Karpowership races to make South African bid deadline

  • Market: Natural gas
  • 23/07/21

Turkish firm Karpowership is pulling out all the stops to meet a tight deadline for its three proposed offshore gas-fired power projects in South Africa to reach financial close, but it seems unlikely to succeed.

Karpowership was selected in March as one of the preferred bidders to provide emergency power under a government scheme that will fast-track 2GW to alleviate South Africa's electricity crisis.

The Department of Mineral Resources and Energy (DMRE) set 31 July 2021 as the deadline for all projects under its Risk Mitigation Independent Power Producer Procurement Programme (RMIPPPP) to reach financial close.

The DMRE has confirmed to Argus that this deadline still stands, despite hints from DMRE minister Gwede Mantashe earlier this month that the previously non-negotiable timeline could be eased. "If it is emergency procurement, we should deal with as if it's an emergency," he said.

But according to the DMRE, "all preferred bidders are [still] expected to meet the deadline" and Karpowership told Argus that it was still working towards achieving this.

The firm was appointed to provide 1.22GW — nearly two thirds of the overall tender — over 20 years using gas-fired power ships berthed at Richards Bay in Kwazulu-Natal, Coega in Eastern Cape and Saldanha in Western Cape.

But last month the Department of Forestry, Fisheries and the Environment (DFFE) refused to grant it the necessary environmental permission, having earlier suspended the firm's application. On 13 July, Karpowership lodged an appeal against the DFFE's decision based on multiple grounds.

It argues that its projects are "vital" for easing South Africa's load-shedding crisis by offering the country access to the "cleaner, more reliable electricity needed to… create a more inclusive economy."

Karpowership refutes the claim that it did not conduct a proper public participation process, and says the fact that nearly 48 local organisations came out in support of its projects is testament to this.

It further dismisses the DFFE's complaint that it did not conduct a thorough study of the impact of its ships' underwater noise on the marine environment. Karpowership says it is impossible to study the impact of a vessel that is not yet in place and, instead it submitted a "rigorous study" of an identical ship in a similar fishing environment in Ghana, on which it then modelled its South African project proposals.

Karpowership's selection as preferred bidder has been heavily criticised by environmental campaigners and other groups.

Apart from Karpowership's plea, the DFFE is currently also considering appeals from other interested and affected parties, who had until 19 July to submit their petitions. Once this has been done, the DFFE has 20 days to respond to appellants. After this, the appeal administrator will draft recommendations to the minister of forestry, fisheries and the environment, Barbara Creecy.

Given that the DFFE could decide Karpowership's appeal as late as September, the firm is unlikely to make the deadline for its projects to reach financial closure.

Nevertheless, the DMRE declined to explicitly say if Karpowership would be disqualified as preferred bidder if it missed the crucial deadline, saying that "the matter is still in court and as such it would be sub-judice".

The DMRE, alongside Karpowership, is currently fighting a lawsuit that was launched by South African LNG importer DNG Energy, which claims that the bid process was rigged in favour of the Turkish firm. DNG is seeking an urgent court interdict to have the appointment reviewed and set aside.

At the same time, Karpowership is facing a probe by the national prosecution agency.

The DFFE's environmental management inspectors known as the Green Scorpions on 15 June referred Karpowership to the Director of Public Prosecutions North Gauteng after investigating the circumstances that led to the authorisation of the firm's project last year. The department revoked its permission after it transpired that Karpowership used Covid-19 emergency provisions to bypass environmental assessment requirements.

The Green Scorpions' referral of the matter to the national prosecution agency indicates that they uncovered prima facie evidence of an offence by Karpowership.

Despite all these challenges, Karpowership still appears determined to win a share of the RMIPPPP tender. "We have confidence in South Africa's institutions, look forward to the next steps, and are eager to get to work generating cleaner, reliable electricity for South Africa," it told Argus.


Sharelinkedin-sharetwitter-sharefacebook-shareemail-share

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

News
25/04/24

LNG Energy eyes sanctions-hit Venezuela oil blocks

LNG Energy eyes sanctions-hit Venezuela oil blocks

Caracas, 25 April (Argus) — A Canadian firm plans to revive two onshore oil blocks in Venezuela, but the conditional deals signed with struggling state-owned PdV come just as the US is reinstating broad sanctions on the South American country. LNG Energy Group's Venezuela unit agreed two deals with PdV to boost output in five fields in the Nipa-Nardo-Niebla and Budare-Elotes blocks, which produce about 3,000 b/d of light- to medium-grade crude, the company said on Wednesday. The Canadian company, which operates in neighboring Colombia, would receive 50-56pc of production of the blocks. Venezuela's oil ministry declined to comment. But finalizing the contracts depends on providing required investment to develop the fields within 120 days of the contract signing on 17 April, LNG Energy said. And the signing came on the same day as the US reimposed oil sanctions on Venezuela and gave most companies until 31 May to wind down business. LNG Energy Group said it intends to comply with existing and upcoming US sanctions, noting that the conditional contracts were executed within the terms of the temporary lifting of sanctions — general license 44 — but it will abide by the new license 44A. The reimposition of US sanctions on Venezuela prohibits new investment in the country's energy sector, at the threat of US criminal and economic penalties. "The company will assess in the coming days the applicability of license 44A to its intended operations in Venezuela and determine the most appropriate course of action," LNG Energy said. "The company intends to operate in full compliance with the applicable sanctions regimes." The two blocks are in the adjacent Anzoategui and Monagas states, part of the Orinoco extra heavy oil belt. Most of Venezuela's output is medium- to heavy-grade crude. Both PdV and Chevron have drilling rigs working in those two states, in separate workover and drilling campaigns. Venezuela is now producing above 800,000 b/d, after the US allowed Chevron to increase production and investment under separate waivers. By Carlos Camacho Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Read more
News

US economic growth slows to 1.6pc in 1Q


25/04/24
News
25/04/24

US economic growth slows to 1.6pc in 1Q

Houston, 25 April (Argus) — The US economy in the first quarter grew at a 1.6pc annual pace, slower than expected, while a key measure of inflation accelerated. Growth in gross domestic product (GDP) slowed from a 3.4pc annual rate in the fourth quarter, the Bureau of Economic Analysis (BEA) reported on Thursday. The first-quarter growth number, the first of three estimates for the period, compares with analyst forecasts of about a 2.5pc gain. Personal consumption slowed to a 2.5pc annual rate in the first quarter from a 3.3pc pace in the fourth quarter, partly reflecting lower spending on motor vehicles and gasoline and other energy goods. Gross private domestic investment rose by 3.2pc, with residential spending up 13.9pc after a 2.8pc expansion in the fourth quarter. Government spending growth slowed to 1.2pc from 4.6pc. Private inventories fell and imports rose, weighing on growth. The core personal consumption expenditures (PCE) price index, which the Federal Reserve closely follows, rose by 3.7pc following 2pc annual growth in the fourth quarter, although consultancy Pantheon Macroeconomics said revisions to the data should pull the index lower in coming months. The Federal Reserve is widely expected to begin cutting its target lending rate in September following sharp increases in 2022 and early 2023 to fight inflation that surged to a high of 9.1pc in June 2022. By Bob Willis Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

India’s Gail to shut Dabhol LNG terminal for monsoon


25/04/24
News
25/04/24

India’s Gail to shut Dabhol LNG terminal for monsoon

Mumbai, 25 April (Argus) — Indian state-controlled gas distributor Gail is planning to shut its 5mn t/yr Dabhol LNG terminal on the west coast from 15 May, ahead of monsoon rains. Gail will also stop importing LNG from mid-May at the terminal, a company official told Argus . This is because of the lack of a breakwater facility at the terminal, which prevents it from anchoring ships in turbulent seas. The breakwater facility was expected to be completed in January, but the cause of the delay is unknown. The terminal is likely to resume operations from the end of September, similar to its plans in 2023 , as this shutdown over the monsoon season is routine. Gail is set to receive a total of 139,635t LNG at the Dabhol terminal in May, which will arrive in two separate shipments from the US' 5.75mn t/yr Cove Point export facility. Both cargoes will be the last that the terminal will receive before it shuts in mid-May. It has received 583,326t of LNG at the terminal since the beginning of the year, lower by 4pc on the year, data from market analytics firm Kpler show. The Dabhol terminal only receives about 2.9mn t/yr of LNG, despite having a nameplate capacity of 5mn t/yr, because it is not used during the monsoon season. Gail intends to gradually increase the capacity of the Dabhol terminal to 12mn t/yr by April 2030–March 2031. By Rituparna Ghosh Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

EU adopts sustainability due diligence rules


24/04/24
News
24/04/24

EU adopts sustainability due diligence rules

Brussels, 24 April (Argus) — The European parliament has formally approved a Corporate Sustainability Due Diligence Directive (CSDDD), which will require large EU companies to make "best efforts" for climate change mitigation. The law will mean that relevant companies will have to adopt a transition plan to make their business model compatible with the 1.5°C temperature limit set by the Paris climate agreement. It will apply to EU firms with over 1,000 employees and turnover above €450mn ($481mn). It will also apply to some companies with franchising or licensing agreements in the EU. The directive requires transposition into different EU national laws. It obliges member states to ensure relevant firms adopt and put into effect a transition plan for climate change mitigation. Transition plans must aim to "ensure, through best efforts" that business models and company strategies are compatible with transition to a sustainable economy, limiting global warming to 1.5°C and achieving climate neutrality by 2050. Where "relevant", the plans should limit "exposure of the company to coal-, oil- and gas-related activities". Despite a provisional agreement, EU states initially failed to formally approve the provisional agreement reached with parliament in December, after some member states blocked the deal. Parliament's adoption — at its last session before breaking for EU elections — paves the way for entry into force later in the year. Industry has obtained clarification, in the non-legal introduction, that the directive's requirements are an "obligation of means and not of results" with "due account" being given to progress that firms make as well as the "complexity and evolving" nature of climate transitioning. Still, firms' climate transition plans need to contain "time-bound" targets for 2030 and in five-year intervals until 2050 based on "conclusive scientific" evidence and, where appropriate, absolute reduction targets for greenhouse gas (GHG) for direct scope 1 emissions as well as scope 2 and scope 3 emissions. Scope 1 refers to emissions directly stemming from an organisation's activity, while scope 2 refers to indirect emissions from purchased energy. Scope 3 refers to end-use emissions. "It is alarming to see how member states weakened the law in the final negotiations. And the law lacks an effective mechanism to force companies to reduce their climate emissions," said Paul de Clerck, campaigner at non-governmental organisation Friends of the Earth Europe, pointing to "gaping" loopholes in the adopted text. By Dafydd ab Iago Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Libya eyes progress on Eni-led oil and gas project


24/04/24
News
24/04/24

Libya eyes progress on Eni-led oil and gas project

London, 24 April (Argus) — Libya intends to move ahead with a $4bn-5bn oil and gas project proposed by Eni, months after putting the project on hold because of widespread opposition. The country's Supreme Council for Energy last month essentially cleared the way for block NC-07 to be awarded to a consortium of Italy's Eni, France's TotalEnergies, Abu Dhabi's Adnoc and Turkey's state-owned Turkish Energy after a technical review found Libyan institutions lacked the financial means to develop the project alone, according to leaked minutes of the meeting seen by Argus . More recently, Turkey's energy minister Alparslan Bayraktar said on 19 April that an agreement on NC-07 was close. "We are about to sign," he said. On 16 April, Libya's acting oil minister Khalifa Rajab Abdulsadek signalled the project was still on the cards. Eni did not comment. State-owned NOC could not be reached. Tripoli-based prime minister Abdelhamid Dbeibeh and NOC had been on the cusp of awarding NC-07 to the Eni-led consortium in January before widespread opposition forced Dbeibeh to order a review addressing concerns . Plans envisage at least 200mn ft³/d of gas and an unspecified amount of oil. The moves reflect a growing impetus by Libya's oil leadership to drive forward long-delayed projects as it seeks to boost oil production capacity from 1.2mn-1.3mn b/d to 2mn b/d and double gas output to around 3.5bn ft³/d over the next three to five years. Libya is also set to begin negotiations with TotalEnergies and ConocoPhillips in Paris next month over their demand for better terms at Waha Oil Company in return for investing in expanding production capacity, an oil industry source told Argus . This is also likely to prove controversial as many in the industry and beyond are opposed to altering contractual terms. The apparent fresh push comes just weeks after the ousting of oil minister Mohamed Oun , who had opposed awarding NC-07 to the consortium and rejected several other oil and gas deals pursued by the Tripoli-based government and NOC. Opponents of the deal have said that the consortium was set to receive a share of production that is too high and that current operator state-owned Agoco could develop the field for a fraction of the cost. The oil ministry under Oun had also suggested that NC-07 could have been put to a public tender rather than be the subject of direct negotiations. Proponents of the NC-07 deal said Libya must rapidly move ahead with projects to ensure domestic demand is met and the country can continue to export gas. The Supreme Council for Energy said Libya will face a severe gas shortage by 2026 on its current trajectory and become a gas importer unless development projects are implemented. While Libya's political divisions persist, its oil sector has enjoyed a greater level of stability over the past two years. Forced production shutdowns have been few and far between while interest from international oil companies has grown. But accusations of improper conduct in the oil industry have increased in tandem. One of the key challenges facing Libya's oil sector is project implementation. A landmark $8bn deal for Eni to develop offshore gas fields was signed in early 2023, but Argus understands that there has been little progress on implementation. By Aydin Calik Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more