The Florida East Coast Railway (FEC) this year became the first US rail system to run primarily on LNG instead of diesel, company executives said.
"We just completed implementing the largest rail LNG project in North America," FEC chief executive James Hertwig said this week at the Natural Gas for High Horsepower Summit in Jacksonville, Florida.
Lower oil prices since mid-2014 have slowed momentum to convert high-horsepower engines to use LNG instead of diesel, although the North American marine sector has progressed in using LNG bunker fuel to comply with stricter emissions regulations. The economics of converting to LNG are based on domestic gas prices being significantly lower than global oil prices, in terms of energy equivalent units.
FEC has unique partnerships and operating conditions that allowed it to convert to LNG, Hertwig said. FEC consumes about 20,000 USG/d of LNG, equivalent to about 1.7mn cf/d (47,000m³/d) of gas.
The 351-mile FEC system, which extends from Miami to Jacksonville, in 2014 ordered 24 new dual-fuel locomotives with the intent to operate them primarily with LNG.
FEC first used LNG in March to power one of the new locomotives, after getting approval from the Federal Railroad Administration, Hertwig said. The number of new locomotives using LNG grew until recently reaching 24. The locomotives, which were built by GE Transportation and have 4,400-horsepower engines, each cost about $2.5mn.
The company has 75 locomotives and uses some diesel, but the 24 new locomotives account for all long-haul transits, FEC chief operating officer Francis Chinnici told Argus on the sidelines of the conference. FEC is paying about 25pc less for LNG than it would for diesel because diesel is relatively expensive in Florida, he said, declining to elaborate.
A major reason FEC was able to convert to LNG is that it combined its operations with a fledgling LNG export business. When FEC decided to buy the new locomotives, it was owned by funds managed by New York-based Fortress Equity Partners.
At the time Fortress was developing plans to export small volumes of LNG to the nearby Caribbean in ISO containers, through its subsidiary American LNG Marketing. Fortress built a small liquefaction plant at the Hialeah rail yard northwest of Miami to produce LNG for FEC and exports.
The unit has liquefaction capacity of 100,000 USG/d, with FEC buying 20pc of the output, Hertwig said.
American LNG Marketing exported its first LNG from Hialeah in February 2016, and through August this year it has exported 66 ISO containers of LNG with a combined volume equivalent to about 229mn cf of gas, according to the latest US Department of Energy (DOE) data. All the exports have gone to Barbados from the ports of Miami or Ft. Lauderdale, at free-on-board prices of $10/mmBtu.
Since March the new locomotives have made 24,000 trips using LNG with a combined volume of 2.7mn USG, equivalent to about 225mn cf of gas, Hertwig said.
In July Fortress sold FEC to Grupo Mexico Transportes, the leading rail freight transportation company in Mexico.
American LNG Marketing initially trucked all the ISO containers from Hialeah to nearby ports, but FEC in recent months has been delivering on its trains about four or five ISO containers a week filled with LNG from Hialeah to nearby ports, Chinnici said. It is not clear where all the supplies are going, as American LNG Marketing is exporting about four or five cargoes a month to Barbados. The DOE does not require the public disclosure of transactions to the US commonwealth of Puerto Rico, which also uses small volumes of US LNG.
FEC has been permitted to carry up to 10 ISO containers filled with LNG per train, and hopes to increase that limit over time, Hertwig added.
American LNG Marketing is building another small liquefaction facility in Titusville, east-central Florida, also along the FEC system. The Hialeah and Titusville facilities both tie into the nearby Florida Gas Transmission system. Fortress plans to soon start exporting US LNG to Jamaica.
FEC also was able to convert to LNG because it is a relatively small system with short routes, Hertwig said. Larger systems have excess locomotives and likely will not attempt to convert until they need to replace those engines, he said.
Related news posts
Brazil narrows lower biofuel mix mandate in south
Brazil narrows lower biofuel mix mandate in south
Sao Paulo, 10 May (Argus) — Brazil's oil regulator ANP dialed back the reduced biofuels mandatory blend in Rio Grande do Sul state to four cities amid the recent flooding in the region. Low blending areas now apply only to the cities of Canoas, Esteio, Rio Grande and Santa Maria. The measure will still last for 30 days, starting on 4 May. ANP lowered the anhydrous ethanol blend on gasoline to 21pc from the current 27pc in the entire state earlier this week , while pushing the mandatory biodiesel mix for 10ppm (S10) diesel down to 2pc, from the usual 14pc. The agency also temporarily suspended the blending mandate for diesel with 500ppm of sulfur (S500). ANP said it decreased the exemption's coverage as it identified "that the supply situation in the rest of the state had stabilized." Rainfall in Rio Grande do Sul blocked railways and highways where biofuels are transported to retail hubs. Floods in the state have left at least 116 dead and 143 missing, according to the local government. By Laura Guedes Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.
Mexican power outages enter fourth day
Mexican power outages enter fourth day
Mexico City, 10 May (Argus) — Mexican power grid operator Cenace issued its fourth consecutive day of operating alerts amid the heatwave gripping the country. Net electricity demand reached 47,321MW early today, with deployed electricity capacity slightly below at 47,233 MW, according to Cenace. Since 7 May, Cenace has declared emergency operating alerts as demand exceeded generation capacity during peak evening hours, prompting the grid operator to preemptively cut electricity supply across different states to maintain grid integrity. Power outages have lasted up to several hours in Mexico City and in major industrial states as power demand has outstripped supply by up to 1,000MW. Peak demand this week hit 49,000MW, just below last year's historic peak of 53,000MW during atypical temperatures in June. "We are very concerned about the unprecedented outages detected across 21 states, a situation that affects the normal functioning of Mexican companies," national business chamber Coparmex said. Peak electricity demand typically rises in June-July but temperatures this week have risen as high as 48°C (118° F) across some states. Mexico City reported a record high of 34.3°C on 9 May and high temperatures are forecast to continue into next week, Mexico's national weather service said. The inability of Mexico's grid to respond to increased demand is because of insufficient power generation capacity, non-profit think-tank the Mexican institute for competitiveness (Imco) said this week. "Despite the energy ministry's forecast that 22,000MW of new power capacity would enter service by 2026, only 1,483MW had entered service as of 2022" since late 2018, Imco said. President Andres Manuel Lopez Obrador's administration pledged to build new generation capacity, including five gas-fired, combined-cycle plants, but recognized this week that delays had contributed to the power outages. "We have an electricity generation deficit because some of the combined-cycle plants were delayed, but we are working on it and it will soon be resolved," Lopez Obrador said on 9 May. Lopez Obrador's government has also curtailed private sector power development during his administration. Mexico needs to upgrade and expand its transmission network, industry associations say. "In order to resolve this problem, we believe that a reopening of the electricity market to the private sector is imperative," Mexico's wind energy association, Amdee, said. Mexico has 87,130MW of installed capacity, with 39.5pc from combined-cycle gas-fired power plants and 31pc in renewable power, including wind, solar, hydroelectric, geothermal and biomass, according to the latest statistics from the energy ministry. By Rebecca Conan Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.
Petrobras to expand free gas market footprint
Petrobras to expand free gas market footprint
Rio de Janeiro, 10 May (Argus) — Petrobras said today it will offer new types of natural gas contracts in Brazil's open market with more flexibile and competitive terms, but provided no details on the planned offers. The company also announced new commercial contract models for gas sales to state distributors, offering price reductions for current contracts of up to 10pc. The reduction will be connected to the distributors performance, Petrobras said, without providing more detail. The move by the state-controlled giant is significant given the 2021 gas market liberalization as aimed at increasing competition at every step of the value chain beyond just Petrobras. But progress has been slow in cutting Petrobras' market share, lowering prices, and increasing market transparency. The 2021 gas law covers the full lifecycle of natural gas, from production to transportation, processing to storage, and sales. A key provision aimed at promoting competition in the upstream, midstream, and downstream sectors, particularly transportation and distribution. Yet, three years later, there is little sign of downstream customers migrating to the free market, despite some moves such as those from Delta Geração, Acelen, Gerdau, Tradener, and others. The number of free market commercial contracts does not exceed ten, according to a lawyer specialized in the energy market. By Betina Moura Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.
Brazil reports more off-spec biodiesel March-April
Brazil reports more off-spec biodiesel March-April
Sao Paulo, 10 May (Argus) — The rate of Brazilian biodiesel falling below required blending limits nearly tripled in March and April after the mandate was increased to 14pc, according to a government analysis. Hydrocarbons regulator ANP's Fuel Quality Monitoring Program (PMQC) found 271 instances of biodiesel below the required level between 1 March — when the blending mandate was increased from 12pc to 14pc — and 30 April. In January and February the PMQC found 97 instances of blends that did not meet the 12pc level. An increase in missed blending targets is common during transitions to higher blending levels, according to the agency, mainly due to difficulties in depleting inventories of the lower-level blend. Several plants claim that a slowdown in biodiesel withdrawals in the first four months of the year also contributed to challenges in complying with the new blending level. Some retailers' loss of market share has also been cited as an aggravating factor. In March, 154 recorded instances of non-compliance covered blending levels between 12.3pc and 13.9pc, according to ANP data. In April, there were 101 occurrences within the 12.3pc and 13.9pc range. Another eight instances of non-compliance were also recorded in each of March and April. The PMQC is a monitoring program and does not have the same effect on market behavior as inspections, according to ANP. "It is used as one of the intelligence vectors for the planning of ANP's inspection actions," the agency said. Only irregularities identified in the context of inspectios can result in fines levied against fuel distributors. By Alexandre Melo Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.
Business intelligence reports
Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.
Learn more