Tokyo defends nuclear programme with court order appeal

  • Market: Coal, Electricity, Emissions, Natural gas
  • 17/12/20

Japan's government has outlined its determination to defend its nuclear industry, seeking to overturn a court ruling that has cast doubt over the country's reactor safety clearance system.

The government today appealed the Osaka district court's 4 December ruling that revoked regulatory approval for the two Ohi nuclear reactors operated by utility Kansai Electric Power. The appeal will start an expected lengthy legal battle but allows Kansai to continue operations of the Ohi reactors until the lawsuit closes and a final verdict is made.

The appeal gives temporary relief to Kansai, which otherwise would have been forced to continue meeting its winter peak power demand season without any nuclear power output. The company has been forced to delay a planned restart of the 870MW Takahama No.3 reactor at least until February, as additional work may be necessary at the reactor following the discovery of technical issues at the Takahama No.4 reactor.

Both of Ohi's reactors are currently closed for regular maintenance. The 1,180MW Ohi No.4 reactor is expected to be reactivated in mid-January next year and resume normal operations in February. But it remains unclear when the 1,180MW Ohi No.3 reactor can be restarted after damage to the reactor's pressuriser spray line.

Kansai earlier this month temporarily halted part of the counterterrorism reinforcement work being done during regular maintenance at the Ohi No.3 reactor because of a Covid-19 outbreak. The firm is required to complete reinforcement work of the Ohi No. 3 reactor by August 2022.

Safety consequences

The Osaka district court's ruling, if finalised, could have serious consequences for other Japanese reactors. It is the first judgement to reject Japan's stricter reactor safety clearance system introduced in the wake of the 2011 Fukushima-Daiichi nuclear disaster.

The appeal follows Japan's nuclear regulation authority (NRA) yesterday clarifying its safety clearance procedure examining a possible earthquake affecting the Ohi nuclear reactors.

The government and the ruling Liberal Democratic Party coalition administration have backed the nuclear power industry despite public distrust following the Fukushima disaster. Nuclear remains a key power source for Japan, with the government reiterating it will stick with its policy of swiftly restarting nuclear reactors when they have met the strict safety standards set by the NRA.

The industry ministry is working to review Japan's energy policies to fit with a 2050 target to achieve net-zero greenhouse gas emissions. The new basic energy policy, due for review every 3-4 years, is expected to usher in an increased focus on electricity derived from renewables and a clearer nuclear policy direction for a decarbonised society in the next 30 years. Japan is planning to generate 20-22pc of its 2030 power output with nuclear and 22-24pc with renewables.

Legal battles

Numerous lawsuits have been filed in Japan since the Fukushima disaster to halt nuclear reactors, with about 30 ongoing cases, including many against reactors that have been cleared by the NRA and restarted. Japan has restored only a third of its 33,235MW nuclear power capacity, or nine out of the country's 33 existing reactors, since the Fukushima disaster.

The Ikata No.3 reactor has been closed following a court injunction issued in January this year. A high court is expected to rule in March next year on an appeal filed by operator Shikoku Electric Power to repeal the court order. The injunction barring Ikata's restart remains effective unless it is cancelled, or until a final judgment is delivered for the main lawsuit in process since 2017 at the Yamaguchi district court.

A ruling is expected in March next year at the Saga district court for a lawsuit to revoke operating permits of Kyushu Electric Power's Genkai No.3-4 reactors. The 1,180MW Genkai No.3 reactor returned to full commercial operations on 15 December following regular maintenance, while the 1,180MW Genkai No.4 reactor is scheduled to close for maintenance on 19 December.


Sharelinkedin-sharetwitter-sharefacebook-shareemail-share

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

News
17/05/24

Brazil's Rio Grande do Sul reallocates gas supply

Brazil's Rio Grande do Sul reallocates gas supply

Sao Paulo, 17 May (Argus) — Natural gas supply in Brazil's Rio Grande do Sul had to be redistributed because of the historic floods in the state, with diesel potentially making its way back as an power plant fuel to leave more gas available for LPG production. Gasbol, the natural gas transportation pipeline that supplies Brazil's south, does not have capacity to meet demand from the 201,000 b/d Alberto Pasqualini refinery (Refap), state-controlled Petrobras' Canoas thermal power plant and natural gas distributors in the region, according to Petrobras' then-chief executive Jean Paul Prates said earlier this week. The Santa Catarina state gas distributor has adjusted its own local network to meet peak demand in neighboring Rio Grande do Sul via the pipeline transportation network. The Canoas thermal plant is running at its minimum generation at 150GW, with 61pc coming from its gas turbine. The plant was brought on line to reinstate proper power supply after transmission lines in the south were affected by the floods. Petrobras plans to use a diesel engine to increase power generation. The current approved fuel cost (CVU) for diesel in the Canoas plant is of R1,115.29/MWh. Petrobras is also operating Refap at 59pc of its maximum installed capacity, at 119,506 b/d. Heavy showers in Rio Grande do Sul since 29 April brought unprecedented flooding to the state, causing a humanitarian crisis and infrastructure damage. The extreme weather has left 154 people dead, 98 missing and over 540,000 people displaced, according to the state's civil defense. By Rebecca Gompertz Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Find out more
News

Japan’s Jera to handle 35mn t/yr LNG until FY2035-36


17/05/24
News
17/05/24

Japan’s Jera to handle 35mn t/yr LNG until FY2035-36

Osaka, 17 May (Argus) — Japan's largest LNG importer Jera plans to maintain its LNG handling volumes at no less than 35mn t/yr until the April 2035-March 2036 fiscal year. Rising renewable power supplies and the possible return of more nuclear reactors are likely to pressure LNG demand from Japan's power sector. Jera consumed 23mn t of LNG in 2023-24, down by 3pc on the year, although it handled 35mn t through its global operations during the same year. But Jera needs to secure sufficient LNG supplies to adjust for imbalances in electricity supplies and ensure power security, through more flexible operations. It is also looking to further promote LNG along with renewable electricity in Asian countries, while helping to reduce their dependence on coal- and oil-fired power generators. The 2035 target for LNG is part of Jera's three pillars of strategic focus, along with renewables as well as hydrogen and ammonia , which was announced on 16 May to spur decarbonisation towards its 2050 net zero emissions goal. The company plans to invest ¥5 trillion ($32bn) for these three areas over 2024-36. Jera also aims to retire all supercritical or less efficient coal-fired units by 2030-31 . This would help achieve the company's target of cutting CO2 emissions from its domestic business by at least 60pc against 2013-14 levels by 2035-36. By Motoko Hasegawa Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Biomass start-ups lift Japan's Renova April power sales


17/05/24
News
17/05/24

Biomass start-ups lift Japan's Renova April power sales

Tokyo, 17 May (Argus) — Japanese renewable power developer Renova's electricity sales doubled on the year in April, following the start-up of three biomass power plants in the past six months. Renova sold 199,601MWh of electricity — including solar, biomass and geothermal — in April, double the 99,857MWh a year earlier, the company announced on 13 May. The 75MW Sendai Gamo plant in northeastern Miyagi prefecture started operations in November 2023 and produced 40,753MWh in April. The 74.8MW Tokushima Tsuda plant in western Tokushima prefecture, which was commissioned in December 2023, generated 10,870MWh in April. The 75MW Ishinomaki Hibarino plant in Miyagi began normal runs in March and supplied 49,495MWh in April. Renova plans to add 124.9MW biomass-fired capacity in the April 2024-March 2025 fiscal year, with the 75MW Omaezaki plant in central Shizuoka city scheduled to begin commercial operations in July, followed by the 49.9MW Karatsu plant in southern Saga city in December. Omaezaki is currently conducting trial runs and Karatsu is under construction. The additions will increase Renova's biomass-fired capacity to 445MW. By Takeshi Maeda Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

EBRD ‘green project’ funding hit €6.54bn in 2023


15/05/24
News
15/05/24

EBRD ‘green project’ funding hit €6.54bn in 2023

London, 15 May (Argus) — The European Bank for Reconstruction and Development (EBRD) hit a record level of investments in the "green economy" in 2023, at €6.54bn ($7.1bn) in 337 projects — up from €6.36bn in 2022. The multilateral development bank (MDB) again reached its target for at least 50pc of its total annual investment to go towards green projects. Of total investments, 50pc went to green projects — flat on the year. The EBRD initially set the goal for 2025, but hit it in 2021, with 51pc of its investment going to green projects. The EBRD's investments stood at €13.1bn in 2023 — a new record high — going towards 464 individual projects. The bank has since the beginning of 2023 ensured that all new investment projects are in line with the Paris climate agreement goals. The Paris agreement seeks to limit the rise in temperature to "well below" 2°C above pre-industrial levels, and preferably to 1.5°C. Countries' focus on MDBs and their role in delivering climate finance has intensified in recent years. Climate finance is set to dominate climate talks this year, including at the UN Cop 29 summit, set for November in Baku, Azerbaijan. Mukhtar Babayev, Cop president-designate, last month called on MDBs and parties to the Cop process to deliver on climate finance. The EBRD is owned by 73 shareholder governments, the EU and the European Investment Bank. By Georgia Gratton Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Chinese importers seek five LNG cargoes for Jun-Sep


15/05/24
News
15/05/24

Chinese importers seek five LNG cargoes for Jun-Sep

Shanghai, 15 May (Argus) — Five Chinese importers, mostly second-tier buyers, are each seeking one LNG cargo for June-September delivery, according to an official notice published by China's national pipeline operator PipeChina on 15 May. The five importers are PipeChina, Chinese independent ENN, Hong Kong-listed city gas firm China Resources Gas, Hong Kong-based Towngas and state-owned China Gas. PipeChina and ENN have indicated a target price of at most $9.50/mn Btu for their intended cargoes, both for delivery to PipeChina's 6mn t/yr Tianjin terminal. China Gas has indicated a target price of at most $9.30/mn Btu for delivery to PipeChina's 6mn t/yr Beihai termial. China Resources Gas and Towngas have both indicated a target price of at most $9/mn Btu for delivery to PipeChina's 2mn t/yr Yuedong and Tianjin terminals, respectively. This consolidated requirement came about because of a need for PipeChina to better leverage on its infrastructure advantages and, at the same time, meet the varying needs of gas importers and consumers in the country. But this requirement comes at a time when spot LNG prices are still somewhat higher than the importers' targeted prices. But the importers can choose not to buy if offers are not within their expectations. The front-half month of the ANEA, the Argus assessment for spot LNG deliveries to northeast Asia, was last assessed at $10.485/mn Btu on 15 May. Chinese importers mostly perceive spot prices below $9-9.50/mn Btu for June-September deliveries to be unattainable for now because there is strong buying interest from south and southeast Asia in particular. Indian state-controlled refiner IOC most recently bought LNG for delivery between 22 May and 15 June at around $10.60/mn Btu, through a tender that closed on 14 May. Thailand's state-controlled PTT most recently bought three deliveries for 9-10 July, 16-17 July and 22-23 July through a tender that closed on 13 May , at just slightly above $10.50/mn Btu. The most recent spot transaction was Japanese utility Tohoku Electric's purchase of a 10-30 June delivery at around $10.55/mn Btu through a tender that closed on 14 May . This is at least $1/mn Btu higher than Chinese importers' indications. Summer requirements have so far been muted but concerns among buyers about potential supply disruptions remain. Malaysia's 30mn t/yr Bintulu LNG export terminal suffered a power loss on 10 May, but this issue may have been resolved as of early on 15 May, according to offtakers. Some unspecified upstream issues may still be affecting production at the Bintulu facility, resulting in Malaysia's state-owned Petronas having to ask some of its buyers for cargo deferments, according to offtakers. Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more