Australian independent Woodside Energy has signed a long-term supply deal with oil major BP for feedstock gas for the first two stages of its Louisiana LNG project, totalling 16.5mn t/yr, ahead of first production planned for 2029.
The agreement is the first in a series of planned deals enabling diversified supply into the three-train Louisiana LNG project, with up to 640bn ft³ (18bn m³) to be piped to the facility via the proposed Line 200, Woodside said on 30 April.
Lines 200 and 300 form one of two interstate pipeline schemes proposed as part of the project. The dual 42-inch pipelines running about 37 miles (60 km) and 34 miles respectively from Ragley in Beauregard Parish to Carlyss in Calcasieu Parish, Louisiana, have planned capacity of 4.6bn ft³/d with maximum seasonal capacity of 5.7bn ft³/d, Woodside said.
The 96-mile Driftwood mainline pipeline to be built through Evangeline, Acadia, Jefferson Davis and Calcasieu parishes will average 4bn ft³/d, Woodside said.
Woodside reached a final investment decision for Louisiana LNG on 29 April after selling down 40pc of the project's infrastructure to US-based investment firm Stonepeak in early April. The facility holds permits for 27.6mn t/yr of capacity, with an eventual total of five trains planned.