US exports of coking coal in the first half of 2019 fell by 8.8pc year on year to 26.31mn t, driven down by falling demand in Asia, Latin America and Turkey, US Census Bureau data shows.

US coking coal shipments in June totalled 4.71mn t, down by 5.3pc year on year.

Exports to Asia totalled 7.59mn t in the first half of this year, down by 17.6pc compared with the same period last year. Shipments to India and China led the decline, dropping by 36.8pc to 3.69mn t and by 60.4pc to 667,140t, respectively.

While Indian imports of US coking coal have fallen, the outlook remains robust as Indian mills are expected to continue to look to the US as an alternative source of supply to Australian coking coal. Steel manufacturing is a key part of Delhi's Make in India campaign, which aims to triple steel output to 300mn t by 2030-31.

The fall in exports to China is in line with expectations, after Beijing imposed an additional 25pc tax on imports of US coal in June last year, and trade tensions between the two countries remained and have escalated since.

But shipments to Japan softened the drop in volumes to the region this year, likely boosted by Japanese mills looking to the US to make up the shortfall stemming from Australian supply disruptions in the first quarter. Exports of coking coal to Japan in the first half totalled 3.3mn t, up by 20.7pc on the year. Shipments to South Korea in the same period edged up 14.8pc year on year to 1.28mn t.

Latin America weakness

Coking coal shipments to Latin America totalled 4.13mn t in the first half, down by 11.6pc, pushed down by lower export volumes to Brazil and Mexico because contracting steel demand across the region has dragged down raw materials demand.

Brazil remained the largest importer of US coking coal, with its receipts reaching 3.54mn st in the first half but down by 10.9pc compared with the first half of 2018, while shipments to Mexico registered the largest drop, falling by 64.4pc on the year to 149,247t.

Mexico led Latin America's crude steel production decline of 4pc on the year to reach 31.3mn t for the first six months of this year. Finished steel production and consumption also fell, by 7pc and 2pc, to 25.6mn t and 27.3mn t, respectively. Steel demand across the entire region is contracting and Latin American steel industry association Alacero said it does not expect apparent consumption to exceed 68mn t for 2019.

Exports to Canada fell to 1.32mn t, down by 16.1pc on the year, likely a reflection of falling steel output levels in the country.

Term contracts keep Europe steady

Exports to Europe have been largely steady in the first half at 11.11mn t as US producers kept up their term contracted deliveries, despite a series of steel production output cuts that have been announced in the region since the spring.

Since late last year, European importers have taken a cautious approach to buying raw materials on the spot market but have kept up with their term commitments.

US shipments to the Netherlands were a healthy 2.79mn t in the first half, up by 13pc on the year.

But this was balanced by volumes to Germany falling by 63.5pc on the year to 309,681t in the first half of this year and exports to the UK falling by 31.9pc to 373,381t.

Potential growth

Exports to Ukraine were flat at 2mn st in the first half, but third-quarter volumes might see an increase as Ukrainian buyers look to the US for additional tons following Moscow's restrictions on Russian coal exports to Ukraine.

Exports to Turkey reached just 550,927t in the first half, down by 58.6pc as cost pressures amid increasingly challenging market conditions in the region have pushed Turkish mills towards cheaper alternative sources such as Russia and Colombia. But there are expectations that US coking coal sales to Turkey may increase from the August shipment period onward. Since Turkey cut its customs duty on imports of US coking coal to 5pc from 10pc, US producers have shown increased interest in supplying Turkish mills again.

Shipments in the first half to Africa have grown by 59.0pc to 1.61mn t, on the back of increased demand from Morocco.

US coking coal exports t
1H 20191H 2018Jun-19Jun-18
Brazil 3,540,6693,972,032656,265528,492
Mexico 149,247419,67948,61349,882
Canada1,321,7001,574,648354,250419,676
India 2,331,8303,688,501158,201711,185
China667,1401,683,184192,000445,674
Japan 3,298,8982,732,826673,803440,111
South Korea1,277,2641,113,040154,013180,000
Netherlands2,786,2672,466,435381,411491,080
Germany309,681848,812139,737104,819
UK373,381548,132-78,685
Ukraine2,001,7712,002,256286,283259,704
Turkey550,9271,329,978-165,731
Morocco1,354,697768,470210,824127,227
Others6,349,2575,718,5181,716,248705,403
Total26,312,72928,866,5114,971,6484,707,669

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

24/04/26

Japan’s JBIC to finance Chilean copper mine development

Japan’s JBIC to finance Chilean copper mine development

Osaka, 26 April (Argus) — Japan is enhancing its financial support for the development of copper mines in Chile, as part of efforts to increase its self-efficiency of base metals. State-owned Japan Bank for International Co-operation (JBIC) on 25 April signed a $248mn loan agreement with Chile-based joint-venture Compania Minera Arqueros (CMAQ) to finance development of its Arqueros copper project in Chile. CMAQ is 80pc owned by Japanese copper producer Nittetsu Mining and 20pc by Chilean firm Fondo de Inversion Privado Talcuna. The load will be co-financed by other Japanese private-sector financial firms, including Sumitomo Mitsui Banking, Mizuho Bank and MUFG Bank. The total co-funding will be $355mn. CMAQ plans to use the funding to develop Arqueros, located 35km northeast of La Serena. The mine is expected to produce 1.8mn t/yr of crude ore and 55,000 t/yr of copper concentrates for 15 years. The company aims to start operations in 2026. Nittetsu is to secure all the output from the project. The latest deal follows last month's loan agreement by JBIC and other financial institutes to provide $2.5bn to develop the Centinela copper mine in Chile . Japan relies on all its copper concentrates demand from imports, which has prompted the government to secure long-term and stable supplies of copper resources. The country's strategic energy plan has a target to achieve at least an 80pc self-sufficiency for base metals, including copper, by 2030. By Motoko Hasegawa Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

US economic growth slows to 1.6pc in 1Q


24/04/25
24/04/25

US economic growth slows to 1.6pc in 1Q

Houston, 25 April (Argus) — The US economy in the first quarter grew at a 1.6pc annual pace, slower than expected, while a key measure of inflation accelerated. Growth in gross domestic product (GDP) slowed from a 3.4pc annual rate in the fourth quarter, the Bureau of Economic Analysis (BEA) reported on Thursday. The first-quarter growth number, the first of three estimates for the period, compares with analyst forecasts of about a 2.5pc gain. Personal consumption slowed to a 2.5pc annual rate in the first quarter from a 3.3pc pace in the fourth quarter, partly reflecting lower spending on motor vehicles and gasoline and other energy goods. Gross private domestic investment rose by 3.2pc, with residential spending up 13.9pc after a 2.8pc expansion in the fourth quarter. Government spending growth slowed to 1.2pc from 4.6pc. Private inventories fell and imports rose, weighing on growth. The core personal consumption expenditures (PCE) price index, which the Federal Reserve closely follows, rose by 3.7pc following 2pc annual growth in the fourth quarter, although consultancy Pantheon Macroeconomics said revisions to the data should pull the index lower in coming months. The Federal Reserve is widely expected to begin cutting its target lending rate in September following sharp increases in 2022 and early 2023 to fight inflation that surged to a high of 9.1pc in June 2022. By Bob Willis Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Australia's MinRes posts higher 1Q spodumene output


24/04/25
24/04/25

Australia's MinRes posts higher 1Q spodumene output

Singapore, 25 April (Argus) — Perth-based major lithium and iron ore producer Mineral Resources (MinRes) has reported higher total spodumene concentrate output from its sites in January-March, and higher spodumene prices later in the quarter. Total attributable spodumene concentrate production of the firm across its assets rose to 170,000 dry metric tonnes (dmt) (see table for detailed breakdown), up by 3.7pc on the quarter and by 63pc on the year, according to the firm's latest quarterly activity report. Total attributable spodumene concentrate shipped volumes fell by 2.9pc on the quarter but rose by 50pc on the year to 166,000dmt. MinRes has an ambitious target of 1mn t/yr of lithium attributable within the next four years, said its managing director Chris Ellison last month during the firm's half-year results presentation. The firm has been aggressively expanding, several delegates told Argus at the Tribeca Future Facing Commodities conference held in Singapore on 26 March. The firm last month agreed to buy fellow developer Poseidon Nickel's concentrator plant in Western Australia as it seeks to retrofit it for lithium processing. MinRes' Mount Marion site saw higher output, driven by higher plant utilisation and improved ore recoveries as the firm continues to advance its plant improvement initiatives. The realised price for spodumene concentrate out of its Mount Marion site was at $718/dmt on a 4.2pc-grade basis, which was above the product's year-to-date fob costs of A$518/dmt ($338/dmt). The realised price translates to $1,048/dmt for 6pc-grade lithium concentrate (spodumene), said the firm. The firm did not process the spodumene concentrate produced from its Wodgina site during the quarter into lithium battery chemicals, citing "prevailing pricing dynamics", but instead resumed spodumene concentrate spot sales. The realised spodumene concentrate price at the site came in at $974/dmt on 5.6pc-grade basis, which translates to $1,028/dmt for 6pc-grade lithium concentrate (spodumene). The lithium battery chemical realised price, excluding value added tax, came in at $11,098/t. MinRes in November 2023 finalised the acquisition of the Bald Hill lithium mine from Alita Resources. January-March was the mine's first full production quarter, hence output was dragged down by limited availability of higher-grade feed, but this is expected to recover in April-June, said the firm. The realised spodumene concentrate price at the Bald Hill site was $878/dmt on 5.1pc-grade basis, which translates to $1,016/dmt for 6pc-grade spodumene concentrate. Argus -assessed prices for 6pc grade spodumene concentrate dipped to $1,080-1,180/t cif China on 23 April, from $1,100-1,200/t cif China a week earlier. Salts producers reduced spodumene bid prices because of a fall in salts prices two weeks earlier. By Joseph Ho MinRes lithium performance Jan-Mar '24 Oct-Dec '23 Jan-Mar '23 Spodumene concentrate production (k dmt) Mt Marion (50pc attributable basis) 91 83 60 Wodgina (50pc attributable basis) 49 55 44 Bald Hill (100pc attributable basis) 30 26 NA Total 170 164 104 Spodumene concentrate shipments (k dmt) Mt Marion (50pc attributable basis) 76 86 62 Wodgina (50pc attributable basis) 64 65 49 Bald Hill (100pc attributable basis) 26 20 NA Total 166 171 111 Lithium battery chemical (t) Wodgina production (50pc attributable basis) 6,793 6,798 3,246 Wodgina sales (50pc attributable basis) 6,954 6,474 1,504 Source: MinRes MinRes previously owned 40pc of the Wodgina project, which increased to 50pc starting from 18 October 2023. Figures for Wodgina before 18 October 2023 were on 40pc attributable basis. Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

EV demand slowdown cuts S Korea’s LGES' profit in 1Q


24/04/25
24/04/25

EV demand slowdown cuts S Korea’s LGES' profit in 1Q

Singapore, 25 April (Argus) — South Korea's top battery manufacturer LG Energy Solution (LGES) reported significant lower revenue and profit in January-March, because of lower battery metal prices and slower electric vehicle (EV) demand. LGES' revenue in January-March fell by 23pc on the quarter and 30pc on the year to 6.13 trillion won ($4.46bn), owing to lower demand for EV pouch cells and energy storage system (ESS), with "prolonged metal price impact" affecting its average selling price. The firm reported W157bn of operating profit in January-March, but would have reported an operating loss of W32bn if it did not receive almost W189bn in US Inflation Reduction Act (IRA) tax credits. But this was still a sharp drop from W633bn of operating profit for January-March 2023. The lower revenue and a demand slowdown in the EV market led to utilisation rate adjustments that weighed on its financial performance. The firm reaped a net profit of W212bn during the quarter, which was up by 12pc on the quarter but down by around 62pc on the year, likely significantly propped up by the US' IRA tax credits. LGES said it will continue to invest despite the difficult market environment, but will "adjust" the size of its capital expenditure and execution speed "as per priority". Battery project updates LGES and automaker General Motors in early April completed the first battery shipment out of their second Ultium battery cell factory in US' Tennessee. The plant's capacity is expected to gradually expand to 50 GWh/yr, said LGES. Construction progress at the firm's battery manufacturing complex in US' Arizona is also on track, said the firm. Ramped up capacity is expected to be 53 GWh/yr, which will comprise 36 GWh/yr of 46-series cylindrical battery for EVs and 17 GWh/yr of lithium-iron-phosphate battery for ESS. LGES' 10 GWh/yr Indonesian battery production joint venture with South Korean conglomerate Hyundai Motor has also started mass production. Its battery module production joint venture with automaker Stellantis in US' Ontario, which encountered a halt in construction in May last year, will start operations in the second half of 2024. The factory has a planned capacity of 45GWh/yr and was supposed to begin operations early this year. LGES earlier this year inked a second agreement with Australian firm Wesfarmers Chemicals, Energy and Fertilisers for lithium concentrate supply. The firm will continue building a raw materials supply chain within regions that have a free trade agreement with US, it said. By Joseph Ho Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Barge delays at Algiers lock near New Orleans


24/04/24
24/04/24

Barge delays at Algiers lock near New Orleans

Houston, 24 April (Argus) — Barges are facing lengthy delays at the Algiers lock near New Orleans as vessels reroute around closures at the Port Allen lock and the Algiers Canal. Delays at the Algiers Lock —at the interconnection of the Mississippi River and the Gulf Intracoastal Waterway— have reached around 37 hours in the past day, according to the US Army Corps of Engineers' lock report. Around 50 vessels are waiting to cross the Algiers lock. Another 70 vessels were waiting at the nearby Harvey lock with a six-hour wait in the past day. The closure at Port Allen lock has spurred the delays, causing vessels to reroute through the Algiers lock. The Port Allen lock is expected to reopen on 28 April, which should relieve pressure on the Algiers lock. Some traffic has been rerouted through the nearby Harvey lock since the Algiers Canal was closed by a collapsed powerline, the US Coast Guard said. The powerline fell on two barges, but no injuries or damages were reported. The wire is being removed by energy company Entergy. The canal is anticipated to reopen at midnight on 25 April. By Meghan Yoyotte Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more