US pipeline companies scale back expansions

  • Market: Crude oil, Oil products
  • 22/05/20

A perfect storm of Covid-19 and the oil price collapse has taken the heat out of a midstream boom, writes Eunice Bridges

US midstream companies have reduced planned crude pipeline capacity expansions by more than 1.4mn b/d through deferrals or scale-backs in the wake of the collapse in oil prices and efforts to contain Covid-19.

There has been a large midstream build-up in the US in recent years, pushed by record production and growing demand to export US crude. But the collapse in oil prices and the pandemic-related plummet in demand have put the brakes on the midstream boom. At least four planned pipelines have been deferred or scaled back (see table). The largest setback is Enterprise Products Partners deferring its 450,000 b/d Midland-to-Echo 4 line — an expansion of Enterprise's system from the Permian basin to the Houston area — as part of a $1.1bn drop in capital expenditure in 2020. The line has been pushed back by about six months and is now expected to start up in the second half of 2021, the company says.

Energy Transfer has scaled down the planned Ted Collins pipeline that will connect a terminal in the Houston Ship Channel to Nederland, Texas. The revised project is for capacity of 275,000 b/d, and it will use some existing infrastructure to lower costs. The previous plan was for a 500,000 b/d newbuild. The scaled-down project is expected to enter service in the fourth quarter of 2021.

US refiner Phillips 66 has paused two large crude pipeline projects — Red Oak and Liberty — and will make a decision on whether to continue them later. Both were previously scheduled to start service in early 2021. Red Oak, a joint venture with Plains, would carry crude from the Permian and Cushing, Oklahoma, to Texas ports. Liberty, a joint venture with Bridger, would have moved 350,000 b/d of Rockies and Bakken production to Cushing. Phillips 66 has also postponed a final investment decision on the Ace pipeline project to connect supply in St James, Louisiana, to refineries in the region.

Other large US pipeline projects remain on schedule, even as companies slash spending because of the collapse in crude prices since early March. Energy Transfer is moving forward with a plan to expand its 570,000 b/d Bakken system from North Dakota to the US Gulf coast. The firm envisages expansion to 750,000 b/d — just by adding pumping stations, at a fraction of the cost of building new lines — but could target 1.1mn b/d, depending on discussions with shippers.

Keystone cops it again?

While US midstream expansions face financial pressures and cutbacks, Canadian firm TC Energy's totemic 830,000 b/d Keystone XL pipeline from western Canada to the US midcontinent faces the potential revival of a political challenge and continuing legal delays. The beleaguered project was dealt another blow last month when a US federal court vacated a key water-crossing permit, sending it back to the US Army Corps of Engineers. But the outcome of the US election in November could present an insuperable barrier if presumptive Democratic presidential nominee Joe Biden wins the White House.

Biden, as vice-president in the previous administration, opposed the project, and will "stop it for good by rescinding the Keystone XL pipeline permit", his campaign policy director Stef Feldman says. Former president Barack Obama blocked Keystone XL in 2015 after years of review, citing environmental concerns. The project was revived in 2017, with a cross-border permit from the administration of President Donald Trump. The Biden campaign says rejecting Keystone XL is more important now because of the urgency of combating climate change. "No other pipeline project in the history of the industry has been studied more than Keystone XL, and every study has concluded it can be built safely and in an environmentally sound manner," TC Energy says.

US pipeline status update
Status/projectPartnersCapacity '000 b/dOriginDestination
Deferred
Red Oak Phillips 66/Plains400CushingUS Gulf coast
LibertyPhillips 66/Bridger350Gulf coastCushing, OK
Midland-to-Echo 4Enterprise 450RockiesHouston
Scaled back
Ted CollinsEnergy TransferCut to 275 from 500HoustonNederland, TX
On track
Wink to WebsterExxon/Plains/others1,000-1,500Wink, TexasHouston
Midland-to-Echo 3*Enterprise450MidlandHouston
Dakota Access expansionEnergy Transfer750-1,100BakkenUS Gulf coast
Diamond expansionPlains/Valero400CushingMemphis, TN
Capline reversal Marathon/Plains/BP1,200Pakota, ILSt James, LA
Keystone XLTC Energy830Hardisty, AlbertaSteele City, NB
Line 3Enbridge760AlbertaWisconsin
*part of Wink to Webster

New crude pipelines

Sharelinkedin-sharetwitter-sharefacebook-shareemail-share

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

News
01/05/24

US Fed signals rates likely to stay high for longer

US Fed signals rates likely to stay high for longer

Houston, 1 May (Argus) — Federal Reserve policymakers signaled they are likely to hold rates higher for longer until they are confident inflation is slowing "sustainably" towards the 2pc target. The Federal Open Market Committee (FOMC) held the federal funds target rate unchanged at a 23-year high of 5.25-5.5pc, for the sixth consecutive meeting. This followed 11 rate increases from March 2022 through July 2023 that amounted to the most aggressive hiking campaign in four decades. "We don't think it would be appropriate to dial back our restrictive policy stance until we've gained greater confidence that inflation is moving down sustainably," Fed chair Jerome Powell told a press conference after the meeting. "It appears it'll take longer to reach the point of confidence that rate cuts will be in scope." In a statement the FOMC cited a lack of further progress towards the committee's 2pc inflation objective in recent months as part of the decision to hold the rate steady. Despite this, the FOMC said the risks to achieving its employment and inflation goals "have moved toward better balance over the past year," shifting prior language that said the goals "are moving into better balance." The decision to keep rates steady was widely expected. CME's FedWatch tool, which tracks fed funds futures trading, had assigned a 99pc probability to the Fed holding rates steady today while giving 58pc odds of rate declines beginning at the 7 November meeting. In March, Fed policymakers had signaled they believed three quarter points cuts were likely this year. Inflation has ticked up lately after falling from four-decade highs in mid-2022. The consumer price index inched back up to an annual 3.5pc in March after reaching a recent low of 3pc in June 2023. The employment cost index edged up in the first quarter to the highest in a year. At the same time, job growth, wages and demand have remained resilient. The Fed also said it would begin slowing the pace of reducing its balance sheet of Treasuries and other notes in June, partly to avoid stress in money markets. By Bob Willis Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Find out more
News

Cenovus boosts oil sands output by 4pc in 1Q


01/05/24
News
01/05/24

Cenovus boosts oil sands output by 4pc in 1Q

Calgary, 1 May (Argus) — Canadian integrated Cenovus Energy increased its oil sands production by 4pc in the first quarter, led by gains at Lloydminster Thermal and Foster Creek heavy crude assets, and the company plans to boost output further to supply the newly opened Trans Mountain Expansion (TMX) pipeline. Cenovus pumped out 613,000 b/d of crude from its oil sands projects in Alberta, up from 588,000 b/d in the same quarter last year, the Calgary-based company reported on Wednesday. This was one of the highest producing quarters for Cenovus' oil sands assets since acquiring Husky in early 2021, second only to the 625,000 b/d produced in the fourth quarter that year. Cenovus has a commitment of about 144,000 b/d on the newly completed 590,000 b/d TMX pipeline, which was placed into service on Wednesday , and the company has plans to push upstream output higher over the next several years across its portfolio to meet its commitment. The pipeline nearly triples the amount of Canadian crude that can reach the Pacific coast without first having to go through the US. First-quarter production from the Lloydminster Thermal segment rose to 114,000 b/d, up from 99,000 b/d a year earlier, because of higher reliability, according to Cenovus. Cenovus' Foster Creek production rose to 196,000 b/d of bitumen, up from 190,000 b/d in first quarter 2023. The company plans to bring another 30,000 b/d online at the steam-assisted gravity drainage (SAGD) asset by the end of 2027 through optimization projects. To the north, Christina Lake's first-quarter bitumen output of 237,000 b/d was steady with previous quarters. The asset is expected to get a significant boost by the end of 2025 when a pipeline connecting the project to output from the neighbouring Narrows Lake asset is completed. The 17 kilometer (11 mile) Narrows Lake tie-back will add 20,000-30,000 b/d of bitumen to Christina Lake, which already ranks as the industry's largest SAGD project. The pipeline is 67pc complete and should be placed into service in early 2025, Cenovus executives said Wednesday on an earnings call. Northeast of Fort McMurray, Alberta, new well pads are planned at Sunrise in 2025, where Cenovus also plans to push production higher by 20,000 b/d. Sunrise produced an average of 49,000 b/d in the first quarter this year, up from 45,000 b/d in the same quarter 2023. Cenovus' output company-wide rose to 801,000 b/d of oil equivalent (boe/d) in the first quarter, up from 779,000 boe/d a year earlier. This includes oil sands, natural gas liquids, natural gas, conventional and offshore assets. Cenovus posted a profit of C$1.2bn ($871mn) in the quarter, up from a C$636mn profit during the same quarter of 2023. By Brett Holmes Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Tankers can take TMX crude mid-May: Trans Mountain


01/05/24
News
01/05/24

Tankers can take TMX crude mid-May: Trans Mountain

Calgary, 1 May (Argus) — Commercial operations for the 590,000 b/d Trans Mountain Expansion (TMX) crude pipeline in western Canada have officially started today, but tankers will not be able to load crude from the line until later this month. Line fill activities, which began on 16 April, are still ongoing for the C$34bn ($25bn) project that stretches from Edmonton, Alberta, to the docks in Burnaby, British Columbia. About 70pc of the volumes needed are in the 1,181 kilometre (733 mile) line, Trans Mountain said on Wednesday. "As of today, all deliveries for shippers will be subject to the Expanded System tariff and tolls, and tankers will be able to receive oil from Line 2 by mid-May," Trans Mountain said. Aframax-size crude tankers started to take position on the west coast last month in anticipation of the new line. But the inability to deliver crude at Burnaby, while still having to pay full tolls, was a concern raised by several shippers on 23 April. "Trans Mountain must be able to receive, transport and deliver a shipper's contract volume," the shippers said in a letter to the CER. The ability to deliver the crude is "clearly central and fundamental qualities of firm service." The CER in November approved interim tolls for the system that will further connect Albertan oil sands producers to Pacific Rim markets. Shippers will, at least initially, pay C$11.46/bl to move crude from Edmonton, Alberta, to the Westridge terminal in Burnaby, British Columbia. The fixed portion accounts for C$10.88/bl of this and has nearly doubled from a C$5.76/bl estimate in 2017. The Canada Energy Regulator (CER) on 30 April gave Trans Mountain a green light to put TMX into service , ending years of uncertainty that the project would ever be completed. The expansion project, or Line 2, nearly triples the capacity of Canadian crude that can flow to the Pacific coast, complementing the original 300,000 b/d line, or Line 1, that has been operating since 1953. By Brett Holmes Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Canada’s TMX pipeline ready to move crude: Update


30/04/24
News
30/04/24

Canada’s TMX pipeline ready to move crude: Update

Adds regulatory approvals received. Calgary, 30 April (Argus) — Canada's 590,000 b/d Trans Mountain Expansion (TMX) crude pipeline can now start moving volumes to the Pacific coast after receiving final regulatory approvals today, more than a decade after the project was first conceived. The Canada Energy Regulator (CER) approved Trans Mountain's final applications on Tuesday, giving the midstream company a green light to put its C$34bn ($25bn) project into service. Trans Mountain had recently maintained its commitment to being ready by 1 May. The expansion nearly triples the existing 300,000 b/d Trans Mountain line that runs from Edmonton, Alberta, to Burnaby, British Columbia. Also expanded was the Westridge Marine Terminal from one dock to three, all capable of loading Aframax-sized vessels. The line will provide Canadian oil sands producers with a significant export outlet without having to first go through the US. Much of the new volume to flow on TMX is expected to be heavy sour crude. Federally-owned Trans Mountain had submitted applications as recent as 15 April for the final section of the pipeline about 140 kilometers (87 miles) east of the line's terminus in Burnaby. The final applications concerned piping, valves and other components at two pipeline inspection device traps and the mainline pipe between the two traps. The traps were added for safety assurance when the operator was allowed by CER to use a smaller diameter pipe as part of the Mountain 3 deviation. Mountain 3 was the last segment of the pipeline to be constructed because of delays relating to difficult terrain while tunneling. The "golden weld" marking the end of construction occurred on 11 April, according to Trans Mountain. A group of shippers last week expressed concern that TMX would not be ready for commercial service by 1 May. The pipeline had been marred by legal challenges and cost over-runs since it was first proposed in 2013 by its then-owner US midstream firm Kinder Morgan. The Canadian government took ownership of it in 2018. By Brett Holmes Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

New US rule may let some shippers swap railroads


30/04/24
News
30/04/24

New US rule may let some shippers swap railroads

Washington, 30 April (Argus) — US rail regulators today issued a final rule designed to help customers switch railroads in cases of poor rail service, but it is already drawing mixed reviews. Reciprocal switching, which allows freight shippers or receivers captive to a single railroad to access to an alternate carrier, has been allowed under US Surface Transportation Board (STB) rules. But shippers had not used existing STB rules to petition for reciprocal switching in 35 years, prompting regulators to revise rules to encourage shippers to pursue switching while helping resolve service problems. "The rule adopted today has broken new ground in the effort to provide competitive options in an extraordinarily consolidated rail industry," said outgoing STB chairman Martin Oberman. The five-person board unanimously approved a rule that would allow the board to order a reciprocal switching agreement if a facility's rail service falls below specified levels. Orders would be for 3-5 years. "Given the repeated episodes of severe service deterioration in recent years, and the continuing impediments to robust and consistent rail service despite the recent improvements accomplished by Class I carriers, the board has chosen to focus on making reciprocal switching available to shippers who have suffered service problems over an extended period of time," Oberman said today. STB commissioner Robert Primus voted to approve the rule, but also said it did not go far enough. The rule adopted today is "unlikely to accomplish what the board set out to do" since it does not cover freight moving under contract, he said. "I am voting for the final rule because something is better than nothing," Primus said. But he said the rule also does nothing to address competition in the rail industry. The Association of American Railroads (AAR) is reviewing the 154-page final rule, but carriers have been historically opposed to reciprocal switching proposals. "Railroads have been clear about the risks of expanded switching and the resulting slippery slope toward unjustified market intervention," AAR said. But the trade group was pleased that STB rejected "previous proposals that amounted to open access," which is a broad term for proposals that call for railroads to allow other carriers to operate over their tracks. The American Short Line and Regional Railroad Association declined to comment but has indicated it does not expect the rule to have an appreciable impact on shortline traffic, service or operations. Today's rule has drawn mixed reactions from some shipper groups. The National Industrial Transportation League (NITL), which filed its own reciprocal switching proposal in 2011, said it was encouraged by the collection of service metrics required under the rule. But "it is disheartened by its narrow scope as it does not appear to apply to the vast majority of freight rail traffic that moves under contracts or is subject to commodity exemptions," said NITL executive director Nancy O'Liddy, noting it was a departure from the group's original petition which sought switching as a way to facilitate railroad economic competitiveness. The Chlorine Institute said, in its initial analysis, that it does not "see significant benefit for our shipper members since it excludes contract traffic which covers the vast majority of chlorine and other relevant chemical shipments." By Abby Caplan Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more