Generic Hero BannerGeneric Hero Banner
Latest market news

Greece's Desfa to front-load gas grid expansion plans

  • Market: Natural gas
  • 10/09/24

Greek transmission system operator Desfa plans to complete nearly all the gas projects in its updated 10-year development plan (TYDP) within the next three years.

Desfa's projected spend on all projects comes to over €1.37bn, of which €1.34bn would be used within the next three years. The most important of these projects are presented below, split by category.

Interconnectors

Desfa expects the 1.5bn m³/yr Greece-North Macedonia interconnector to start commercial operations in January 2026, a delay of roughly a year from the timeline it gave in October 2023.

The pipeline will run from Nea Messimvria — where Azeri gas enters the Greek grid — to Gevgelija and will cost around €92mn.

LNG terminals

The connection of the Dioriga LNG terminal will start commercial operations in December 2026, according to the latest TYDP, 1½ years later than previously envisaged.

Desfa expects to reach a final investment decision (FID) on a metering and regulating station to connect the planned Dioriga LNG terminal in February 2025.

Developer Motor Oil Hellas recently told Argus it plans to make FID on the project by the end of this year. The project will cost Desfa around €21mn and will be financed through connection fees. The new entry point will have a capacity of around 11.8mn m³/d, or 4.3bn m³/yr.

Desfa expects a new small-scale jetty already under construction at Revithoussa to start commercial operations in December 2025. The €38mn project will enable ships with capacities of 1,000-30,000m³ of LNG to unload and reload.

And Desfa has also taken FID on a compressor station for Revithoussa, which will allow for boil-off gas to be sent into the transmission system rather than flared. Commercial operations are envisioned to start in May 2025.

No mention of grid connections for the Argo floating storage and regasification unit or Thessaloniki LNG projects were included in the TYDP, throwing their future into further doubt following recent delays.

Power plants

Desfa included multiple pipeline connections to gas-fired power plants in the TYDP.

The operator expects the 877MW Thermoilektriki Komotinis plant's connection to the grid to start commercial operations in October. It will have a capacity of around 3.4mn m³/d, or 1.24bn m³/yr. The project's operators expect test operations to begin this autumn.

Another project will connect Elpedison's planned 826MW plant near Thessaloniki, with a capacity of around 1.14bn m³/yr. Desfa envisions commercial operations beginning in November 2025.

A third project would connect to an 840MW plant at Alexandroupolis and start commercial operations in May 2027. Lastly, Desfa expects a project connecting the 873MW Larisa Thermoelectriki plant to start commercial operations in mid-2027. Pipeline capacities for these two projects were not disclosed, but would likely be similar to the first two.

Compressor stations

Several compressor station plans have been delayed, notably at Komotini and Ampelia.

The two expansion phases at Komotini have been pushed back by six months to March and June 2025, respectively, because of delays during the permitting process. The project will increase the system's "technical adequacy", as well as its capacity, according to Desfa.

And Desfa expects the compressor station at Ampelia, a crucial part of enabling higher north to south transmission, to start commercial operations only in June 2025. The nine-month delay is because of "extreme weather events" in the area in 2023.

And a booster compressor for the Trans-Adriatic pipeline at Nea Messimvria — which will enable fully bidirectional flows — is scheduled to start commercial operations in December 2025. Permitting delays have pushed back the start date by more than a year.

Domestic grid

Several large projects are also in the works to expand the domestic grid.

Desfa plans a 145km pipeline to connect the city of Patras and its industrial area to the grid, expecting FID in June 2025 and the start of commercial operations in March 2027. The pipeline will have a capacity of around 240mn m³/yr, but with the possibility to be doubled if demand is sufficient.

Desfa is also planning a 157km pipeline to connect west Macedonia and a metering station at Kardia-Kozani, with a planned capacity of around 440mn m³/yr. This project will help to enable gas supply to district heating installations in the area, Desfa said. Desfa has taken FID and expects commercial operations to start in June 2025.

And Desfa's most expensive plan, at €311mn, will duplicate the 215km main transmission line from Karperi to Komotini. This will increase capacity from north to south and aims to eliminate bottlenecks for the provision of firm capacity from new entry and exit points in the northern part of the system, as well as the provision of firm access to the VTP. This will increase liquidity and provide "equitable access to all northern exit points, and is a "priority project" for Desfa. FID is planned for June 2025, and commercial start-up in March 2027.

A related €151mn plan will duplicate the 100km Patima-Livadeia line, which will increase pressure in the system and enable firm capacity from the Dioriga Gas terminal. FID is planned for October 2025, and commercial operations in March 2027.


Sharelinkedin-sharetwitter-sharefacebook-shareemail-share

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

News
22/05/25

India's Petronet LNG delays Dahej terminal expansion

India's Petronet LNG delays Dahej terminal expansion

Mumbai, 22 May (Argus) — India's state-run LNG terminal operator Petronet LNG has delayed commissioning the 5mn t/yr capacity addition at its Dahej terminal to September, from the previous March deadline, chief executive officer Akshay Kumar Singh said in a press conference this week. The expansion will take the entire capacity of the terminal to 22.5mn t/yr. The firm has cited several challenges, including logistics and recent security concerns owing to cross-border tensions between India and Pakistan, for causing the delay. Petronet commissioned two storage tanks , each with a capacity of 180,000m³, at Dahej in September last year, taking the total to eight storage tanks. The company is also in the process of building a 2.5km jetty that can accommodate Q-Max LNG tankers as well as receive propane and ethane, besides LNG at its upcoming petrochemical plant. Petronet has also announced plans to build a new 5mn t/yr import facility at Gopalpur on the country's east coast, with commissioning expected by 2027. But the project also faces delays for land acquisition, because it shifted plans to a land-based terminal from the previous floating, storage and regasification unit. Petronet would also have to get the project registered and approved by India's Petroleum and Natural Gas Regulatory Board under the new LNG terminal registration law, which will further add to costs and delays. It will take 3-4 years from receipt of all approvals to complete the project, Petronet officials said in an analysts' call back in October 2024. By Rituparna Ghosh Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

Find out more
News

New Zealand to invest $119mn in gas fields


22/05/25
News
22/05/25

New Zealand to invest $119mn in gas fields

Sydney, 22 May (Argus) — The New Zealand coalition government will co-invest NZ$200mn ($119mn) over four years in new gas fields to support the country's low natural gas supply, it announced today in its 2025 budget release. This is part of efforts to address the gas shortage risk and will take the government's commercial stake to up to 10-15pc in new gas field developments by the private sector that feed the domestic market. Further details were not disclosed. Natural gas will be critical in New Zealand's energy generation for at least another 20 years, resources minister Shane Jones said on 22 May. The government must stand by the petroleum sector as a co-investor with private companies to get through winter periods and counter the country's reliance on imported thermal coal, according to Jones. The coalition government plans to ensure reliable generation from coal, oil, gas or geothermal resources , Jones said in 2024. New Zealand has been facing a gas shortage for months, and domestic utility Meridian Energy called for an ease in regulations to allow LNG import facilities in early 2025. The country's national gas production fell to its lowest level since 1983 in October-December 2024. By Susannah Cornford Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

News

US gas market expected to tighten in 2026


20/05/25
News
20/05/25

US gas market expected to tighten in 2026

New York, 20 May (Argus) — US natural gas producers and analysts are forecasting a tighter market in 2026 than previously expected because of rising LNG exports, a slowdown in crude production and a reluctance on the part of gas-focused producers to ramp up supply. The market has already tightened this year as cold winter weather balanced the previously oversupplied domestic market and Venture Global's Plaquemines LNG terminal ramped up faster than expected. Nymex gas delivery for 2026 at the US benchmark Henry Hub settled Tuesday at $4.30/mmBtu, up from $3.91/mmBtu at the start of the year. US LNG exports are expected to rise by 19pc to 14.2 Bcf/d this year, followed by a 15pc increase to 16.4 Bcf/d in 2026, the US Energy Information Administration forecasts. Meanwhile, tariff-induced economic uncertainty and plans by Opec+ to boost supply have lowered crude prices this year, which will probably throttle growth in the Permian basin, a prolific US oil field in west Texas and southeast New Mexico that accounted for 22pc of US gas supply in 2024. US onshore crude production has likely peaked as activity slows in response to the recent decline in oil prices, Diamondback Energy chief executive officer Travis Stice said earlier this month. US producer Antero Resources this week forecast a 5.5 Bcf/d supply growth shortfall from 2025-26 as producers fail to keep up with booming LNG exports, pipeline sales to Mexico and rising gas-fired power demand. Producers have so far been reluctant to ramp up activity in the Haynesville shale basin of east Texas and northwest Louisiana, the major marginal gas supplier to the US market and a key supplier to the coming wave of new US LNG export terminals, all of which are sited in Texas and Louisiana. Producers' hesitation might be linked to past experience, when they ramped up output for new LNG terminals only for those terminals' in-service dates to get pushed back, contributing to an oversupplied market that depressed prices. Haynesville operators' lack of response to higher gas prices in the first quarter of this year led analyst group Enverus to raise its 2026-30 US gas price forecast to $4/mmBtu. Some producers, including EQT, the second-largest US gas producer by volume, are holding off on locking in the elevated prices for 2026 production with financial derivatives, in part because they want exposure to the possibility of even higher prices. Those producers are "playing a little bit of a dangerous game", according to FactSet senior energy analyst Connor McLean. If a mild summer or delayed LNG terminal start-ups reverse expectations of a tighter market, producers might enter a weaker market in 2026 having "missed their chance" at more opportunistic hedges, McLean said. US LNG out the window Tudor Pickering Holt last week raised its "2026 base case forecast" for US gas prices from $4/mmBtu to $5/mmBtu. The Houston-based investment bank expects the US gas market to shift to a state of "material undersupply" in 2026, potentially pushing domestic prices so high that the price of producing LNG from US gas would exceed prevailing global LNG prices. Aside from short-term price spikes caused by storms or maintenance events, this would be the first instance of the US gas-to-global LNG price "arbitrage window" closing since pandemic-induced demand destruction caused more than 175 US LNG cargoes to be cancelled from April-November 2020, according to consultancy McKinsey. Energy Aspects head of North American gas David Seduski said he would not rule out the possibility of high US gas prices reducing exports, but that is not his "base case". According to Seduski, Europe is "in such desperate need of gas" that in the absence of some geopolitical development that boosts Russian gas sales to Europe, high US gas prices would probably just spur higher European gas prices and keep US sales to the continent profitable. Henry Hub prices would probably have to exceed $7/mmBtu given current global gas prices for US LNG cargoes to start being cancelled, FactSet's McLean said. By Julian Hast Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

News

Shell CEO defends 'resilient investment strategy'


20/05/25
News
20/05/25

Shell CEO defends 'resilient investment strategy'

London, 20 May (Argus) — Shell chief executive Wael Sawan defended the company's "resilient investment strategy" at its annual shareholder meeting today, as directors faced a barrage of questions from climate-focused investors. A resolution calling for more details on Shell's LNG strategy gained over 20pc support, a level consistent with climate-related votes in previous years . But absent this year were the disruptive climate protests that have marked past meetings. This was partly due to Shell's choice of venue, London's Heathrow Airport, which has a five-year High Court injunction banning environmental protests on site. Still, climate-conscious shareholders dominated the discussion. One questioned how Shell could justify expanding oil and gas operations when the IEA's net zero emissions by 2050 scenario suggests no new oil and gas projects are needed. Shell's chairman Andrew Mackenzie responded that the IEA's scenario is just one of many and includes conditional commitments made by governments that may not materialise. "We see a phase of continuing growth, particularly in the use of gas and especially in LNG, that we think is appropriate to invest in," he said. Sawan pointed out that most of the net present value from Shell's oil and gas projects will be realised before 2040, "and so this is a very resilient investment strategy that we are offering our shareholders". He also highlighted that Shell has $20bn of capital invested in low-carbon alternatives such as biofuels, hydrogen and electric vehicle charging. "It is in our interest... to see that market grow," he said. A key focus was Resolution 22, filed by the Australasian Centre for Corporate Responsibility (ACCR), which called on Shell to explain how its LNG strategy aligns with its climate goals. "We believe that shareholders still don't have the information that they need to properly assess the risks associated with this strategy," said the ACCR's Sarah Brewin. The scale of Shell's uncontracted LNG out to 2050 exposes the company and its shareholders to "significant risk should prices fall and demand soften", she said. The company's LNG outlook "is highly optimistic and increasingly out of step with global trends", she added. Shell's board opposed the resolution, arguing that its strategy is based on a range of scenarios — including one exploring the impact of AI on energy demand. Its 2025 LNG Outlook, based on Wood Mackenzie data, forecasts a 60pc rise in global LNG demand by 2040, driven by economic growth in Asia and decarbonisation in heavy industry and transport. While the resolution did not pass, Shell said it will prepare a note within six months detailing its LNG market outlook, its LNG business strategy and how these align with its climate commitments. By Jon Mainwaring Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

News

Unsold German storage tightens 3Q global LNG balance


20/05/25
News
20/05/25

Unsold German storage tightens 3Q global LNG balance

London, 20 May (Argus) — A lack of commercial interest in some German storage sites could support European injection demand in the third quarter, when Asian summer demand peaks. Operators are struggling to sell underground storage capacity at the 45TWh Rehden and 11.5TWh Breitbunn sites — probably because the German THE hub's prompt discount to the winter contract is not large enough to cover the reserve price. In Rehden, only 900GWh has been allocated of the 20.5TWh needed to reach the 45pc fill target. A inverted summer 2025-winter 2025-26 spread earlier this year provided no incentive for firms to book space ahead of the storage year, and although the spread normalised last month, it remains too narrow to make some sites attractive. In addition, Rehden is slow-cycling, so capacity holders have less flexibility to react to price movements. That said, these sites would still need be filled at some point this summer to help meet demand in Germany during winter plus EU and German mandates for 1 November. The lack of a commercial incentive to fill storage could prompt the intervention of market area manager THE later in summer, either by subsidising injections — as Italy did in early April — or through direct purchases, as THE did in 2022. THE said on Monday that it currently has no plans to intervene. But an intervention, if any, would probably only take place later in summer, as Rehden injections could start as late as 17 August to reach the 45pc fill target for 1 November. Asian demand Europe's stockbuild has benefited from weak Asian demand, but firms delaying injections to the third quarter are likely to contend with tighter LNG supply as northeast Asian demand peaks. Asian summer imports tend to be at their heaviest in July-August, when high temperatures boost air-conditioning use and power-sector gas burn. LNG imports in China, South Korea, Japan and Taiwan in July-August have on average increased by 6.4pc from May-June over the last three years, according to Kpler data, equivalent to 2.2mn t, or 30 LNG cargoes, over the two months. The European delivered discount to the TTF third-quarter contract has already started to narrow on stronger buying interest from Asia, falling to a 45¢/mn Btu discount from an average discount of 52¢/mn Btu the previous week. That said, part of the increase in Asian demand in the third quarter could be offset by weaker consumption from downstream sectors affected by US tariffs. And Asian delivered LNG prices above $11/mn Btu will probably continue to suppress demand from price-sensitive buyers in China and India, reducing competition for uncommitted Atlantic-basin supply. By Isabel Valverde Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

Generic Hero Banner

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more