Renewable additions to accelerate in Colombia

  • : Electricity
  • 24/01/19

Non-conventional renewable energy (NCRE) capacity additions in Colombia could accelerate sharply this year as over 1GW of projects are set to come online, after regulatory and social challenges hindered the sector last year.

Colombia added 224MW of new NCRE capacity in 2023, lifting NCRE capacity to 467MW. Additions in 2022 were 243MW.

But the country will reach the 1GW mark by May 2024, according to renewable association SER's director Alexandra Hernandez, a goal that the government had expected to reach by the end of 2023. Long permitting processes, higher taxes for the sale of renewable electricity and community backlash hit a previously projected faster growth in renewables.

More than 1,100MW of solar and almost 32MW of wind projects are currently in the testing phase. If all projects come into operation as scheduled, the country would have 1.55GW of renewable capacity by end of year.

Of the 1,100MW solar plants, five have capacity ranging from 100MW-370MW, another five from 20MW-80MW, and the rest are smaller plants. The solar projects fed over 4,000MWh/day of electricity to the grid in the first week of January, data from grid operator XM show.

Government policies to speed tracking progressseems to be working, Adrian Correa, director of the government's mining and planning unit Upme told Argus. Correa believes the government's target of 6GW of NCRE capacity by August 2026 is likely to be reached given the implementation of periodic monitoring of generation projects. This has helped identify and manage solutions to the environmental, social and permitting problems.

But renewable projects still face hurdles as some communities demand formal consultation processes, even though they do not live in the areas where projects are planned.

Regulation should also be reviewed because the norms say that larger renewable plants must tell XM the prior day how much electricity they will sell to the market. If they fail to deliver the amount committed, XM levies a fine, Alejandro Piñeros, director of regulation at the consulting firm Optima says.

Enel's projects dominate

Among the projects planned to be operational this year are Italian Enel Green Power's 132.2MW Fundacion and 187MW La Loma solar farms.

Both projects are 95pc advanced and should start delivering electricity on a commercial basis during the first half 2024.

Construction of the Guayepo I and II solar farms, with a combined capacity of 486.7MW is more than 60pc advanced. The plants began testing phases on 26 December and will begin commercial operation in the fourth quarter 2024, Enel said. The project costs $290mn and is in the Caribbean Atlantico province.

Guayepo will generate around 1,030 GWh/yr of electricity once completed — equivalent to generating electricity to supply 770,000 inhabitants. Colombia's largest beer company Bavaria will use electricity produced to supply Bavaria's seven breweries after signing a power and purchase agreement (PPA).

Other smaller projects with operations targeted for this year are French firm Green Yellow's solar farms with a combined capacity of 49.5MW.

Meanwhile, the Dinamarca and Versalles solar projects with 14MW of capacity each began commercial operations in the second week of January. The 14MW La Mena will begin commercial operations by the end of January, Green Yellow said.


Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

24/05/20

Japan’s FEPC calls for clearer nuclear policy stance

Japan’s FEPC calls for clearer nuclear policy stance

Osaka, 20 May (Argus) — Japan's Federation of Electric Power Companies (FEPC) has called for a clarification of the country's nuclear power policy, to ensure stable electricity supply and alignment with its net zero emissions goal. The call comes as the government reviews its basic energy policy , which was formulated in 2021 and calls for the reduction of dependence on nuclear reactors as much as possible. But Japan's guidelines for green transformation, which was agreed in February 2023, states that Japan should make the most of existing nuclear reactors. Tokyo should clearly state in its new energy policy that it is necessary to not only restart existing nuclear reactors, but also build new reactors, said FEPC chairman Kingo Hayashi on 17 May. Hayashi is also the president of utility Chubu Electric Power. Hayashi emphasised that to utilise reactors, it would be necessary to have discussions regarding financial support, policy measures that would help ensure cost recovery, address back-end issues in the nuclear fuel cycle and conduct a review of nuclear damage compensation law. Japan's current basic energy policy is targeted for the April 2030-March 2031 fiscal year, when the country's greenhouse gas (GHG) emissions is forecast to fall by 46pc from 2013-14 levels. To achieve this, the power mix in the policy set the nuclear ratio at 20-22pc, as well as 36-38pc from renewables, 41pc from thermal fuels and 1pc from hydrogen and ammonia. Japan typically reviews the country's basic energy policy every three years. Nuclear, as well as renewables, would be necessary to reduce Japan's GHG emissions, although thermal power units would still play a key role in addressing power shortages. But Japan has faced challenges in restarting the country's reactors following safety concerns after the 2011 Fukushima nuclear disaster, with only 12 reactors currently operational. Japan's nuclear generation in 2023 totalled 77TWh, which accounted for just 9pc of total power output. Tokyo has made efforts to promote the use of reactors, after the current basic energy policy was introduced in 2021. The trade and industry ministry (Meti) has updated its nuclear policy, by allowing nuclear power operators to continue using reactors beyond their maximum lifespan of 60 years by excluding a safety scrutiny period in the wake of the 2011 Fukushima nuclear disaster. This could advance the discussion on Japan's nuclear stance, especially if the new basic energy policy includes more supportive regulations. The trade and industry ministry started discussions to review the energy policy on 15 May, aiming to revise it by the end of this fiscal year. It is still unclear what year it is targeting and what ratio will be set for each power source in the new policy. But the deliberation would form a key part of efforts to update the GHG emissions reduction goal, ahead of the submission of the country's new nationally determined contribution in 2025, with a timeframe for implementation until 2035. By Motoko Hasegawa Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Japan’s Jera to handle 35mn t/yr LNG until FY2035-36


24/05/17
24/05/17

Japan’s Jera to handle 35mn t/yr LNG until FY2035-36

Osaka, 17 May (Argus) — Japan's largest LNG importer Jera plans to maintain its LNG handling volumes at no less than 35mn t/yr until the April 2035-March 2036 fiscal year. Rising renewable power supplies and the possible return of more nuclear reactors are likely to pressure LNG demand from Japan's power sector. Jera consumed 23mn t of LNG in 2023-24, down by 3pc on the year, although it handled 35mn t through its global operations during the same year. But Jera needs to secure sufficient LNG supplies to adjust for imbalances in electricity supplies and ensure power security, through more flexible operations. It is also looking to further promote LNG along with renewable electricity in Asian countries, while helping to reduce their dependence on coal- and oil-fired power generators. The 2035 target for LNG is part of Jera's three pillars of strategic focus, along with renewables as well as hydrogen and ammonia , which was announced on 16 May to spur decarbonisation towards its 2050 net zero emissions goal. The company plans to invest ¥5 trillion ($32bn) for these three areas over 2024-36. Jera also aims to retire all supercritical or less efficient coal-fired units by 2030-31 . This would help achieve the company's target of cutting CO2 emissions from its domestic business by at least 60pc against 2013-14 levels by 2035-36. By Motoko Hasegawa Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Biomass start-ups lift Japan's Renova April power sales


24/05/17
24/05/17

Biomass start-ups lift Japan's Renova April power sales

Tokyo, 17 May (Argus) — Japanese renewable power developer Renova's electricity sales doubled on the year in April, following the start-up of three biomass power plants in the past six months. Renova sold 199,601MWh of electricity — including solar, biomass and geothermal — in April, double the 99,857MWh a year earlier, the company announced on 13 May. The 75MW Sendai Gamo plant in northeastern Miyagi prefecture started operations in November 2023 and produced 40,753MWh in April. The 74.8MW Tokushima Tsuda plant in western Tokushima prefecture, which was commissioned in December 2023, generated 10,870MWh in April. The 75MW Ishinomaki Hibarino plant in Miyagi began normal runs in March and supplied 49,495MWh in April. Renova plans to add 124.9MW biomass-fired capacity in the April 2024-March 2025 fiscal year, with the 75MW Omaezaki plant in central Shizuoka city scheduled to begin commercial operations in July, followed by the 49.9MW Karatsu plant in southern Saga city in December. Omaezaki is currently conducting trial runs and Karatsu is under construction. The additions will increase Renova's biomass-fired capacity to 445MW. By Takeshi Maeda Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Mexican power outages enter fourth day


24/05/10
24/05/10

Mexican power outages enter fourth day

Mexico City, 10 May (Argus) — Mexican power grid operator Cenace issued its fourth consecutive day of operating alerts amid the heatwave gripping the country. Net electricity demand reached 47,321MW early today, with deployed electricity capacity slightly below at 47,233 MW, according to Cenace. Since 7 May, Cenace has declared emergency operating alerts as demand exceeded generation capacity during peak evening hours, prompting the grid operator to preemptively cut electricity supply across different states to maintain grid integrity. Power outages have lasted up to several hours in Mexico City and in major industrial states as power demand has outstripped supply by up to 1,000MW. Peak demand this week hit 49,000MW, just below last year's historic peak of 53,000MW during atypical temperatures in June. "We are very concerned about the unprecedented outages detected across 21 states, a situation that affects the normal functioning of Mexican companies," national business chamber Coparmex said. Peak electricity demand typically rises in June-July but temperatures this week have risen as high as 48°C (118° F) across some states. Mexico City reported a record high of 34.3°C on 9 May and high temperatures are forecast to continue into next week, Mexico's national weather service said. The inability of Mexico's grid to respond to increased demand is because of insufficient power generation capacity, non-profit think-tank the Mexican institute for competitiveness (Imco) said this week. "Despite the energy ministry's forecast that 22,000MW of new power capacity would enter service by 2026, only 1,483MW had entered service as of 2022" since late 2018, Imco said. President Andres Manuel Lopez Obrador's administration pledged to build new generation capacity, including five gas-fired, combined-cycle plants, but recognized this week that delays had contributed to the power outages. "We have an electricity generation deficit because some of the combined-cycle plants were delayed, but we are working on it and it will soon be resolved," Lopez Obrador said on 9 May. Lopez Obrador's government has also curtailed private sector power development during his administration. Mexico needs to upgrade and expand its transmission network, industry associations say. "In order to resolve this problem, we believe that a reopening of the electricity market to the private sector is imperative," Mexico's wind energy association, Amdee, said. Mexico has 87,130MW of installed capacity, with 39.5pc from combined-cycle gas-fired power plants and 31pc in renewable power, including wind, solar, hydroelectric, geothermal and biomass, according to the latest statistics from the energy ministry. By Rebecca Conan Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Floods stress Brazil energy sector vulnerability


24/05/10
24/05/10

Floods stress Brazil energy sector vulnerability

New York, 10 May (Argus) — Record flooding in Brazil's Rio Grande do Sul state over the past week underscores vulnerabilities in the country's energy system to extreme weather, which could also slow its pace of transition to cleaner energies. Nearly one week after record rainfall began flooding the state, power outages continue to plague it, with nearly 400,000 residents still in the dark. The flooding forced companies to suspend operations of critical infrastructure for the power sector, including three substations, 25 transmission lines, six hydroelectric plants and 11 power transformers. This led grid operator ONS to import power from Uruguay to meet domestic demand. With forecasts pointing to more rain, it is increasingly clear that it will take weeks if not months for the state to start returning to normal. The Rio Grande do Sul government estimates that the floods will cost the state R19bn ($3.6bn) . The tragedy in southern Brazil comes less than a year after a record drought struck the Amazon basin, which pushed water levels of the Amazon River and its tributaries to their lowest in 120 years. The drought reduced hydroelectric output from the region's plants and interrupted transport of fuel along key river corridors, leaving many households without power, because of the lack of diesel to operate generators used in off-grid communities. These crises highlight the country's failure to prepare for extreme weather and underscore the lack of investment in critical infrastructure, including in the energy sector. A study by the World Bank from 2023warned of the need to upgrade the country's aging infrastructure and of future power supply risks. Brazil's large hydroelectric plants have been operating for an average of 55 years, according to the study, and need investments to boost efficiency and to limit the impact of extreme weather. A total of 11 hydroelectric plants in Rio Grande do Sul are being monitored, including six that present an elevated risk of rupture, such as the 28MW 14 de Julho plant that experienced a partial rupture last week because of the heavy rains. Authorities will now need to change their focus, which has been largely on limiting the impact of dry weather on the electricity sector, especially following the 2021 droughts, that resulted in expansion of thermoelectric generation. More recently, electricity regulator Aneel has been focusing on making power distribution and transmission networks more resilient to extreme weather, especially after downed power lines resulted in extended blackouts for some 4mn consumers in the city of Sao Paulo and over 1.3mn consumers in Rio de Janeiro. The sector is working to make transmission towers more resilient to high winds. Several cities and states in Brazil have launched plans to prepare for climate change, but the bulk of these plans focus on increasing investments in renewable energy and emissions reduction. Increasingly, these plans will also need to focus on mitigating risk from floods, heat waves and landslides. Brazilian energy companies are also behind the curve in their preparations for climate change. Only 13pc of executives in the energy sector that participated in a recent survey conducted by consulting firm PwC Brasil said they have assessed the impact of climate change on their financial planning. State of climate Brazil faced 12 extreme climate events in 2023, according to the World Meteorological Association (WMO). This included a tropical cyclone that hit Rio Grande do Sul last year and affected more than 340,000 people and left nearly 50 dead. The WMO blamed the extreme climate events in Brazil on the "double-whammy of El Niño and longer-term climate change." Last year, eight Brazilian states recorded their lowest July-to-September rainfall in over 40 years, it said. Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more