Utilities doubt 2030 German coal exit

  • : Electricity, Hydrogen
  • 24/03/06

Utilities told Argus that the window for bringing the German coal phase-out forward by eight years to 2030 is fast disappearing, citing a lack of clarity on details of tenders for hydrogen-ready gas-fired plants under the power plant strategy and the tight timeline to build the new dispatchable capacity.

Utility EnBW told Argus that the 10GW of hydrogen-ready gas-fired capacity planned for tender is "unlikely to be sufficient" for an early coal phase-out, stating that analysts see a "greater need" for dispatchable capacity. And Uniper chief executive Michael Lewis said at the E-World conference in Essen that 10GW is "not enough", and last week added that 20-25GW of new capacity would be needed to even replace decommissioned power plants. And the timing to meet the 2030 target is "very tight", Lewis said.

Steag told Argus that the country's exit from coal-fired power generation by 2030 is "still possible" but has become "less likely", and highlighted the fact that grid regulator Bnetza has designated some coal-fired plants as system-relevant as far out as 2031. According to analysis from the country's four transmission system operators (TSOs) in September last year, bringing forward the market-side coal phase-out is possible from a grid congestion perspective, but coal-fired plants will need to stay in the grid reserve beyond this date. And on Tuesday, Bnetza set out a timeline for statutory reduction of coal burn, which still anticipates the last units going off line in 2038.

Beyond 2030, modelling by Swiss utility Axpo "very clearly indicates" that more than 10GW of hydrogen-ready capacity will be needed, head of fundamental analysis and modelling Andy Sommer told Argus at E-World. The country will probably "come back" to the original target of around 25GW at some point, according to Sommer.

Utilities call for clarity on strategy details

Utilities also told Argus that the government must publish additional details about the power plant strategy as soon as possible to ensure security of planning for new hydrogen-ready gas-fired plants. While Leag and RWE said that the 10GW of capacity to be tendered is an "important step" and goes "in the right direction", respectively, they also, along with Uniper and Steag, told Argus that additional details of the power plant strategy must be published as soon as possible as remaining uncertainties around tendering conditions impede investment planning. Steag, which has already begun preliminary planning work at existing coal-fired power plant sites for future hydrogen-ready units, pointed to the lack of timeline and concrete details for the tenders as well as the pending state aid agreement with the EU, while EnBW highlighted that as projects can take between six and eight years to commission, tenders should start this year.

Leag and EnBW argued that plants should be built at sites with existing infrastructure, which EnBW called more "cost-effective". And Leag reiterated that it favours a fair distribution of sites across Germany without preferential treatment for certain regions. The bulk of its capacity is lignite-fired and located in eastern Germany while demand is concentrated in the west and south of the country. But EnBW pointed to expectations from TSOs that southern Germany will see "particularly high demand" for gas-fired plants for grid stability, and said this could lead to it investing further at its other sites in Baden-Wurttemberg depending on the details of the incentive mechanisms in the strategy.

Several utilities welcomed the introduction of a capacity mechanism by 2028, with Uniper stating that it was "very relieved" that the government is in favour of introducing such a mechanism, and RWE stating that it is an "efficient way" to ensure security of supply. But EnBW, while welcoming the intention, urged further clarity on how the capacity mechanism and the power plant strategy "should interact", as uncertainty on this will make it "more difficult" to bid in the tenders.

Leag said it plans to build 3GW of hydrogen-ready gas-fired plants by 2030, and RWE said it is prepared to build the same capacity if the framework conditions allow economically-viable operation. Steag is planning to build 2-2.5GW across three plants at its sites in Bergkamen, Bexbach and Quierschied-Weiher. And Uniper assumes that it will build a "significant portion" of the new capacity, having pointed to planned "gigawatt scale" flexible plants in October.

EnBW is also currently working on various fuel-switch projects that will see coal-fired units at its Altbach/Deizisau, Heilbronn and Stuttgart-Munster sites replaced with hydrogen-ready gas-fired combined heat and power plants. Work should be completed by next year for Stuttgart-Munster, and by 2026 for the other two sites, the utility said.

Vattenfall did not disclose planned capacity additions. Together, RWE, EnBW, Leag, Vattenfall and Uniper's portfolios account for over half of Germany's installed capacity outside the renewable energy act.


Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

24/05/17

Clean hydrogen industry still upbeat but more realistic

Clean hydrogen industry still upbeat but more realistic

London, 17 May (Argus) — The clean hydrogen sector still lacks tangible progress and final investment decisions (FIDs) for projects remain far and few between, but it is reaching a moment of reckoning essential for market maturity, delegates at the World Hydrogen Summit in Rotterdam said. When asked whether they were more or less positive than a year ago, industry participants gave diverging answers, but there was widespread agreement that progress on clean hydrogen has been slower than expected. This has been "the year of doldrums", the Dutch port of Rotterdam's hydrogen supply chain programme manager Martijn Coopman said. Increasing material and financing costs, the unstable geopolitical situation and a lack of clarity on regulatory frameworks are just some of the challenges developers have faced. This is a "grim environment if you were expecting the Swiss army knife approach" to work, industry body the Australia Hydrogen Council's chief executive Fiona Simon said, alluding to the — misguided — expectation that hydrogen could be used across all sectors to help decarbonise. "We are coming to terms" on the real use and appropriate applications of hydrogen, Simon said, pointing to green steel production. "We are converging on the same concepts and same policies". The industry has reached the point where the wheat is separated from the chaff and it is becoming a lot clearer which projects will actually materialise.There is now a greater sense of "realism" underpinning discussions according to Dutch gas company Gasunie chief executive Willemien Terpstra. And this is why market participants are more optimistic than a year ago. Demanding as ever Still, delegates widely urged more policy action, especially on the demand side, which has been a recurrent theme. Spurring on demand will be key to get to more FIDs, Spanish utility Iberdrola's hydrogen development director Jorge Palomar Herrero, said. "We can have great intentions and great projects but without the demand, they are not going to happen". Even in Europe, which has pushed ahead with efforts to stimulate demand, these have not been enough to spur offtake, Herrero said. Demand-side incentives alone will likely not be enough and eventually there will have to be consumption obligations too, some said. Incentives may help to reduce project costs and kickstart production, but the amount of "carrots" needed is "phenomenal", so "sticks" will be key, the port of Rotterdam's Coopman said. Consumption mandates could help accelerate momentum in emerging markets and developing countries that have big ambitions for exports to future demand centres, the World Bank's private sector arm IFC energy chief investment officer Ignacio de Calonje said. Governments are now ready to act on these requests, according to industry body the Hydrogen Council's director for policy and partnerships Daria Nochevnik. "The penny has dropped," Nochevnik told Argus , noting that the need for demand-side action was the number one priority outcome of a ministerial-executive roundtable held in Rotterdam this week. Red and blue Governments must also remove red tape to speed things up, conference delegates said. European developers in particular are increasingly frustrated with paperwork involved in funding applications, according to German utility Uniper's vice-president for hydrogen business development Christian Stuckmann. Shortening lengthy permitting and funding processes is also high on governments' lists, Nochevnik noted. Some delegates renewed calls for a wider acceptance of "blue" low-carbon hydrogen made from natural gas with carbon capture and storage to address concerns that, if it is up to renewable hydrogen alone, things will start too late — or not at all. There appeared to be widespread consensus that this low-carbon hydrogen will have a key role to play, especially in a transitional period, as it can already deliver significant emissions reductions. But there is still a "stigma" in Europe, according to industrial gas firm Linde's vice-president for clean energy David Burns. This could hamper its adoption, which many delegates argued the world cannot afford. By Pamela Machado Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Japanese bank Mizuho boosts support for H2, ammonia


24/05/17
24/05/17

Japanese bank Mizuho boosts support for H2, ammonia

Tokyo, 17 May (Argus) — Japanese bank Mizuho Financial aims to provide ¥2 trillion ($12.8bn) in financial support for domestic and overseas cleaner fuel projects by 2030 to support Japan's plan to build a hydrogen supply chain. Private-sector Mizuho is offering financing to low-carbon hydrogen, ammonia and e-methane projects related to production, import, distribution and development of hydrogen carriers. Mizuho said it has in the past offered project financing for large-scale overseas low-carbon hydrogen and ammonia manufacturing projects, as well as transition loans. Japan is focusing on cleaner fuel use in the power sector and hard-to-abate industries, as part of its drive to reach net zero CO2 emissions by 2050. Japanese firms are getting involved in overseas hydrogen projects because domestic production is bound to be comparatively small and costly. They are looking to co-fire ammonia at coal-fired power generation plants to cut CO2 emissions and examining use of the fuel as a hydrogen carrier . Japanese companies have also partnered with several overseas firms on e-methane. Mizuho has to date offered $1bn for cleaner fuel projects. The bank has set a goal to accelerate the setting up of a clean fuel supply chain by addressing the financial challenge faced by projects requiring large investments. Mizuho has attempted to help Japan's decarbonisation push by tightening biomass and coal financing policies. Mizuho has also stopped investing in new coal-fired power projects, including existing plant expansions. The bank has a plan to reduce the ¥300bn credit available for coal-fired power development projects by half by the April 2030-March 2031 fiscal year and to zero by 2040-41. By Nanami Oki Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Japan’s Jera to handle 35mn t/yr LNG until FY2035-36


24/05/17
24/05/17

Japan’s Jera to handle 35mn t/yr LNG until FY2035-36

Osaka, 17 May (Argus) — Japan's largest LNG importer Jera plans to maintain its LNG handling volumes at no less than 35mn t/yr until the April 2035-March 2036 fiscal year. Rising renewable power supplies and the possible return of more nuclear reactors are likely to pressure LNG demand from Japan's power sector. Jera consumed 23mn t of LNG in 2023-24, down by 3pc on the year, although it handled 35mn t through its global operations during the same year. But Jera needs to secure sufficient LNG supplies to adjust for imbalances in electricity supplies and ensure power security, through more flexible operations. It is also looking to further promote LNG along with renewable electricity in Asian countries, while helping to reduce their dependence on coal- and oil-fired power generators. The 2035 target for LNG is part of Jera's three pillars of strategic focus, along with renewables as well as hydrogen and ammonia , which was announced on 16 May to spur decarbonisation towards its 2050 net zero emissions goal. The company plans to invest ¥5 trillion ($32bn) for these three areas over 2024-36. Jera also aims to retire all supercritical or less efficient coal-fired units by 2030-31 . This would help achieve the company's target of cutting CO2 emissions from its domestic business by at least 60pc against 2013-14 levels by 2035-36. By Motoko Hasegawa Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Biomass start-ups lift Japan's Renova April power sales


24/05/17
24/05/17

Biomass start-ups lift Japan's Renova April power sales

Tokyo, 17 May (Argus) — Japanese renewable power developer Renova's electricity sales doubled on the year in April, following the start-up of three biomass power plants in the past six months. Renova sold 199,601MWh of electricity — including solar, biomass and geothermal — in April, double the 99,857MWh a year earlier, the company announced on 13 May. The 75MW Sendai Gamo plant in northeastern Miyagi prefecture started operations in November 2023 and produced 40,753MWh in April. The 74.8MW Tokushima Tsuda plant in western Tokushima prefecture, which was commissioned in December 2023, generated 10,870MWh in April. The 75MW Ishinomaki Hibarino plant in Miyagi began normal runs in March and supplied 49,495MWh in April. Renova plans to add 124.9MW biomass-fired capacity in the April 2024-March 2025 fiscal year, with the 75MW Omaezaki plant in central Shizuoka city scheduled to begin commercial operations in July, followed by the 49.9MW Karatsu plant in southern Saga city in December. Omaezaki is currently conducting trial runs and Karatsu is under construction. The additions will increase Renova's biomass-fired capacity to 445MW. By Takeshi Maeda Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

New Dutch government to cut funds for green H2


24/05/16
24/05/16

New Dutch government to cut funds for green H2

Hamburg, 16 May (Argus) — The Netherlands' new government could reduce the budget of the country's climate fund by €1.2bn, primarily through cuts to renewable hydrogen support measures. Four parties announced an agreement to form a coalition government on 16 May and outlined broad policy measures. The agreement includes a "budget supplement" which foresees the climate fund's budget being cut by €300mn in each of the next four years compared with existing plans. This will be achieved by cutting funds available for the development of batteries and renewable hydrogen "in proportion to the current budget", according to the text. The majority of the cuts could be for renewable hydrogen given that the earmarked budget for this was much larger than for battery-related projects. Around €9bn of the fund's €35bn budget was set aside for renewable hydrogen support measures, with the bulk to go towards subsidising production projects . The coalition agreement was reached between the far-right PVV, the centre-right VDD party of outgoing prime minister Mark Rutte, the centre-right NSC, which was formed just shortly before the election last November, and the farmer's citizen movement BBB. The PVV, led by Geert Wilders, won most seats in the election but had to tone down some of the demands and promises from its election manifesto during the negotiations. In its manifesto, the PVV had pledged to abolish the climate fund entirely , saying that climate policies should "go straight through the shredder". The parties have retained a general commitment to support renewable hydrogen through the climate fund and note that low-carbon hydrogen made from natural gas with carbon capture and storage (CCS) can be used as a "transitional step" towards reducing emissions "if necessary". The agreement also says a planned increase in the national CO2 tax will be scrapped and outlines plans to open new nuclear power plants. The four parties have yet to decide on who will become the new prime minister. By Stefan Krumpelmann Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more