natural gas fuels 0.0 0.0 2.7 6.3 10.6 13.2 14.8 16.2 17.5 18.7 DGEC Proposed energy content mandate by fuel type % (en.) 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 Diesel 9.0 9.5 10.1 10.7 11.4 12.2 13.0 13.8 14.9 16.0 Petrol 9.5 9.7 10.0 10.2 10.5 11.1 11.8 12.6 13.4 14.5 Natural gas fuels 0.0 0.0 3.0 7.0 12.0 15.0 16.0 18.0 19.0 21.0 LPG 0.0 0.0 3.0 7.0 12.0 15.0 16.0 18.0 19.0 21.0 Marine fuel 2.9 3.8 4.7 5.9 7.1 8.2 9.4 11.8 14.1 17.1 DGEC Proposed caps and sub-targets % (en.) 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 Feedstock caps Crop feedstocks 6.2 6.4 6.6 6.8 7.0 7.0 7.0 7.0 7.0 7.0 Annex IX-B feedstocks* 0.6 0.6 0.65 0.7 0.7 0.75 0.8 0.85 0.9 1.0 Cat. 3 tallow 0.5 0.6 0.6 0.6 0.6 0.6 0.7 0.7 0.7 0.7 Tall oil 0.1 0.1 0.1 0.1 0.15 0.15 0.15 0.15 0.15 0.2 Fuel sub-targets Advanced feedstocks 0.7 0.95 1.25 1.6 1.95 2.0 2.1 2.25 2.4 2.6 RFNBOs/Renewable hydrogen 0.05 0.2 0.5 1.0 1.5 1.6 1.7 1.8 1.9 2.0 *For diesel and petrol Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

Generic Hero Banner

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more