UK government sets out preferred power Beccs model

  • : Biomass, Electricity
  • 22/08/11

The UK government is proposing a "minded-to" business model to support bioenergy with carbon capture and storage for power (power Beccs) which consists of a contract for difference for electricity generation (CfDe) combined with a CfD for carbon (CfDc).

The department for business, energy and industrial strategy (BEIS) set out its minded-to model (CfDe+CfDc) along with three other short-listed alternatives on 11 August as it launched a consultation on power Beccs. The other three models that Beis analysed internally were a CfDc alone, a CfDe with a negative emissions payment (NEP), and a CfDe combined with an NEP and the emissions trading scheme (ETS).

The models were assessed based on five main criteria — affordability, benefit maximisation, cost minimisation, investment potential, and timeline.

BEIS selected the CfDe+CfDc model as its preferred one as it offers a combination of a CfD for electricity generation and carbon. It differs from the other options mostly as it "allows for flexibility to include negative emissions in any appropriate carbon markets in the future", meets the 'polluter pays' principle and could reduce the proportion of support payments.

Under this model, the CfDe strike price would be set "equivalent to the cost of generating power from biomass on an unabated basis and the CfDc strike price would need to cover the incremental costs associated with adding carbon capture and storage capability and operating the plant on an abated basis". A 10 to 15-year contract length has been proposed for the minded-to business model.

BEIS is asking stakeholders whether they agree with the minded-to CfD framework, and if they think the power Beccs projects should be incentivised to run as base-load or flexibly. It is also looking into whether there are alternatives to the business model and support framework. It is also seeking views on whether a consumer price indexed (CPI) strike price option similar to the existing CfD scheme for biomass generation that would require the project to bear the risk of biomass costs was an appropriate allocation of risk. It will accept feedback until 8 October.

BEIS is also considering options on how to support generators with transport and storage (T&S) network related risks. One alternative is allowing T&S charges to pass-through cost to generators as a separate third-stream payment; another option is to allow such charges to be an integrated part of the payment mechanism.

The government is also undertaking work with the chief scientific adviser to scientifically prove the net-negativity of power Beccs and the sustainability of biomass used as fuel. It will publish the outcomes of this study.

It launched a consultation for development of a greenhouse gases removal (GGR) business model in July, but such a model was not deemed suitable for power Beccs, which requires a specific framework "to ensure correct behaviours are incentivised, both in relation to the grid, and to the wider societal benefit of negative emissions". It is therefore developing a bespoke business model for power Beccs, "reflective of the advanced technological readiness of this specific technology and the significant co-benefits of both power generation and negative emissions".

Market barriers

A credit for carbon removal for utilities was not proposed under previous frameworks. But there are a number of market barriers preventing scaling-up and investment in Beccs, despite the high level of technological readiness, and the consultation will consider actions the government could take to help companies overcome such barriers, Beis said.

BEIS said it recognises there are no viable investment frameworks that would enable power Beccs to deploy at scale in Great Britain, and that private market-based investment was hindered by risks attached to a variety of operational and economic challenges common to bioenergy and carbon capture and storage technology. Such risks include wholesale power price volatility, biomass fuel price risk, cross-chain risk with a T&S network, current lack of predictable, long-term demand and stable revenue streams to produce negative emissions, immaturity of carbon removal markets and uncertainty around future scales and prices, regulatory and policy uncertainty over GGRs long term, and new technology development risks.

Power Beccs is expected to "deliver a steady increase of engineered removals of greenhouse gases (GHG) between the late 2020s and 2035", which will help the UK to achieve its net-zero targets through delivery of negative emissions, and to reach the 5mn t/yr of GHG removals by 2030, BEIS said. Power Beccs also helps boost system resilience, with sustainable biomass having "proven to be a reliable source of base-load generation", it added.

The government has been working on such a business model since it published the biomass policy statement in November last year, in which it stated it would support future biomass-fired generation only for large-scale plants with CCS.

"The government is paving the way for the UK to lead the world in deploying vital carbon removal technologies like Beccs. This could kickstart a whole new sector of the economy, creating green growth on an even greater scale than we have seen in the UK previously with renewables like wind and solar," utility Drax chief executive Will Gardiner said today. In April, Drax put a cost of about £150 to generate 1MWh of power and remove 1t of carbon dioxide from the atmosphere. It aims to commission Beccs at one of its 645MW pellet-fired units by 2027 and at a second unit by 2030. It aims to deliver 8mn t/yr of negative emissions in the UK by 2030.

The 420MW dedicated biomass-fired Lynemouth power plant has also completed a feasibility study on Beccs and is exploring further investment opportunities in the technology.

The UK aims to have a fully decarbonised, reliable and low-cost power system by 2050, predominantly composed of wind and solar in 2035 and in 2050 — its medium and long-term timelines, respectively.


Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

24/04/30

G7 countries put timeframe on 'unabated' coal phase-out

G7 countries put timeframe on 'unabated' coal phase-out

London, 30 April (Argus) — G7 countries today committed to phasing out "unabated coal power generation" by 2035 — putting a timeframe on a coal phase-out for the first time. The communique, from a meeting of G7 climate, energy and environment ministers in Turin, northern Italy, represents "an historic agreement" on coal, Canadian environment minister Steven Guilbeault said. Although most G7 nations have set a deadline for phasing out coal-fired power, the agreement marks a step forward for Japan in particular, which had previously not made the commitment, and is a "milestone moment", senior policy advisor at think-tank E3G Katrine Petersen said. The G7 countries are Italy — this year's host — Canada, France, Germany, Japan, the UK and the US. The EU is a non-enumerated member. But the pledge contains a caveat in its reference to "unabated" coal-fired power — suggesting that abatement technologies such as carbon capture and storage could justify its use, while some of the wording around a deadline is less clear. The communique sets a timeframe of "the first half of [the] 2030s or in a timeline consistent with keeping a limit of 1.5°C temperature rise within reach, in line with countries' net-zero pathways". OECD countries should end coal use by 2030 and the rest of the world by 2040, in order to align with the global warming limit of 1.5°C above pre-industrial levels set out in the Paris Agreement, according to research institute Climate Analytics. The countries welcomed the outcomes of the UN Cop 28 climate summit , pledging to "accelerate the phase out of unabated fossil fuels so as to achieve net zero in energy systems by 2050". It backed the Cop 28 goal to triple renewable energy capacity by 2030 and added support for a global target for energy storage in the power sector of 1.5TW by 2030. The group committed to submit climate plans — known as nationally determined contributions (NDCs) — with "the highest possible ambition" from late this year or in early 2025. And it also called on the IEA to "provide recommendations" next year on how to implement a transition away from fossil fuels. The G7 also reiterated its commitment to a "fully or predominantly decarbonised power sector by 2035" — first made in May 2022 and highlighted roles for carbon management, carbon markets, hydrogen and biofuels. Simon Stiell, head of UN climate body the UNFCCC, urged the G7 and G20 countries to lead on climate action, in a recent speech . The group noted in today's outcome that "further actions from all countries, especially major economies, are required". The communique broadly reaffirmed existing positions on climate finance, although any concrete steps are not likely to be taken ahead of Cop 29 in November. The group underlined its pledge to end "inefficient fossil fuel subsidies" by 2025 or earlier, but added a new promise to "promote a common definition" of the term, which is likely to increase countries' accountability. The group will report on its progress towards ending those subsidies next year, it added. Fostering energy security The communique placed a strong focus on the need for "diverse, resilient, and responsible energy technology supply chains, including manufacturing and critical minerals". It noted the important of "guarding against possible weaponisation of economic dependencies on critical minerals and critical raw materials" — many of which are mined and processed outside the G7 group. Energy security held sway on the group's take on natural gas. It reiterated its stance that gas investments "can be appropriate… if implemented in a manner consistent with our climate objectives" and noted that increased LNG deliveries could play a key role. By Georgia Gratton Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Japan’s Chugoku delays Shimane No.2 reactor restart


24/04/30
24/04/30

Japan’s Chugoku delays Shimane No.2 reactor restart

Tokyo, 30 April (Argus) — Japanese utility Chugoku Electric Power has postponed the restart of its 820MW Shimane No.2 nuclear reactor in western Japan's Shimane prefecture from August to December, as reinforcement works are taking longer than expected. The reinforcement works are taking longer, as the utility is also conducting facility inspections to prepare to reactivate the reactor after an extended closure since January 2012 for stricter nuclear safety inspections, said Chugoku on 30 April. Chugoku previously planned to complete the reinforcement works in May , but has now postponed this to October. The utility had aimed to begin normal operations at the reactor in September , but has now delayed it to January 2025. Chugoku had previously modified the restart schedule multiple times . The return of the Shimane No.2 reactor could have helped Chugoku reduce its reliance on thermal generation fuels including oil, LNG and coal, especially during the peak power demand season of summer. Chugoku is currently building the 1,373MW No.3 reactor at Shimane, aiming to complete its safety-enhanced construction sometime during April-September 2025. The company has filed an application with the Nuclear Regulation Authority for a safety screening of the No.3 reactor. Its 460MW Shimane No.1 reactor was scrapped in April 2015. By Nanami Oki Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Gas-fired units win Japan's clean power auction


24/04/30
24/04/30

Gas-fired units win Japan's clean power auction

Osaka, 30 April (Argus) — A planned 10 gas-fired generation units have won Japan's first long-term zero emissions power capacity auction, with the awarded capacity totalling nearly 6GW, or auction volumes sought for the first three years of the programme. Japan launched the clean power auction system from the April 2023-March 2024 fiscal year, aiming to spur investment in clean power sources by securing funding in advance to drive the country's decarbonisation towards 2050. The auction generally targets clean power sources — such as renewables, nuclear, storage battery, biomass, hydrogen and ammonia. But the scheme also applies to a new power plants burning regasified LNG as an immediate measure to ensure stable power supplies, subject to a gradual switch from gas to cleaner energy sources. The first auction held in January saw 10 new gas-fired units with a combined capacity of 5.76GW secure the funding of ¥176.6bn/yr ($1.12bn), the nationwide transmission system operator Organisation for Cross-regional Co-ordination of Transmission Operator (Occto), which manages the auction, said on 26 April. All winners can receive the money for 20 years through Occto, which collect money from the country's power retailers, although they need to refund 90pc of other revenue. Winners with a new gas-fired project should start commissioning their plants within six years and then begin refurbishment work to introduce clean fuels and technology within 10 years after commissioning. This means all the projects selected in the 2023-24 auction need to start operations by the end of 2030-31. Hokkaido Electric Power previously planned to begin operations of its Ishikariwan-Shinko No.2 gas-fired unit in December 2034 but it has advanced the start-up to 2030-31. Japan has secured a total of 9.77GW net zero capacity through the 2023-24 auction. Contract volumes include 1.3GW of nuclear, 1.1GW of storage batteries, 770MW for ammonia co-firing, 55.3MW hydrogen co-firing, 199MW biomass and 577MW of hydroelectric power projects, along with the 5.76GW of gas-fired projects. By Motoko Hasegawa Japan 2023-24 decarbonisation power capacity auction result Winner Power plant MW* Planned start-up Hokkaido Electric Power Ishikariwan-Shinko No.2 551 FY2030 Tohoku Electric Power Higashi Niigata No.6 616 FY2030 Kansai Electric Power Nanko No.1 592 FY2029 Kansai Electric Power Nanko No.2 592 FY2030 Kansai Electric Power Nanko No.3 592 FY2030 Chugoku Electric Power Yanai new No.2 464 Mar '2030 Tokyo Gas Chiba Sodegaura Power Station 605 FY2029 Osaka Gas Himeji No.3 566 FY2030 Jera Chita No.7 590 FY2029 Jera Chita No.8 590 FY2029 Total gas-fired capacity 5,756.3 Source: Occto, Argus * Sending end capacity Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

APLNG's Jan-Mar output higher: Origin


24/04/30
24/04/30

APLNG's Jan-Mar output higher: Origin

Sydney, 30 April (Argus) — The 9mn t/yr Australia Pacific LNG (APLNG) project in Queensland state produced and sold more LNG than the previous quarter and year earlier, Australian independent Origin Energy said in its January-March results. Output rose from the final quarter of 2023 because of the power failure of a vessel docked at APLNG's terminal in Gladstone harbour in late November , which prompted upstream operator Origin to cut flows to the liquefaction plant and APLNG to defer three cargoes to 2024. APLNG exported 134PJ (2.4mn t) of LNG through 34 cargoes for January-March, 8pc up from 124PJ and 32 cargoes the previous quarter and 4pc up on the 129PJ and 33 cargoes shipped in January-March 2023. Total APLNG production for July 2023-March 2024, the first three quarters of Origin's fiscal year to 30 June, was 519PJ, 4pc higher than 498PJ a year earlier, because of effective well and field optimisation activities, fewer maintenance disruptions and the continuing benefit of reducing workover backlog resulting in more wells being on line, Origin said. The terminal will take half a train of capacity off line for 12 days in June , following a two-day maintenance period in January. APLNG's domestic gas sales were 36PJ, steady on the previous quarter but higher by 24pc from the 29PJ sold a year earlier. Gas sales volumes for Origin's energy markets business fell by 5pc to 36PJ from 38PJ in January-March 2023. Origin said it continues to negotiate a deal with the government of New South Wales (NSW) regarding the 2,880MW Eraring coal-fired power station's future . The power plant had been due to close in 2025 but insufficient new generation capacity has been completed in NSW for this to occur. "We continue to progress large-scale batteries under development at Eraring and Mortlake power stations and recently announced our first storage offtake agreement from the Supernode battery in Queensland, taking Origin's storage portfolio to around 1GW of capacity once these batteries come on line," chief executive Frank Calabria said on 30 April. By Tom Major APLNG results Jan-Mar '24 Oct-Dec '23 Jan-Mar '23 y-o-y % ± q-o-q % ± Production (PJ) 176 167 165 7 5 Sales (PJ) 168 160 158 6 4 Commodity revenue (A$mn) 2,303 2,149 2,583 -11 7 Average realised LNG price ($/mn Btu) 12.17 11.88 14.50 -15 3 Average realised domestic gas price (A$/GJ) 6.90 6.39 6.17 12 8 Source: Origin Energy Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Japan boosts wood pellet imports in March


24/04/26
24/04/26

Japan boosts wood pellet imports in March

Tokyo, 26 April (Argus) — Japan's wood pellet imports in March rose from a year earlier, with Indonesian supplies hitting a record high of almost 60,000t. Japan imported 531,500t of wood pallets in March, up by 47pc from a year earlier, according to preliminary data released by the country's finance ministry on 26 April. This was also higher by 9pc from February. Imports from Indonesia jumped to 59,353t in March, more than a fivefold increase from 10,796t a year earlier. This significantly exceeded the previous record high of 35,516t in January. But Vietnam remained Japan's top supplier at 247,054t, up by 63pc on the year. Japan received 102,478t of wood pellets from the US in March, with no cargoes delivered in March 2023.Imports from Malaysia also almost tripled to 22,261t from the previous year's 7,591t. Higher March imports sent Japan's total imports in the April 2023-March 2024 fiscal year to around 6.1mn t, up by 29pc from a year earlier. PKS imports But Japan cut imports of palm kernel shell (PKS) in March, down by 30pc from a year earlier. Imports from Indonesia fell by 23pc to 184,384t, while Malaysian supplies declined by 51pc to 40,462t. The start-up of a new biomass-fired power plant in March helped increase Japan's total imports. Japanese renewable power developer Renova in March started commercial operations at its 75MW Ishinomaki Hibarino biomass-fired power plant in northeast Japan's Miyagi prefecture, which burns an undisclosed volume of wood pellets and PKS. But domestic utility Jera's 1,070MW Taketoyo No 5 coal and biomass co-fired power unit in Aichi prefecture has been off line since a fire in January. Fellow utility Tokyo Gas' 51.5MW Fushiki Manyofuto biomass-fired plant in Toyama prefecture also continued to face technical issues after a 7.6 magnitude earthquake hit the Hokuriku area in January. By Takeshi Maeda Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more