Australian mining firm Australian Pacific Coal (AQC) is planning to restart its Dartbrook thermal coal mine soon after multiple attempts to do so over the past five years.

The underground mine produced and transported coal to the surface on 4 September, the first time since it was placed into care and maintenance in 2006, AQC said on 5 September.

The Dartbrook mine is located in the Hunter valley coal mining region in New South Wales. It could potentially produce 5mn t/yr of thermal coal.

AQC had installed and tested a 4km conveyor system designed to transport coal produced from the Kayuga seam to the surface via the Hunter Tunnel. The coal will then be processed at a handling and preparation plant.

"Commissioning is under way and the team on the ground is working hard to bring the mine safely into commercial production in the coming weeks," said AQC managing director and chief executive Ayten Saridas.

Dartbrook will initially only produce unwashed thermal coal for sale to domestic or export customers when it resumes operations, the company said. Once the coal handling and preparation plant is refurbished early next year, the mine will produce washed and graded coal with high-calorific values (CV) for export. It may also produce semi-soft or pulverised coal injection coal.

Dartbrook was placed into care and maintenance by its previous owner, UK-South African mining firm Anglo American, in 2006 when high-CV NAR 6,000 kcal/kg coal was as low as $50/t fob Newcastle. AQC had hoped to restart the mine in 2019 but was delayed by opposition from local communities and a fraught approvals process. Australian high-CV coal prices have rallied recently on concerns regarding natural gas supplies arising from the Russia-Ukraine conflict. Argus last assessed the price of NAR 6,000 kcal/kg coal at $143.92/t fob Newcastle on 30 August.


Sharelinkedin-sharetwitter-sharefacebook-shareemail-share

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

News

Japan to phase out inefficient coal plants by 2030


03/10/24
News
03/10/24

Japan to phase out inefficient coal plants by 2030

London, 3 October (Argus) — Japan will target a phase-out of inefficient coal plants by 2030, as it continues its energy transition push, although the country is still yet to provide further details on any broader movement away from coal. "By 2030, the inefficient use of coal-fired power will be phased out," Japan's newly appointed environment minister Keiichiro Asao said at a press conference on Wednesday. Asao was appointed after Japan's new prime minister Shigeru Ishiba took office this week. Japan had earlier pledged to phase out "unabated" coal-fired plants by 2035 , or "in a timeline consistent with keeping a limit of a 1.5°C temperature rise within reach, in line with countries' net zero pathways". But inefficient, sub-critical coal plants — with below 40pc efficiency — make up only 22pc of Japan's total fleet, while 25pc is supercritical and 53pc is ultra-supercritical. The sub-critical plants probably produce less of Japan's coal-fired electricity, given the generation margins for them will fall below the majority of gas-fired generation in the merit order. This means Japan's overall coal-fired power generation is likely to be less impacted than the overall change to its coal fleet capacity. Japan has been considered a laggard in green energy transition among its G7 counterparts, but the country's coal demand could decline to some extent as a result of global divestment pressure. But coal is still key to the resource-poor country, as the government sees renewables and nuclear as insufficient to meet rising power demand driven by the growth of data centres needed to enable artificial intelligence. Japan's new government has recently announced that it will be restarting more of its nuclear reactors to help meet its power demand. Utility Shikoku Electric Power reactivated its sole nuclear reactor at Ikata on 29 September, after closing the unit for turnaround since 19 July. But the utility pushed back the restart of the 890MW Ikata No.3 nuclear reactor on Wednesday because of a technical issue during the process of resuming power generation. Japanese thermal coal imports rose by 10pc to 9.25mn t on the year in August, owing to increased deliveries from Australia. But this was 4pc lower than the past five-year August average of 9.6mn t. By Shreyashi Sanyal Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Colombia coal mining could halt with government decree


03/10/24
News
03/10/24

Colombia coal mining could halt with government decree

Bogota, 3 October (Argus) — Colombia's coal operations could come to a stop as the government will soon start issuing resolutions that regulate mining areas as temporary environmental reserves, Colombian Mining Association (ACM) director Juan Camilo Narino said. The decree, enacted on 30 January, states the country's environment ministry will identify, delimit and declare through administrative acts reserves of natural resources in areas that require restoration and rehabilitation. Such areas will become environmentally protected zones for five years with the possibility of extending that period for an additional five years. The decree takes away the autonomy and competence of the Regional Autonomous Corporations, which until now grants key licensing to keep coal operations running, but without those licences, coal operations could come to a halt, Narino told Argus on the sidelines of a hydrocarbon summit held in Cartagena. Narino said coal, gold, copper and other types of mining firms are extremely concerned with the potential resolutions due to be issued as they need minor licences granted by the corporations. Such licensing includes environmental licences to pour water into channels, take water from rivers and to pass over rivers. The environment ministry is likely to announce those resolutions at the CBD Cop 16 in Cali, Colombia, on 21 October-2 November. Colombia is set to champion a comprehensive and regionally inclusive approach to biodiversity conservation and climate action at this conference. "The decree clearly states that those corporations could no longer grant permits," Narino said. "As a result, the operating activity of existing licences is unfeasible as you can no longer operate without those minor licences." ACM has filed a lawsuit against the decree, while 11 industry unions, including the regional autonomous corporations, joined in suing the government in a lawsuit submitted on 6 August. They filed the lawsuits with Colombia's state council, the highest administrative court in the country, while requesting precautionary measures including halting the decree. The state council agreed on studying the lawsuit and could annul the ruling, but it could take 6-12 months to examine the case. The state council must listen to the defendants — the environment ministry — lawyer Luis Eduardo Delgado Martinez said. Environmental minister Susana Muhamad was summoned by congress to face a political control debate to explain the scope of the decree, Narino noted. Narino levelled several other criticisms against the decree, including calling the time frame of the temporary environmental reserve designations arbitrary. He also said IT bypasses other legal and constitutional norms. By Diana Delgado Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Groups challenge Montana coal mine expansion


01/10/24
News
01/10/24

Groups challenge Montana coal mine expansion

Houston, 1 October (Argus) — A number of conservation groups are challenging Montana regulators' approval of a mining expansion at Signal Peak Energy's Bull Mountains coal mine in Montana. Earthjustice filed a complaint for declaratory relief with the Montana 13th Judicial District Court on 27 September, claiming the state Department of Environmental Quality's (DEQ) environmental analysis of Signal Peak's permit application was insufficient. The complaint accuses the Montana DEQ of violating the Montana Environmental Policy Act (MEPA) by inadequately analyzing the mine expansion's potential effects on water supplies and cultural resources. Earthjustice is representing Bull Mountains Land Alliance, Northern Plains Resource Council and the Montana Environmental Information Center in the lawsuit. The environmental assessment and permit amendment approved by the state DEQ in August allows operators of the Bull Mountains mine to access an additional 12.7mn short tons (11.5mn metric tonnes) of recoverable coal. Environmental groups claim the Montana DEQ failed to assess the expansion's "cumulative and secondary impacts […] to water quantity, wildlife, unique resources and cultural and historical sites, greenhouse gas pollution, agriculture, worker safety and the community's inevitable transition from coal mining to other, more sustainable sources of revenue", the environmental groups argue in the lawsuit filed on 27 September. Additionally, DEQ's decision to not prepare an environmental impact statement — which is more comprehensive than an environmental assessment — before permitting the Signal Peak coal mine expansion also violated MEPA because such a statement is required by state agencies if a proposed action is expected to "significantly affect the quality of the human environment", the complaint stated. The Montana DEQ said it does not comment on active litigation. Signal Peak did not respond immediately to a request for comment. Signal Peak applied for the permit amendment on 7 November 2023. That came nine months after the US District Court for the District of Montana vacated a federal agency's approval of a different plan to expand Bull Mountains' mining on federal land after the US 9th Circuit Court of Appeals found fault with the US Office of Surface Mining Reclamation and Enforcement's (OSMRE) environmental assessment of the plan. OSMRE has not yet concluded a revised analysis of that plan. By Anna Harmon Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

OECD's coal power in 2023 falls to half its peak: Ember


01/10/24
News
01/10/24

OECD's coal power in 2023 falls to half its peak: Ember

Singapore, 1 October (Argus) — The OECD's coal generation fell to just 17pc of its total power generation in 2023, down from 36pc at its peak in 2007, because of rapid growth in solar and wind power, according to think-tank Ember. A third of the 38 OECD countries are now coal-free, according to Ember's report on coal generation in OECD countries published on 1 October. The UK closed its last coal-fired power plant, the Ratcliffe-on-Soar, on 30 September , making it the 14th OECD country to achieve coal-free power. About three-quarters of the OECD nations will be coal-free by 2030. The majority of coal has been replaced by wind and solar power, which increased by 1,723TWh, or eleven-fold, over 2007-23. Only Turkey set a new record-high for coal generation in 2023, indicating it has not yet passed its peak. The country raised the share of coal in its electricity supply to 37pc, overtaking Poland as the second-biggest coal generator in Europe after Germany. There are also a number of countries in the OECD that still rely on coal for more than a quarter of their electricity needs, such as Poland with 61pc of its power mix, Australia with 46pc, the Czech Republic with 40pc and Germany with 27pc. But even countries that have been slower to phase out coal are still planning to reduce its share in their electricity mix, such as Japan, which aims to cut coal generation from 32pc in 2023 to 19pc by 2030, and South Korea, which targets to halve coal from 33pc in 2023 to 17pc in 2030. The drop in coal-fired power generation has also led to a 28pc drop in the OECD's power sector emissions over 2007-23, according to the report, although it did not provide further details on emissions reductions. Countries are boosting renewable electricity to cater to the increase in electricity demand, while reducing fossil fuels. Electricity demand in the OECD rose by just 1pc, so the growth in renewables was able to replace fossil fuels instead of "just meeting new demand," stated the report. But coal-powered generation globally hit a new record in 2023 as the fall in the OECD's coal power was outweighed by increasing coal-fired power in emerging Asian economies. OECD countries should end coal use by 2030 to align with the global warming limit of 1.5°C above pre-industrial levels the Paris Agreement seeks, energy watchdog the IEA and research institute Climate Analytics said. The OECD is working on a "gold standard" for financial institutions as part of the coal transition accelerator initiative, and the standard will provide clear guidelines on creating a robust financing policy or strategy to transition away from coal. By Prethika Nair Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.