Eight northeast gas line projects set for 2019: Update

  • : Natural gas
  • 19/02/15

Updates total projects and in-service date for Supply Header project in tenth paragraph.

At least eight major natural gas pipeline expansions are scheduled to begin service in the US northeast this year, boosting capacity by as much as 6.1 Bcf/d (173mn m³/d), according to an Argus analysis.

Booming output from the Appalachian shale region, combined with spikes in heating demand in the US northeast, makes the area fertile ground for pipeline expansions. Developers have regularly announced major projects to unleash more gas from Appalachia since the advent of hydraulic fracturing lead to a drilling boom there.

December production from Appalachia topped 31.1 Bcf/d, according to the most recent data from the US Energy Information Administration (EIA). Regional output in December was 16pc higher than a year earlier, and the agency estimates output in January climbed to more than 31.3 Bcf/d.

Expansions in recent years have increasingly met with pushback as residents, environmentalists and some state regulators take issue with use of the fuel and pipeline construction, often leading to delays. Two projects on tap for early 2019 were delayed from their original late 2018 in-service dates: Columbia Gas Transmission's 2.7 Bcf/d Mountaineer XPress expansion in West Virginia and Dominion's 284mn cf/d Eastern Market Access project in Maryland and Virginia.

The $3bn Mountaineer XPress line has begun partial service of about 1.4 Bcf/d and this week said it will be ready to begin full flows as early as 25 February.

Dominion this week declined to tell Argus what its estimated in-service date for the $147mn Eastern Market Access project is, saying it is currently in discussions with customers.

EQT's 580mn cf/d Equitrans Expansion project is scheduled to begin flows in Pennsylvania and West Virginia by the end of March. The project is designed to deliver volumes onto the 1.9 Bcf/d Mountain Valley pipeline, which has been pushed back to the fourth quarter. Construction on Equitrans is complete according to filings with the US Federal Energy Regulatory Commission (FERC), but the line has not yet requested approval to start service.

NJR Pipeline's 242mn cf/d Adelphia Gateway project is scheduled to start up in early 2019 and received a positive environmental review from FERC last month. The project has a relatively small footprint in Pennsylvania and Delaware, primarily involving acquiring and converting an existing 84-mile (135km) mainline and a 4.5-mile lateral.

National Fuel Gas this month said its 113mn cf/d Line N to Monaca expansion is proceeding on schedule for start up in June. The project will expand the company's Line N in Pennsylvania to boost takeaway capacity from the Appalachian shale.

Dominion had two projects scheduled to begin flowing in late 2019: the 1.5 Bcf/d Supply Header expansion and the 116mn cf/d Sweden Valley project. The company has since delayed the Supply Header project to late 2020, as it would primarily funnel gas from Pennsylvania and West Virginia into the 1.5 Bcf/d Atlantic Coast pipeline, which has been delayed to 2021. The $50mn Sweden Valley project in Pennsylvania and Ohio would ship Appalachian gas to a new interconnection with Tennessee Gas pipeline.

At the tail end of this year, the Transcontinental Gas pipeline will expand its service in New Jersey just in time to meet winter heating demand with its 184mn cf/d Rivervale South to Market project. FERC has already approved that expansion.


Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

24/04/23

US oil and gas deals slowing after record 1Q: Enverus

US oil and gas deals slowing after record 1Q: Enverus

New York, 23 April (Argus) — US oil and gas sector mergers will likely slow for the rest of the year following a record $51bn in deal in the first quarter, according to consultancy Enverus. Transactions slowed in March and the second quarter appears to have already lost momentum, according to Enverus, following the year-end 2023 surge in consolidation that spurred an unprecedented $192bn of upstream deals last year. The Permian shale basin of west Texas and southeastern New Mexico continued to dominate mergers and acquisitions, as companies competed for the remaining high-quality inventory on offer. Acquisitions were led by Diamondback Energy's $26bn takeover of closely-held Endeavor Energy Resources . Others include APA buying Callon Petroleum for $4.5bn in stock and Chesapeake Energy's $7.4bn takeover of Southwestern Energy . The deal cast a spotlight on the remaining private family-owned operators, such as Mewbourne Oil and Fasken Oil & Ranch, which would be highly sought after if they decided to put themselves up for sale. "However, there are no indications these closely held companies are looking to exit any time soon," said Andrew Dittmar, principal analyst at Enverus. "That leaves public explorers and producers (E&P) looking to scoop up the increasingly thin list of private E&Ps backed by institutional capital and built with a sale in mind — or figuring out ways to merge with each other." Deals including ExxonMobil's $59.5bn takeover of Pioneer Natural Resources, as well as Chevron's $53bn deal for Hess, have attracted the attention of anti-trust regulators. The Federal Trade Commission has also sought more information on the Chesapeake/Southwestern deal. "The most likely outcome is all these deals get approved but federal regulatory oversight may pose a headwind to additional consolidation within a single play," said Dittmar. "That may force buyers to broaden their focus by acquiring assets in multiple plays." By Stephen Cunningham Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

USGC LNG-VLSFO discount to steady itself


24/04/23
24/04/23

USGC LNG-VLSFO discount to steady itself

New York, 23 April (Argus) — The premium for US Gulf coast (USGC) very low-sulphur fuel oil (VLSFO) to LNG is expected to linger but not widen this spring, maintaining interest in LNG as a bunkering fuel. US Gulf coast LNG prices slipped from a premium to a discount to VLSFO in March 2023 and have remained there since. The discount surpassed 200/t VLSFO-equivalent in January (see chart). Both LNG and VLSFO prices are expected to remain under downward pressure due to high inventories, which could keep the current LNG discount steady. The US winter natural gas withdrawal season ended with 39pc more natural gas in storage compared with the five-year average, according to the US Energy Information Administration (EIA). Henry Hub natural gas monthly average prices dropped below $2/mmBtu in February, for the first time since September 2020, Argus data showed. The EIA expects the US will produce less natural gas on average in the second and third quarter of 2024 compared with the first quarter of 2024. Despite lower production, the US will have the most natural gas in storage on record when the winter withdrawal season begins in November, says the EIA. As a result, the agency forecasts the Henry Hub spot price to average less than $2/mmBtu in the second quarter before "increasing slightly" in the third quarter. EIA's forecast for all of 2024 averages about $2.20/mmBtu. US Gulf coast VLSFO is facing downward price pressure as demand falls and increased refinery activity signals a potential supply build . Rising Gulf coast refinery activity was likely behind some of the drop in prices. Gulf coast refinery utilization last week rose to 91.4pc, the highest in 12 weeks and up by 0.9 percentage points from the prior week. US Gulf coast suppliers are also eyeing strong fuel oil price competition from eastern hemisphere ports such as Singapore and Zhoushan, China, importing cheap Russian residual fuel oil. In general, LNG's substantial discount to VLSFO has kept interest in LNG for bunkering from ship owners with LNG-burning vessels high. The EIA discontinued publishing US bunker sales statistics with the last data available for 2020. But data from the Singapore Maritime & Port Authority, where the LNG–VLSFO discount widened to over $200/t VLSFOe in February, showed Singapore LNG for bunkering demand increase 11.4 times to 75,900t in the first quarter compared with 6,700t in the first quarter of 2023 and 110,900t for full year 2022. By Stefka Wechsler US Gulf coast LNG vs VLSFO $/t VLSFOe Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

India’s Chhara LNG terminal faces commissioning delay


24/04/23
24/04/23

India’s Chhara LNG terminal faces commissioning delay

Mumbai, 23 April (Argus) — Indian state-owned refiner HPCL's 5mn t/yr Chhara LNG import terminal is again facing delays in receiving and unloading its commissioning cargo, a market source told Argus . Fender failure at the terminal has caused problems in berthing the LNG vessel. The fender acts as a buffer or cushion between the ship hull and the dock, and prevents damage as a result of contact between the two surfaces. HPCL on 22 April issued a tender offering the commissioning LNG cargo , which is onboard the 160,000m³ Maran Gas Mystras. The vessel is currently laden offshore the terminal and ready to redeliver to another Indian LNG terminal on 25-30 April, according to HPCL. The company is seeking bids at a fixed price, and custom duty has already been paid by the firm. Indian firm Gujarat State Petroleum (GSPC) facilitate HPCL's purchase of the cargo on 26 March, with the cargo for delivery over 9-12 April. HPCL has put up the commissioning cargo for auction, and it can be discharged from any alternative port in India. LNG terminals closer to Chhara include Indian state-controlled importer Petronet's 17.5mn t/yr Dahej, Shell's 5.2mn t/yr Hazira or state-owned gas distributor Gail's 5mn t/yr Dhabol LNG terminal. HPCL also has not awarded a tender that is seeking another early-May delivery cargo , which closed on 19 April. Commissioning of the Chhara LNG terminal has been delayed since September 2022 owing to pipeline issues. The terminal is the country's eighth LNG import facility, which would lift total regasification capacity to 52.7mn t/yr from 47.7mn t/yr currently. The pipeline runs from the terminal and connects the city gas distribution network from Lothpur to Somnath district in Gujarat. There has been a delay in opening the pipeline as it passes through the eco-sensitive zone of the Gir wildlife sanctuary for 25.816km, a government document shows. The facility was completed in February, but is set to be closed from 15 May-15 September ahead of the completion of a breakwater facility , which is required to ensure safe LNG tanker berthing during India's monsoon season. No specific timeline has been given for building the breakwater, but the terminal will be able to operate year-round once it is completed. By Rituparna Ghosh Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

TotalEnergies to fully own Malaysian gas firm SapuraOMV


24/04/23
24/04/23

TotalEnergies to fully own Malaysian gas firm SapuraOMV

Singapore, 23 April (Argus) — TotalEnergies has signed an agreement to acquire Sapura Upstream Assets' 50pc stake in Malaysian private gas producer and operator SapuraOMV, which will take TotalEnergies' total stake to 100pc. The acquisition will cost $530mn, subject to closing adjustments, with closing expected to take place in the second half of this year, said TotalEnergies. This latest deal follows a previous agreement that TotalEnergies signed in January with Austrian firm OMV to acquire its 50pc interest in SapuraOMV. This means TotalEnergies will own 100pc of SapuraOMV once both transactions are completed. "Following the transaction with OMV announced two months ago and this new transaction with Sapura Upstream Assets, TotalEnergies will have full ownership of SapuraOMV and become a significant gas operator in Malaysia," said TotalEnergies' chairman and chief executive officer Patrick Pouyanné. "The SapuraOMV assets are fully in line with our strategy to grow our gas production to meet demand growth, focusing our portfolio on low-cost and low-emission assets," he added. SapuraOMV in 2023 produced 500mn ft³ of gas, which was used to feed the Bintulu LNG plant operated by state-controlled Petronas, as well as 7,000 b/d of condensates. SapuraOMV holds 40pc and 30pc operating interests, respectively, in blocks SK408 and SK310, which are offshore Sarawak, Malaysia. Block SK408's Jerun gas field, which could hold up to 84.9bn m³, is on track to start up in the second half of this year. SapuraOMV also has interests in exploration licences in Malaysia, Australia, New Zealand, and Mexico, where there was a discovery on block 30 last year, with estimated resources of 200mn-300mn bl of oil equivalent. TotalEnergies holds interests in two production sharing contracts in Malaysia. It in June last year signed an agreement with Petronas and Japanese trading firm Mitsui to jointly develop a carbon capture and storage project in Malaysia as well as assess maturing depleted fields and saline aquifers for storage. The firms hope to develop a CO2 merchant storage service to help industrial customers in Asia decarbonise. By Prethika Nair Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Australia’s Tamboran agrees NT gas sales deal


24/04/23
24/04/23

Australia’s Tamboran agrees NT gas sales deal

Sydney, 23 April (Argus) — Australian independent Tamboran Resources has signed a long-term gas sales agreement with the Northern Territory (NT) government for supplies from the Beetaloo joint venture's (BJV) proposed Shenandoah South pilot project. The binding deal for 40 TJ/d (1.07mn m³/d) on a take-or-pay basis from Shenandoah South in the onshore Beetaloo sub-basin of the NT equates to a total 131.4PJ (3.5bn m³) and begins in January-June 2026, running for nine years with an option to extend 6½ further years to 2042, Tamboran said on 23 April. This represent about two-thirds of the NT's present gas requirements and is conditional on the BJV entering a binding transportation agreement with pipeline operator APA for the planned 35km Sturt Plateau Pipeline , as well as reaching a final investment decision (FID) for Shenandoah South. Tamboran has a working interest of 47.5pc in Shenandoah South, which is aiming for a FID mid-year, following Canadian independent Falcon Oil and Gas' decision to reduce its participation from 22.5pc to 5pc in March to reduce its cost exposure to the project. BJV is operated by Tamboran, which holds a 50:50 interest in the Tamboran B2 joint venture with privately-held Daly Waters Energy controlled by US billionaire Bryan Sheffield. The BJV also holds a 10-year, 36.5 PJ offtake deal with Australian utility Origin Energy signed in 2022. The NT is dependent on gas-fired power generation. Continuing supply problems at Italian oil firm Eni's offshore Blacktip field has it currently sourcing gas from Australian independent Santos' depleting Bayu-Undan field in the Timor Sea and the onshore Mereenie joint venture . Tamboran is aiming in the long term to develop its proposed 6.6mn t/yr Northern Territory LNG project , for which it is aiming to complete initial engineering this year. By Tom Major Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.