US pipeline companies scale back expansions
A perfect storm of Covid-19 and the oil price collapse has taken the heat out of a midstream boom, writes Eunice Bridges
US midstream companies have reduced planned crude pipeline capacity expansions by more than 1.4mn b/d through deferrals or scale-backs in the wake of the collapse in oil prices and efforts to contain Covid-19.
There has been a large midstream build-up in the US in recent years, pushed by record production and growing demand to export US crude. But the collapse in oil prices and the pandemic-related plummet in demand have put the brakes on the midstream boom. At least four planned pipelines have been deferred or scaled back (see table). The largest setback is Enterprise Products Partners deferring its 450,000 b/d Midland-to-Echo 4 line — an expansion of Enterprise's system from the Permian basin to the Houston area — as part of a $1.1bn drop in capital expenditure in 2020. The line has been pushed back by about six months and is now expected to start up in the second half of 2021, the company says.
Energy Transfer has scaled down the planned Ted Collins pipeline that will connect a terminal in the Houston Ship Channel to Nederland, Texas. The revised project is for capacity of 275,000 b/d, and it will use some existing infrastructure to lower costs. The previous plan was for a 500,000 b/d newbuild. The scaled-down project is expected to enter service in the fourth quarter of 2021.
US refiner Phillips 66 has paused two large crude pipeline projects — Red Oak and Liberty — and will make a decision on whether to continue them later. Both were previously scheduled to start service in early 2021. Red Oak, a joint venture with Plains, would carry crude from the Permian and Cushing, Oklahoma, to Texas ports. Liberty, a joint venture with Bridger, would have moved 350,000 b/d of Rockies and Bakken production to Cushing. Phillips 66 has also postponed a final investment decision on the Ace pipeline project to connect supply in St James, Louisiana, to refineries in the region.
Other large US pipeline projects remain on schedule, even as companies slash spending because of the collapse in crude prices since early March. Energy Transfer is moving forward with a plan to expand its 570,000 b/d Bakken system from North Dakota to the US Gulf coast. The firm envisages expansion to 750,000 b/d — just by adding pumping stations, at a fraction of the cost of building new lines — but could target 1.1mn b/d, depending on discussions with shippers.
Keystone cops it again?
While US midstream expansions face financial pressures and cutbacks, Canadian firm TC Energy's totemic 830,000 b/d Keystone XL pipeline from western Canada to the US midcontinent faces the potential revival of a political challenge and continuing legal delays. The beleaguered project was dealt another blow last month when a US federal court vacated a key water-crossing permit, sending it back to the US Army Corps of Engineers. But the outcome of the US election in November could present an insuperable barrier if presumptive Democratic presidential nominee Joe Biden wins the White House.
Biden, as vice-president in the previous administration, opposed the project, and will "stop it for good by rescinding the Keystone XL pipeline permit", his campaign policy director Stef Feldman says. Former president Barack Obama blocked Keystone XL in 2015 after years of review, citing environmental concerns. The project was revived in 2017, with a cross-border permit from the administration of President Donald Trump. The Biden campaign says rejecting Keystone XL is more important now because of the urgency of combating climate change. "No other pipeline project in the history of the industry has been studied more than Keystone XL, and every study has concluded it can be built safely and in an environmentally sound manner," TC Energy says.
US pipeline status update | ||||
Status/project | Partners | Capacity '000 b/d | Origin | Destination |
Deferred | ||||
Red Oak | Phillips 66/Plains | 400 | Cushing | US Gulf coast |
Liberty | Phillips 66/Bridger | 350 | Gulf coast | Cushing, OK |
Midland-to-Echo 4 | Enterprise | 450 | Rockies | Houston |
Scaled back | ||||
Ted Collins | Energy Transfer | Cut to 275 from 500 | Houston | Nederland, TX |
On track | ||||
Wink to Webster | Exxon/Plains/others | 1,000-1,500 | Wink, Texas | Houston |
Midland-to-Echo 3* | Enterprise | 450 | Midland | Houston |
Dakota Access expansion | Energy Transfer | 750-1,100 | Bakken | US Gulf coast |
Diamond expansion | Plains/Valero | 400 | Cushing | Memphis, TN |
Capline reversal | Marathon/Plains/BP | 1,200 | Pakota, IL | St James, LA |
Keystone XL | TC Energy | 830 | Hardisty, Alberta | Steele City, NB |
Line 3 | Enbridge | 760 | Alberta | Wisconsin |
*part of Wink to Webster |
Related news posts
Shell's 1Q profit supported by LNG and refining
Shell's 1Q profit supported by LNG and refining
London, 2 May (Argus) — Shell delivered a better-than-expected profit for the first quarter of 2024, helped by a strong performance from its LNG and oil product businesses. The company reported profit of $7.4bn for January-March, up sharply from an impairment-hit $474mn in the previous three months but down from $8.7bn in the first quarter of 2023. Adjusted for inventory valuation effects and one-off items, Shell's profit came in at $7.7bn, 6pc ahead of the preceding three months and above analysts' estimates of $6.3bn-$6.5bn, although it was 20pc lower than the first quarter of 2023 when gas prices were higher. Shell's oil and gas production increased by 3pc on the quarter in January-March and was broadly flat compared with a year earlier at 2.91mn b/d of oil equivalent (boe/d). For the current quarter, Shell expects production in a range of 2.55mn-2.81mn boe/d, reflecting the effect of scheduled maintenance across its portfolio. The company's Integrated Gas segment delivered a profit of $2.76bn in the first quarter, up from $1.73bn in the previous three months and $2.41bn a year earlier. The segment benefited from increased LNG volumes — 7.58mn t compared to 7.06mn t in the previous quarter and 7.19mn t a year earlier — as well as favourable deferred tax movements and lower operating expenses. For the current quarter, Shell expects to produce 6.8mn-7.4mn t of LNG. In the downstream, the company's Chemicals and Products segment swung to a profit of $1.16bn during the quarter from an impairment-driven loss of $1.83bn in the previous three months, supported by a strong contribution from oil trading operations and higher refining margins driven by greater utilisation of its refineries and global supply disruptions. Shell's refinery throughput increased to 1.43mn b/d in the first quarter from 1.32mn b/d in fourth quarter of last year and 1.41mn b/d in January-March 2023. Shell has maintained its quarterly dividend at $0.344/share. It also said it has completed the $3.5bn programme of share repurchases that it announced at its previous set of results and plans to buy back another $3.5bn of its shares before the company's next quarterly results announcement. The company said it expects its capital spending for the year to be within a $22bn-$25bn range. By Jon Mainwaring Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.
US Fed signals rates likely to stay high for longer
US Fed signals rates likely to stay high for longer
Houston, 1 May (Argus) — Federal Reserve policymakers signaled they are likely to hold rates higher for longer until they are confident inflation is slowing "sustainably" towards the 2pc target. The Federal Open Market Committee (FOMC) held the federal funds target rate unchanged at a 23-year high of 5.25-5.5pc, for the sixth consecutive meeting. This followed 11 rate increases from March 2022 through July 2023 that amounted to the most aggressive hiking campaign in four decades. "We don't think it would be appropriate to dial back our restrictive policy stance until we've gained greater confidence that inflation is moving down sustainably," Fed chair Jerome Powell told a press conference after the meeting. "It appears it'll take longer to reach the point of confidence that rate cuts will be in scope." In a statement the FOMC cited a lack of further progress towards the committee's 2pc inflation objective in recent months as part of the decision to hold the rate steady. Despite this, the FOMC said the risks to achieving its employment and inflation goals "have moved toward better balance over the past year," shifting prior language that said the goals "are moving into better balance." The decision to keep rates steady was widely expected. CME's FedWatch tool, which tracks fed funds futures trading, had assigned a 99pc probability to the Fed holding rates steady today while giving 58pc odds of rate declines beginning at the 7 November meeting. In March, Fed policymakers had signaled they believed three quarter points cuts were likely this year. Inflation has ticked up lately after falling from four-decade highs in mid-2022. The consumer price index inched back up to an annual 3.5pc in March after reaching a recent low of 3pc in June 2023. The employment cost index edged up in the first quarter to the highest in a year. At the same time, job growth, wages and demand have remained resilient. The Fed also said it would begin slowing the pace of reducing its balance sheet of Treasuries and other notes in June, partly to avoid stress in money markets. By Bob Willis Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.
Cenovus boosts oil sands output by 4pc in 1Q
Cenovus boosts oil sands output by 4pc in 1Q
Calgary, 1 May (Argus) — Canadian integrated Cenovus Energy increased its oil sands production by 4pc in the first quarter, led by gains at Lloydminster Thermal and Foster Creek heavy crude assets, and the company plans to boost output further to supply the newly opened Trans Mountain Expansion (TMX) pipeline. Cenovus pumped out 613,000 b/d of crude from its oil sands projects in Alberta, up from 588,000 b/d in the same quarter last year, the Calgary-based company reported on Wednesday. This was one of the highest producing quarters for Cenovus' oil sands assets since acquiring Husky in early 2021, second only to the 625,000 b/d produced in the fourth quarter that year. Cenovus has a commitment of about 144,000 b/d on the newly completed 590,000 b/d TMX pipeline, which was placed into service on Wednesday , and the company has plans to push upstream output higher over the next several years across its portfolio to meet its commitment. The pipeline nearly triples the amount of Canadian crude that can reach the Pacific coast without first having to go through the US. First-quarter production from the Lloydminster Thermal segment rose to 114,000 b/d, up from 99,000 b/d a year earlier, because of higher reliability, according to Cenovus. Cenovus' Foster Creek production rose to 196,000 b/d of bitumen, up from 190,000 b/d in first quarter 2023. The company plans to bring another 30,000 b/d online at the steam-assisted gravity drainage (SAGD) asset by the end of 2027 through optimization projects. To the north, Christina Lake's first-quarter bitumen output of 237,000 b/d was steady with previous quarters. The asset is expected to get a significant boost by the end of 2025 when a pipeline connecting the project to output from the neighbouring Narrows Lake asset is completed. The 17 kilometer (11 mile) Narrows Lake tie-back will add 20,000-30,000 b/d of bitumen to Christina Lake, which already ranks as the industry's largest SAGD project. The pipeline is 67pc complete and should be placed into service in early 2025, Cenovus executives said Wednesday on an earnings call. Northeast of Fort McMurray, Alberta, new well pads are planned at Sunrise in 2025, where Cenovus also plans to push production higher by 20,000 b/d. Sunrise produced an average of 49,000 b/d in the first quarter this year, up from 45,000 b/d in the same quarter 2023. Cenovus' output company-wide rose to 801,000 b/d of oil equivalent (boe/d) in the first quarter, up from 779,000 boe/d a year earlier. This includes oil sands, natural gas liquids, natural gas, conventional and offshore assets. Cenovus posted a profit of C$1.2bn ($871mn) in the quarter, up from a C$636mn profit during the same quarter of 2023. By Brett Holmes Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.
Tankers can take TMX crude mid-May: Trans Mountain
Tankers can take TMX crude mid-May: Trans Mountain
Calgary, 1 May (Argus) — Commercial operations for the 590,000 b/d Trans Mountain Expansion (TMX) crude pipeline in western Canada have officially started today, but tankers will not be able to load crude from the line until later this month. Line fill activities, which began on 16 April, are still ongoing for the C$34bn ($25bn) project that stretches from Edmonton, Alberta, to the docks in Burnaby, British Columbia. About 70pc of the volumes needed are in the 1,181 kilometre (733 mile) line, Trans Mountain said on Wednesday. "As of today, all deliveries for shippers will be subject to the Expanded System tariff and tolls, and tankers will be able to receive oil from Line 2 by mid-May," Trans Mountain said. Aframax-size crude tankers started to take position on the west coast last month in anticipation of the new line. But the inability to deliver crude at Burnaby, while still having to pay full tolls, was a concern raised by several shippers on 23 April. "Trans Mountain must be able to receive, transport and deliver a shipper's contract volume," the shippers said in a letter to the CER. The ability to deliver the crude is "clearly central and fundamental qualities of firm service." The CER in November approved interim tolls for the system that will further connect Albertan oil sands producers to Pacific Rim markets. Shippers will, at least initially, pay C$11.46/bl to move crude from Edmonton, Alberta, to the Westridge terminal in Burnaby, British Columbia. The fixed portion accounts for C$10.88/bl of this and has nearly doubled from a C$5.76/bl estimate in 2017. The Canada Energy Regulator (CER) on 30 April gave Trans Mountain a green light to put TMX into service , ending years of uncertainty that the project would ever be completed. The expansion project, or Line 2, nearly triples the capacity of Canadian crude that can flow to the Pacific coast, complementing the original 300,000 b/d line, or Line 1, that has been operating since 1953. By Brett Holmes Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.
Business intelligence reports
Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.
Learn more