Mexican electricity law temporarily suspended: Update

  • : Crude oil, Electricity, LPG, Metals, Natural gas, Oil products
  • 21/03/11

Adds recipient of injunction.

A court temporarily suspended Mexico's new electricity law yesterday, a day after it took effect, signaling the start of a wave of litigation against the controversial reform.

"While this interim relief was requested by one company, it will have general effect," stated a Mexico City court judgment yesterday.

Zuma Energia was awarded the first injunction in relation to its La Orejana solar park in Sonora, but Argus understands that developers EDF and Naturgy also secured injunctions against the law. More are expected tomorrow.

Zuma Energia, originally backed by UK private equity fund Actis and acquired last November by China's State Power Investment, is developing 816MW in wind and solar projects in Mexico.

Mexico's new electricity law was published in the official gazette on 9 March after a fast-tracked legislative process launched by President Andres Manuel Lopez Obrador on 1 February.

The law prioritizes dispatching CFE-generated power regardless of cost or environmental impact, revokes self-supply permits and begins a review process of all long-term power purchase agreements (PPAs) between CFE and independent power producers (IPPs).

The temporary suspension of the law was awarded "to guarantee the rights to competition and a free market," states the decision.

Some 40,924 MW, or 48pc, of Mexico's installed capacity is operated under private-sector generation permits that will all be affected by the reform, lawyers have said, predicting an avalanche of legal action under Mexican law and foreign trade agreements.

The law will impact up to $39bn of investments in the renewable energy sector alone, Mexican wind and solar associations Amdee and Asolmex said.

Lopez Obrador's government has passed a flurry of regulatory changes over the past two years that have sought to strengthen CFE's market position despite the 2014 energy reform that called for an even playing field among market participants. But the courts have largely sided with private company legal action over the changes and the supreme court recently set aside the government's electricity policy because it contravened the constitutional right to free competition.

The government has two days to appeal the judgment.


Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

24/05/01

FERC OK’s Virginia Transco gasline expansion

FERC OK’s Virginia Transco gasline expansion

New York, 1 May (Argus) — The US Federal Energy Regulatory Commission (FERC) today gave Williams the green light to expand natural gas capacity to Virginia by 101mn cf/d (2.9mn m3/d) on its Transco pipeline. The project, called the Commonwealth Energy Connector, involves the construction of 6.3 miles of new pipeline within Transco's existing right-of-way in southeast Virginia, near the border with North Carolina. The project also includes adding horsepower at compressor station 168, west of the new pipeline segment. Williams plans to begin construction this winter and put the project into service by the end of 2025. Environmental advocacy group Sierra Club opposed the project, arguing FERC failed to assess its potential greenhouse gas emissions, rendering its National Environmental Policy Act analysis moot. FERC disagreed, conceding that although the project's final Environmental Impact Statement demonstrated it would contribute to greenhouse gas emissions, the effects of those emissions on the environment could not be measured because FERC lacks the methodology to do so. The US south-Atlantic gas market has become more volatile in recent years as gas and power demand have soared, outpacing pipeline capacity expansions in the region. The combined gas consumption of Virginia and North and South Carolina in 2022 averaged 4.7 Bcf/d, up by 69pc from a decade earlier, US Energy Information Administration data show. Regional gas and power consumption is widely expected to continue climbing through the end of the decade on a massive build-out of data centers , especially in Virginia. By Julian Hast Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Cenovus boosts oil sands output by 4pc in 1Q


24/05/01
24/05/01

Cenovus boosts oil sands output by 4pc in 1Q

Calgary, 1 May (Argus) — Canadian integrated Cenovus Energy increased its oil sands production by 4pc in the first quarter, led by gains at Lloydminster Thermal and Foster Creek heavy crude assets, and the company plans to boost output further to supply the newly opened Trans Mountain Expansion (TMX) pipeline. Cenovus pumped out 613,000 b/d of crude from its oil sands projects in Alberta, up from 588,000 b/d in the same quarter last year, the Calgary-based company reported on Wednesday. This was one of the highest producing quarters for Cenovus' oil sands assets since acquiring Husky in early 2021, second only to the 625,000 b/d produced in the fourth quarter that year. Cenovus has a commitment of about 144,000 b/d on the newly completed 590,000 b/d TMX pipeline, which was placed into service on Wednesday , and the company has plans to push upstream output higher over the next several years across its portfolio to meet its commitment. The pipeline nearly triples the amount of Canadian crude that can reach the Pacific coast without first having to go through the US. First-quarter production from the Lloydminster Thermal segment rose to 114,000 b/d, up from 99,000 b/d a year earlier, because of higher reliability, according to Cenovus. Cenovus' Foster Creek production rose to 196,000 b/d of bitumen, up from 190,000 b/d in first quarter 2023. The company plans to bring another 30,000 b/d online at the steam-assisted gravity drainage (SAGD) asset by the end of 2027 through optimization projects. To the north, Christina Lake's first-quarter bitumen output of 237,000 b/d was steady with previous quarters. The asset is expected to get a significant boost by the end of 2025 when a pipeline connecting the project to output from the neighbouring Narrows Lake asset is completed. The 17 kilometer (11 mile) Narrows Lake tie-back will add 20,000-30,000 b/d of bitumen to Christina Lake, which already ranks as the industry's largest SAGD project. The pipeline is 67pc complete and should be placed into service in early 2025, Cenovus executives said Wednesday on an earnings call. Northeast of Fort McMurray, Alberta, new well pads are planned at Sunrise in 2025, where Cenovus also plans to push production higher by 20,000 b/d. Sunrise produced an average of 49,000 b/d in the first quarter this year, up from 45,000 b/d in the same quarter 2023. Cenovus' output company-wide rose to 801,000 b/d of oil equivalent (boe/d) in the first quarter, up from 779,000 boe/d a year earlier. This includes oil sands, natural gas liquids, natural gas, conventional and offshore assets. Cenovus posted a profit of C$1.2bn ($871mn) in the quarter, up from a C$636mn profit during the same quarter of 2023. By Brett Holmes Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

US gas industry pins hopes on AI power demand


24/05/01
24/05/01

US gas industry pins hopes on AI power demand

New York, 1 May (Argus) — US natural gas producers and pipelines have pivoted almost in unison this year to talking up what they see as one of the strongest bullish cases for gas this decade: surging electricity demand from yet-to-be-built data centers to power artificial intelligence software. EQT, the largest US gas producer by volume, in an investor presentation last week called growing data center demand the "cornerstone" to the "natural gas bull case." Combining its own research with data from the US Energy Information Administration, the gas giant forecast an increase in gas demand of 10 Bcf/d (283mn m3/d) by 2030 to generate electricity, mostly to run data centers. Its more aggressive data center build-out scenario envisions a whopping 18 Bcf/d increase in gas demand through 2030. Total US gas production is currently about 100 Bcf/d. Kinder Morgan, one of the largest US gas pipeline operators, this month forecast 20pc of US power being gobbled up by data centers in 2030, up from a 2.5pc share in 2022. Cobbling together projections from several consultancies and financial advisories, the company said the electricity needed to run artificial intelligence software alone will comprise 15pc of US power demand by 2030. If just 40pc of that demand is met by gas, that would represent an increase in gas demand of 7-10 Bcf/d, it said. This is roughly in line with the high end of US bank Tudor Pickering Holt's forecast for gas demand to power data centers through 2030 (1.3-8.5 Bcf/d) and well above Goldman Sachs' and consultancy Enverus' projections of 3.3 Bcf/d and 2 Bcf/d, respectively. New tech, old problems Separating the wide ranges of these projections is the highly speculative nature of forecasting demand years into the future for competing energy sources to power next-generation technology. But the major upside and downside risks, analysts say, concern the more humdrum challenges of permitting and building out energy infrastructure. Goldman Sachs expects 28GW, or 60pc, of the generation capacity needed to power new data centers through 2030 will come from natural gas — 9GW from combined cycle gas turbines and 19GW from gas peaker plants. But with an average lag of four years from the time a gas transmission project is announced to the time it enters service, to say nothing of the high probability of litigation being brought by environmentalists and landowners, construction and permitting timelines are "the most top of mind constraint for natural gas," the bank said. Indeed, litigation and opposition from state regulators have ultimately led developers to call off several interstate pipeline projects in the eastern US in recent years. The exception to the rule, Equitrans' 2 Bcf/d Mountain Valley Pipeline is moving forward only because congressional action allowed it to bypass federal permitting hurdles. This is a particular problem for the gas industry's hopes of exploiting the data center boom, as a large share of future data centers are slated to be built in the southeast US, far from the major US gas fields. New data centers representing 2 Bcf/d of gas demand in Georgia probably requires a new pipeline into the southeast, FactSet senior energy analyst Connor McLean said. Southeast premium A significant data-center buildout in the southeast without new pipelines could put upward pressure on regional gas prices, McLean said. This could exacerbate the effects of what has become perhaps the most prominent bullish case for US gas: a massive build-out of LNG export terminals along the US Gulf coast. With new export terminals pulling increasing volumes of gas south along the Transcontinental gas pipeline to super-chill and ship overseas in the coming years, the build-out in data centers will likely produce "an even bigger deficit in that southeast (gas) market," EQT chief financial officer Jeremy Knop told investors last week. "We think that market really, in time, becomes the most premium market in the country," he said. By Julian Hast Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Tankers can take TMX crude mid-May: Trans Mountain


24/05/01
24/05/01

Tankers can take TMX crude mid-May: Trans Mountain

Calgary, 1 May (Argus) — Commercial operations for the 590,000 b/d Trans Mountain Expansion (TMX) crude pipeline in western Canada have officially started today, but tankers will not be able to load crude from the line until later this month. Line fill activities, which began on 16 April, are still ongoing for the C$34bn ($25bn) project that stretches from Edmonton, Alberta, to the docks in Burnaby, British Columbia. About 70pc of the volumes needed are in the 1,181 kilometre (733 mile) line, Trans Mountain said on Wednesday. "As of today, all deliveries for shippers will be subject to the Expanded System tariff and tolls, and tankers will be able to receive oil from Line 2 by mid-May," Trans Mountain said. Aframax-size crude tankers started to take position on the west coast last month in anticipation of the new line. But the inability to deliver crude at Burnaby, while still having to pay full tolls, was a concern raised by several shippers on 23 April. "Trans Mountain must be able to receive, transport and deliver a shipper's contract volume," the shippers said in a letter to the CER. The ability to deliver the crude is "clearly central and fundamental qualities of firm service." The CER in November approved interim tolls for the system that will further connect Albertan oil sands producers to Pacific Rim markets. Shippers will, at least initially, pay C$11.46/bl to move crude from Edmonton, Alberta, to the Westridge terminal in Burnaby, British Columbia. The fixed portion accounts for C$10.88/bl of this and has nearly doubled from a C$5.76/bl estimate in 2017. The Canada Energy Regulator (CER) on 30 April gave Trans Mountain a green light to put TMX into service , ending years of uncertainty that the project would ever be completed. The expansion project, or Line 2, nearly triples the capacity of Canadian crude that can flow to the Pacific coast, complementing the original 300,000 b/d line, or Line 1, that has been operating since 1953. By Brett Holmes Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Mitsui makes delayed exit from Paiton power project


24/05/01
24/05/01

Mitsui makes delayed exit from Paiton power project

Tokyo, 1 May (Argus) — Japanese trading house Mitsui completed on 30 April the ¥109bn ($690mn) sale of its stake in Indonesia's 2,045MW Paiton coal-fired power plant in east Java following multiple delays. Mitsui originally tried to complete its exit by the end of March 2022 . It said the procedures with Paiton's offtaker Indonesian state-owned power firm Persero took more time than expected without providing further details. Japanese thermal power producer Jera withdrew from Paiton by selling its 14pc share in 2021. Mitsui sold its 45.515pc share in Paiton Energy, as well as a 45.515pc stake in Netherlands-based subsidiary Minejesa Capital and a 65pc stake in Singapore-based IPM Asia that are related companies of the Paiton project. Mistui sold the stakes to RH International (RHIS), which is a Singapore-based subsidiary of Thai power producer Ratch, and Indonesian power company Medco Daya Abadi Lestari's subsidiary Medco Daya Energi Sentosa (MDES). Paiton Energy is now owned by RHIS, MDES and Qatar-based company Nebras Power. Mitsui did not disclose their ownership ratios. Paiton consists of the 615MW No.7, 615MW No.8 and the 815MW No.3 units, which sell electricity to Persero through an unspecified long-term contract. Mitsui now holds 9.6GW of power capacity assets globally, with 8pc being coal-fired projects. The exit from Paiton cut its coal-fired ratio by 8 percentage points, while raising its renewable ratio by 3 percentage points to 32pc. Growing global pressure against coal-fired power generation likely prompted Mitsui to exit Paiton. Energy ministers from G7 countries this week pledged to accelerate "efforts towards the phase-out of unabated coal power generation". By Nanami Oki Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more