UK power prices deliver at new record high
The UK day-ahead power markets cleared at a record high for delivery today amid forecasts for low wind output and limited plant and interconnector availability, along with demand beginning to rise again following the end of the holiday period.
The UK N2EX was at £219.46/MWh for base load on Monday, surpassing the previous high of £198.79/MWh in January. Hourly prices hit a high of £722.94/MWh but were below the record of just less than £1,500/MWh at the start of this year.
Wind generation was forecast at below 1.5GW throughout the day, with lows of about 800MW expected. And realised wind power generation has been even lower than forecast, at 400-600MW for most of the morning.
Availability on the 2GW IFA interconnector with France is scheduled to be reduced to 1.5GW until 10 September and then to 1GW from 10-17 September.
Combined-cycle gas turbine (CCGT) availability has been low since the start of this month, although units have steadily come back on line in recent days, with more scheduled to end shutdowns today. The 810MW Seabank 1 plant and 1.4GW South Humber Bank facility both are scheduled to return to service this afternoon.
System prices have been up to £283.65/MWh so far today, with the potential to rise again in the evening as demand picks back up. Loss-of-load probability forecasts remain above zero for the evening peak-demand hours, with de-rated margins below 3GW, National Grid ESO data show.
Early this morning, units at EdF's West Burton A coal-fired plant were accepted into the balancing mechanism with offers of up to £3,950/MWh, while Uniper's Grain 6 combined-heat-and-power plant was accepted at £4,950/MWh.
West Burton A's start-up this morning has brought coal-fired generation to above 1.5GW for the first time since March.
Demand began to rise again at the start of September as the holiday period comes to an end. Transmission system demand was forecast to average 28.2GW and peak at 33.8GW today, compared with August when demand averaged 25.7GW and peaked at 33.2GW. Low output from embedded wind also supports demand in the transmission system.
Demand in August was up by just 0.8pc on the year, down from increases of 2.2pc in July and 12.3pc in the second quarter. The holiday period will have suppressed demand, while temperatures were also below the long-term average for most of that month. And increasing supply chain disruption in many industries may have also hit demand recovery in the past two months.
Higher wind and the return of some CCGT and nuclear units could keep price spikes lower during the rest of this week. But the system is expected to remain tight — if less so than today — and high gas and emissions prices will continue to provide support.
The 1.2GW Heysham 1 nuclear plant is scheduled to return from maintenance this week, although the plant's shutdown has been extended several times since it went off line in mid-July.
Related news posts
Japan’s Renova starts Miyagi biomass power plant
Japan’s Renova starts Miyagi biomass power plant
Tokyo, 28 March (Argus) — Japanese renewable power developer Renova started commercial operations today at its 75MW Ishinomaki Hibarino biomass-fired power plant in northeast Japan's Miyagi prefecture. The power plant is designed to consume an undisclosed volume of wood pellets and palm kernel shells (PKS) to generate around 530 GWh/yr of electricity. Renova originally targeted to start up the power plant in May 2023 but postponed the start-up multiple times. Renova has been forced to delay the start-up schedules at several of its power plants. It previously targeted to begin commercial operations of the 75MW Omaezaki biomass power plant this month but postponed it to July, as the final adjustment of boiler and turbine units is taking longer than expected. It delayed the launch of the 74.8MW Tokushima Tsuda biomass power plant in September before it began commercial operations in December 2023 . Japan imported 1mn t of wood pellets during January-February, up by 14pc from the same period in 2023, according to the finance ministry. PKS purchases fell by 24pc to 466,186t. By Nanami Oki Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.
Electrification key to cut UK offshore emissions: NSTA
Electrification key to cut UK offshore emissions: NSTA
London, 27 March (Argus) — The UK offshore oil and gas industry must make "decisive emissions reduction actions now and on an ongoing basis", with asset electrification and low carbon power central to making cuts, regulator the North Sea Transition Authority (NSTA) said today. "Where the NSTA considers electrification reasonable, but it has not been done, there should be no expectation that the NSTA will approve field development plans", the regulator said in a new emissions reduction plan. The NSTA set out "four clear contributing factors to decarbonising the industry" — including asset electrification, investment and efficiency and action on flaring and venting. It will also look at "inventory as a whole", ramping up scrutiny on assets with high emissions intensity. Relevant companies must produce emissions reduction action plans for offshore assets, the NSTA said. New developments with first oil or gas after the beginning of 2030 must be either fully electrified or run on "alternative low carbon power with near equivalent emission reductions", the NSTA said. New developments with first oil or gas before 2030 should be electrification-ready at minimum. If electrification is not reasonable, other power emissions reductions must be sought, the regulator said. The offshore industry must from 1 June provide "a documented method of the split of projected flaring and venting figures into categories", and must from 1 June 2025 have a plan and budget to "deliver continuous improvements in flaring and venting", it said. New developments — including tie-backs — must be planned on the basis of zero routine flaring and venting, which every asset must reach by 2030. Industry flaring almost halved between 2018-22, the NSTA said. The regulator has flagged a particular focus on methane emissions. The NSTA may require developers to agree to cease production of assets with high emissions intensity "with reference to societal carbon values", it said. Societal carbon values are calculated by the UK government to reflect the marginal cost to society of additional CO2 emissions. It will discuss end dates for production for assets with greenhouse gas (GHG) emissions intensity 50pc over the average for the UK offshore, and which intend to produce oil or gas beyond 2030. This represents a slight watering down of the initial plan the NSTA consulted on last year. The North Sea Transition Deal, agreed in 2021, commits the UK offshore industry to reducing its production emissions of GHGs by 10pc by 2025, by 24pc by 2027 and by 50pc by 2030, from a 2018 baseline. Industry has itself committed to a 90pc reduction by 2040 and a net zero basin by 2050, the NSTA said. It "would welcome industry owning and delivering these reductions", it said, adding that its plan is focused on emissions cuts and "emissions offsetting will not be considered towards meeting the obligations." By Georgia Gratton Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.
Jera delays Hekinan NH3-coal co-firing test: Correction
Jera delays Hekinan NH3-coal co-firing test: Correction
Corrects trial period in first paragraph Osaka, 26 March (Argus) — Japan's largest power producer by capacity Jera has pushed back a trial to co-fire 20pc of fuel ammonia with coal at its Hekinan power plant to after the end of March. Jera previously said the co-firing demonstration at the 1GW Hekinan No.4 unit will start on 26 March at the earliest . But the company has decided to push this back. The trial will begin sometime after the end of this month, Jera said on 25 March. It took more time to test run equipment ahead of the demonstration, with safety the main priority, it added. It is unclear when exactly the company will start the trial to co-fire 20pc of ammonia with coal. Jera aims to demonstrate 20pc co-firing of ammonia with coal ahead of planned commercial operations in the April 2027-March 2028 fiscal year. It also hopes to achieve a 50pc mixture on a commercial basis in the first half of the 2030s. By Motoko Hasegawa Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.
Oil sands producers plan CCS network, hub
Oil sands producers plan CCS network, hub
Calgary, 25 March (Argus) — A group of Canadian oil sands companies are planning to build a massive C$16.5bn ($12.2bn) carbon capture and storage (CCS) project to decarbonize operations. Canadian Natural Resources (CNRL), on behalf of the Pathways Alliance consortium, filed plans for the project with the Alberta Energy Regulator (AER) last week to store 10mn-12mn t/yr of carbon dioxide (CO2) equivalent in the oil sands region of northeast Alberta. The Pathways Alliance also includes Cenovus, Suncor, Imperial Oil, ConocoPhillips Canada and MEG Energy, which account for about 95pc of the province's roughly 3.3mn b/d of oil sands production. Construction of the project is expected to begin as early as the fourth quarter 2025 with operations starting in 2029 or 2030. The main CO2 transportation pipeline will be 24-36-inches in diameter and stretch about 400km (249 miles). It will initially tap into 13 oil sands facilities from north of Fort McMurray to the Cold Lake region, where the CO2 will be stored underground. "When you have that concentration of emission sources, technologies like carbon capture and storage become very, very technically viable," Pathways Alliance president Kendall Dilling told the CERAWeek by S&P Global conference in Houston, Texas, earlier this month. Oil sands crude producers have been criticized for being particularly carbon intensive. The Pathways Alliance is their answer to driving operations to net zero by 2050. The CCS project and "a host of other technologies" represent Phase 1 of the Pathways Alliance's efforts and will reduce oil sands emissions by about 25pc by 2030, according to Dilling. The CCS project itself accounts for about half of this reduction. Phase 2 is planned for between 2031 to 2040 and would tie in at least another eight oil sands projects, while also ramping up alternative energy initiatives related to hydrogen, electrification and small modular nuclear reactors. By Brett Holmes Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.
Business intelligence reports
Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.
Learn more