Indonesia scales up renewable energy plans

  • : Coal
  • 21/10/07

Indonesia has raised its new and renewable energy generation target to 51.6pc from an earlier proposal of 48pc in its 2021-30 electricity plan, with an aim of reducing its reliance on thermal power.

The country's energy ministry (ESDM) validated the 2021-30 generation plans of state-owned utility PLN. More than half of the nation's planned 40.6GW generation capacity to 2030 is being targeted from renewables, the ESDM said.

The 10-year plan does not have a provision for new coal-fired power plants except those already committed to and under construction. This creates space for the development of renewables to replace coal-fired generation, the ESDM added. But Indonesia will also add 14.7GW of power capacity, primarily coal-fired generation, over the next two years as these projects were announced earlier and are already under construction.

Indonesia had total generation capacity of 73.34GW as of June this year. Of this, 47pc is coal-fired, gas-fired generation at 28pc and hydropower at 9pc. The rest comes from diesel-fired generation, waste-based power units and renewables. The share of renewables was 3pc or 2.21GW.

Indonesia is the world's largest thermal coal exporter and shipped 407mn t in 2020 from output of 563mn t.

Jakarta has taken steps to reduce greenhouse gas (GHG) emissions, starting with a ban on new coal-fired power projects from 2023, along with plans to retire ageing coal-fired plants. New tax legislation with a provision for carbon taxation has been submitted to the People's Representative Council and has been marked as a priority bill.

Indonesian coal consumption is projected to increase for the next nine years as new generation capacity is brought on line, despite a government drive to reduce GHG emissions, according to PLN.

The increase will come from the under-construction coal-fired power plants. These additional power plants are expected to increase Indonesia's annual power sector coal consumption by 36.7pc from now to 156.3mn t by 2030.

But Indonesian coal output could fall by as much as 47pc from 610mn t in 2019 to 322mn t by 2050 under a low-carbon scenario compatible with the 2015 Paris climate agreement target, according to a long-term projection by the UN Framework Convention on Climate Change.


Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

25/07/08

Australia's Gladstone port coal exports drop in FY25

Australia's Gladstone port coal exports drop in FY25

Sydney, 8 July (Argus) — Coal shipments out of Australia's Gladstone Port — which mainly supports coking coal mines in the northeastern state of Queensland — fell by 2.5pc on the year to 64mn t for the July 2024-June 2025 financial year. The decline was due to a mix of domestic operational and weather challenges, and subdued global steel production. Coal producers in the region faced multiple mine, rail, and port disruptions over 2024-25, beginning less than a month into the financial year. Rail operator Aurizon — which manages the lines linking Queensland's mines to Gladstone Port — closed its 100mn t/yr Blackwater and 30mn t/yr Moura lines for two weeks over July-August 2024. Gladstone Port faced its own challenges later in the year. The LNG and coal hub handled [multiple work stoppages in December]( https://direct.argusmedia.com/newsandanalysis/article/2640101), during tense labour negotiations between the port's management and five worker unions. Coal and LNG exports from Gladstone fell by 9.3pc and 2pc, respectively, that month . Challenges around the port continued into 2025. Global natural resources company Glencore's Oaky Creek mine along Aurizon's Blackwater line has been shut since late-April 2025 due to a water leak from a storage facility. Another mine, US-Australian producer Coronado's Curragh mine, faced cash availability challenges for much of the year. Australian producer Whitehaven Coal, which ships coal out of a number of Queensland ports, including Gladstone, also reported reduced coal sales in January-March because of wet weather. Coal financing issues in Queensland — and the rest of Australia — will likely persist in 2025-26. Australian producer Bowen Coking Coal, which produces both thermal and coking coal at its flagship Burton mine complex, said on 3 July that it may soon need to halt or reduce production at the site, if it is unable to raise capital. The company was suspended from the Australian Stock Exchange (ASX) a few days later and remains suspended. Chinese purchases of Gladstone coal also fell in the 2024-25 financial year as the country's crude steel output waned. China-based steelmakers cut production by 1.7pc on the year in January-May 2025, data from China's National Bureau of Statistic show. Accordingly, China's coal buying from Gladstone also fell 5.2pc on the year, port data showed. Demand for Gladstone coal was largely supported by Vietnamese and Taiwanese buying in 2024-25 (see table) — a trend which is expected to continue over the coming years. Vietnam-based steelmakers bought 4mn t of Gladstone coal over the fiscal year, up from 2.7mn t in 2023-24. The country's coal imports — which include both thermal and coking coal — rose to a 23-month high in May, Vietnamese customs data show. Vietnamese demand for Australian coking coal is expected to remain elevated in 2025-26, pushing up Queensland coal exports , the state government said in June. The state also expects buying from India to rise though coal shipments to the south Asian country fell by 11pc on the year for the 2024-25 financial year to 11.8mn t. By Avinash Govind Gladstone coal exports (July-June financial years) t 2024-25 2023-24 Change (%) Vietnam 4,012,532 2,706,506 48 Taiwan 3,939,110 2,956,583 33 Japan 18,063,450 18,464,123 -2.2 India 11,784,331 13,167,414 -11 China 10,201,030 10,759,961 -5.2 Total 64,291,396 65,961,612 -2.5 * Total includes other countries Source: Gladstone Ports Corporation (GPC) Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

US' Peabody extends Australian coal mine lock-out again


25/07/07
25/07/07

US' Peabody extends Australian coal mine lock-out again

Sydney, 7 July (Argus) — US coal producer Peabody Energy has extended a lock-out of workers at its Australian Metropolitan mine until late on 9 July, because of a continuing dispute with the Mining and Energy Union (MEU). MEU workers will remain barred from entering the mixed thermal, pulverised coal injection (PCI), and hard coking coal mine — which produced 1.8mn t of coal in 2024 — without pay until 9 July, the union and company confirmed on 7 July. Peabody's lock-out began on 28 June and was scheduled to end on 6 July . The company ended the action early on 3 July, but then reintroduced and extended it late on 4 July because of partial work bans. The MEU can launch an unlimited number of work stoppages and limited work bans at Metropolitan, based on a 7 June strike authorisation. The MEU and Peabody remain at odds over the use of contractors at the mine, among other issues. The two groups are scheduled to engage in a Fair Work Commission (FWC) mediation on 8 July. They have already had two FWC mediations over the dispute, said Peabody's vice-president of underground operations Mike Carter on 7 July. Peabody has also met with employees more than 10 times, he added. Metropolitan Coal remains fully committed to ongoing good faith negotiations with its workers, a Peabody spokesperson said on 7 July. MEU workers will rally outside the site early on 8 July, joined by other labour unions. The labour dispute at Metropolitan follows a series of strikes at Peabody Energy's 12mn t/yr Wilpinjong thermal coal mine in February, over a different contract negotiation. By Avinash Govind Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

EU coal burn and output fall to record low in 2024


25/07/03
25/07/03

EU coal burn and output fall to record low in 2024

London, 3 July (Argus) — EU coal consumption and production fell to an all-time low last year, with coal burn nearly halving from 2018 as the solid fuel's role in EU power generation continues to fade progressively. Coal production in the EU fell by 12pc on the year to 242mn t in 2024, while consumption declined by 13pc to 306mn t, according to Eurostat data. This followed a record year-on-year decrease between 2022 and 2023, when production dropped by 21pc and consumption by 23pc. Although the energy crisis in Europe brought on by Russia's invasion of Ukraine in 2022 provided a brief reversal of declining coal burn and output, the EU since 2023 has returned to steadily decreasing its use of coal. Hard coal consumption in the EU was estimated to have fallen to 107mn t in 2024, 51pc less compared with 2018. Poland and the Czech Republic were the only two hard coal producers left in the EU last year, having produced 44mn t and 1.4mn t, respectively. Poland accounted for 43pc of total EU hard coal consumption, while Germany made up 23pc. The Netherlands, France, Italy, Spain, the Czech Republic and Belgium also consumed hard coal last year, but at a much smaller share of total EU hard coal burn of 3-6pc each. Brown coal consumption was estimated to have declined to 198mn t last year, 47pc lower than in 2018. Germany accounted for the largest share of brown coal consumption last year at 46pc, followed by Poland at 21pc, the Czech Republic at 12pc and Bulgaria at 8pc, while Romania and Greece accounted for 4-6pc each. Separately, fossil fuels accounted for 7.2pc of total power generation in the EU last year, while a dominant 47pc of electricity was generated by renewables last year, Eurostat data show. By Shreyashi Sanyal Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

US adds 147,000 jobs in June, jobless rate down


25/07/03
25/07/03

US adds 147,000 jobs in June, jobless rate down

Houston, 3 July (Argus) — US hiring rose more than forecast in June, defying expectations for slowing growth in the face of President Donald Trump's shifting tariff and spending policies. The US added 147,000 nonfarm jobs in June, the Bureau of Labor Statistics (BLS) reported Thursday, exceeding economists' expectations for about 110,000 jobs. Gains for the prior two months were revised up by a combined 16,000 jobs, with May at 144,000. Job growth averaged 146,000 over the 12 months prior to June, BLS said. Fed funds futures after the report showed a 6.7pc probability the Federal Reserve would cut its target rate at the next meeting at the end of July, down from 24pc on Wednesday. The Fed has signaled it will continue to monitor the impacts of the administration's tariff, fiscal and other policies before adjusting policy, even as Trump has publicly lambasted the Fed chief for holding rates steady this year following a full percentage point of cuts last year. The US unemployment rate edged down to 4.1pc from 4.2pc in May and has remained in a range of 4-4.2pc since May 2024. Federal government jobs declined by 7,000 and have dropped by 69,000 since January, reflecting the initial impacts of Trump's efforts to slash the federal workforce, moves that are facing court challenges. Employees receiving severance pay or on paid leave are reported as employed. State government added 47,000 jobs, mostly in education. Health care added 39,000 jobs while social assistance added 16,000. Transportation and warehousing added 7,500 jobs. Manufacturing lost 7,000 jobs. Jobs were little changed in mining, quarrying, and oil and gas extraction; construction; wholesale trade; retail trade; information; financial activities; professional and business services; leisure and hospitality; and other services. Average hourly earnings were up on the year by 3.7pc in June, compared with 3.9pc in May. By Bob Willis Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

Indonesia plans to cut RKAB approval period


25/07/02
25/07/02

Indonesia plans to cut RKAB approval period

Singapore, 2 July (Argus) — Indonesia is planning to reduce the RKAB mining quota period from three years back to one year starting from 2026, said Indonesia's energy and mineral resources (ESDM) minister Bahlil Lahadalia in parliament today. The current RKAB system approves a quota for three years, longer than the previous period of one year. But the Indonesia government is considering cutting the issuance period back to a year. This comes as it tries to address oversupply and price volatility issues and to increase its control over raw mineral supplies. The ESDM has approved a total of 296.1mn t and 261.4mn t nickel RKAB for 2025 and 2026, respectively, so far this year. It remains unclear what will happen to the quota that has been approved for 2026. The ESDM has approved an RKAB for thermal coal at 917.2mn t for 2025, slightly lower than the 922.1mn t accepted in the 2024 work plan. But actual coal output is typically below RKAB approval levels. The country has set an output target of 739.7mn t for 2025. The country's coal output reached 834.1mn t in 2024, against a target of 710mn t. Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.