Dutch Eemshaven A plant delayed

  • Spanish Market: Electricity
  • 08/12/14

The start of full commercial operations for German utility RWE's new 777MW Eemshaven A coal-fired unit in the Netherlands has been delayed by nearly one month to 31 January 2015.

The unit was previously due to come fully on line on 1 January, but the utility will use the extra time to conduct further boiler optimisations and the contractual trial run for the steam turbine.

Eemshaven A is one of four new higher-efficiency coal-fired units that were originally expected to come on line in the Netherlands this year or earlier, only to suffer delays. Unit B at RWE's Eemshaven plant, also 777MW, is expected to be commissioned on 6 May next year, while Eon's 1070MW Maasvlakte 3 unit is currently scheduled to come on line at the end of January. French GDF Suez's 724MW Rotterdam 1 coal-fired unit is still undergoing its test phase, after missing a number of deadlines for commissioning. GDF Suez has not disclosed an updated start-up date.

sg/ms

Send comments to feedback@argusmedia.com





If you would like to review other ArgusMedia.com content options, request more information about Argus' energy news, data and analysis services.

Copyright © 2014 Argus Media Ltd - www.ArgusMedia.com - All rights reserved.


Generic Hero Banner

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more