Latest Market News

Territorial risks cloud Mexico’s Centauro expansion

  • Spanish Market: Electricity, Natural gas
  • 18/09/26

Territorial risks threaten to delay the second phase of Mexico's Centauro del Norte natural gas pipeline, designed to bring cheaper US Permian basin gas to northwestern power plants, while disparate metrics obscure its rate of progress.

Grupo Carso is building the $1.43bn, approximately 442km (275-mile) pipeline across Baja California and Sonora states. The project will supply two of state-owned utility CFE's newest combined-cycle power plants and add generation capacity in a region facing grid constraints.

The 72km first phase runs from an interconnection with Sempra's Rosarito pipeline near Mexicali to San Luis Rio Colorado, connecting the new plants to existing infrastructure. Mexicali's 641MW Gonzalez Ortega plant began commercial operations in May. CFE is also developing the 648MW San Luis Rio Colorado plant.

Construction of the 365km second phase is not scheduled to begin until early 2027, with completion targeted for December 2028, but market sources doubt that schedule can be met. The expansion would receive Permian gas primarily through the Samalayuca-Sasabe pipeline system and northern cross-border hubs connected to west Texas supplies.

The second phase presents territorial risks that engineering alone cannot resolve, Carlos Alberto Torres, a former official at state-owned Pemex, told Argus. These include its proximity to the El Pinacate y Gran Desierto de Altar biosphere reserve, consultations with Tohono O'odham communities along the Sonoyta-Caborca corridor, rights of way across agricultural land near Caborca and Altar, and security conditions affecting workers and contractors.

None has been confirmed as currently blocking the project, Torres said, but each could delay construction.

Uncertainty has been compounded by the different scopes used to report progress. The energy ministry's 15-year hydrocarbons development plan, released on 7 September, put overall project progress at 7.12pc.

Carso filings, meanwhile, showed progress rising from 47pc at the end of the first quarter to 77pc as of 30 June, likely referring only to the first phase. Those figures measure execution of a $47.85mn contract held by Carso subsidiary CICSA rather than the entire project. Carso's filings also vary in describing Centauro as either a two- or three-phase project.

Carso has not responded to Argus requests for clarification, while the energy ministry's plan provides little detail beyond funding.

"The question is not whether there is money, it is whether we are budgeting for territorial and regulatory risk with the same rigor as capex," Torres said.


Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more