The European majors are scaling back oil refining and focusing on cutting greenhouse gas emissions at their remaining sites, as lower oil demand resulting from Covid-19 sharpens their energy transition plans.

Shell is marketing five of its 11 operated oil refineries. By 2025, the six remaining sites are expected to form the firm's integrated energy and chemical parks in the US, the Netherlands, Germany, Canada and Singapore. But even those six plants will not be immune to significant changes. Shell will halve crude processing capacity at its 500,000 b/d Pulau Bukom refinery in Singapore, with the facility pivoting "from a crude oil, fuels-based product slate towards new, low-carbon value chains". The company is planning for output that is "resilient to the energy transition", such as biofuels, and more speciality products such as bitumen, using more feedstocks that are renewable or recyclable.

Europe has been at the forefront of refinery rationalisation for decades given the maturity of its markets, but the effects of the pandemic and the prospect of an accelerated energy transition are propelling its oil firms to act faster. Conversion to biofuel production increasingly offers an alternative to closure or divestment. And biorefining has performed better financially since the start of the pandemic than oil-processing plants, Total says. The firm has already converted its 160,000 b/d La Mede refinery in France into a 500,000 t/yr hydrotreated vegetable oil plant, and will cease conventional refining at its 93,000 b/d Grandpuits facility near Paris early next year, converting it to a biorefinery by 2024. Most of Total's downstream capital goes to its six large integrated refining and chemicals complexes in France, Belgium, South Korea, the US, Saudi Arabia and Qatar.

BP aims to "high-grade" its portfolio of eight operated refineries, as its energy transition plan envisages cutting refining throughputs from 1.7mn b/d to 1.5mn b/d in 2025 and 1.2mn b/d in 2030. It also aims to boost the use of renewable feedstocks to increase output of biodiesel and biojet, and scale up marketing of advanced fuels. The firm plans to make its 82,000 b/d Lingen refinery in Germany "contribute to net zero" by working with Danish renewables firm Orsted on a green hydrogen project that will use output from Orsted's wind farm in the North Sea to power a 50MW electrolyser at the refinery. This will produce 9,000 t/yr of hydrogen through electrolysis of water, enough to replace around 20pc of the refinery's current hydrogen consumption, BP says. "The project could be expanded to up to 500MW to replace all of Lingen's fossil fuel-based hydrogen," BP says.

Oceans apart

The US majors are assuming a more bullish long-term outlook for oil demand and are not planning any radical shifts in their downstream strategies. "Chemicals integration is probably the overlying factor we look at in terms of refiner assets that we think long-term are going to be very competitive," ExxonMobil senior vice-president Jack Williams says. Almost 80pc of ExxonMobil's 4.5mn b/d refining capacity is integrated with chemicals or lubricant manufacturing. "But medium, low-complexity refineries, in an OECD country, not integrated with chemicals — those are going to be a challenge," Williams says.

Bucking the trend, Chevron bought the 100,000 b/d Pasadena refinery in Texas last year, to integrate with its growing Permian oil production. This deal and a recent acquisition of marketing assets in Australia, "further extend our value chains in those regions", executive vice-president for downstream Mark Nelson says. While not talking about biorefineries, Chevron is not standing still either. It will use existing infrastructure to co-process biofeed as it aims to start producing biodiesel at its El Segundo, California, refinery, in the first half of 2021.


Sharelinkedin-sharetwitter-sharefacebook-shareemail-share

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

News
17/05/24

Houston refiners weather hurricane-force winds: Update

Houston refiners weather hurricane-force winds: Update

Adds Calcasieu comment, update on flaring reporting Houston, 17 May (Argus) — Over 2mn b/d of US refining capacity faced destructive winds Thursday evening as a major storm blew through Houston, Texas, but the damage reported so far has been minimal. Wind speeds of up to 78 mph were recorded in northeast Houston and the Houston Ship Channel — home to five refineries with a combined 1.5mn b/d of capacity — faced winds up to 74 mph, according to the National Weather Service . Further South in Galveston Bay, where Valero and Marathon Petroleum refineries total 818,000 b/d of capacity, max wind speeds of 51 mph were recorded. Chevron's 112,000 b/d Pasadena refinery on the Ship Channel just east of downtown Houston sustained minor damage during the storm and continues to supply customers, the company said. ExxonMobil's 564,000 b/d Baytown refinery on the Ship Channel and 369,000 b/d Beaumont, Texas, refinery further east faced no significant impact from the storm and the company continues to supply customers, a spokesperson told Argus . Neither Phillips 66's 265,000 b/d Sweeny refinery southwest of Houston nor its 264,000 b/d Lake Charles refinery 140 miles east in Louisiana were affected by the storm, a spokesperson said. There was no damage at Motiva's 626,000 b/d Port Arthur, Texas, refinery according to the company. Calcasieu's 136,000 b/d refinery in Lake Charles, Louisiana, was unaffected by the storm and operations are normal, the refiner said. Marathon Petroleum declined to comment on operations at its 593,000 b/d Galveston Bay refinery. Valero, LyondellBasell, Pemex, Total and Citgo did not immediately respond to requests for comment on operations at their refineries in the Houston area, Port Arthur and Lake Charles. A roughly eight-mile portion of the Houston Ship Channel from the Sidney Sherman Bridge to Greens Bayou closed from 9pm ET 16 May to 1am ET today when two ships brokeaway from their moorings, and officials looked in a potential fuel oil spill, according to the US Coast Guard. The portion that closed provides access to Valero's 215,000 b/d Houston refinery, LyondellBasell's 264,000 b/d Houston refinery and Chevron's Pasadena refinery. Emissions filings with the Texas Commission on Environmental Quality (TCEQ) are yet to indicate the extent of any flaring and disruption to operations in the Houston area Thursday evening, but will likely be reported later Friday and over the weekend. Gulf coast refiners ran their plants at average utilization rates of 93pc in the week ended 10 May, according to the Energy Information Administration (EIA), up by two percentage points from the prior week as the industry heads into the late-May Memorial Day weekend and beginning of peak summer driving season. The next EIA data release on 22 May will likely reveal any dip in Gulf coast refinery throughputs resulting from the storm. By Nathan Risser Houston area refineries Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Find out more
News

Houston area refiners weather hurricane-force winds


17/05/24
News
17/05/24

Houston area refiners weather hurricane-force winds

Houston, 17 May (Argus) — Over 2mn b/d of US refining capacity faced destructive winds Thursday evening as a major storm blew through Houston, Texas, but the damage reported so far has been minimal. Wind speeds of up to 78 Mph were recorded in northeast Houston and the Houston Ship Channel — home to five refineries with a combined 1.5mn b/d of capacity — faced winds up to 74 Mph, according to the National Weather Service . Further South in Galveston Bay, where Valero and Marathon Petroleum refineries total 818,000 b/d of capacity, max wind speeds of 51 Mph were recorded. Chevron's 112,000 b/d Pasadena refinery on the Ship Channel just east of downtown Houston sustained minor damage during the storm and continues to supply customers, the company said. ExxonMobil's 564,000 b/d Baytown refinery on the Ship Channel and 369,000 b/d Beaumont, Texas, refinery further east faced no significant impact from the storm and the company continues to supply customers, a spokesperson told Argus . Neither Phillips 66's 265,000 b/d Sweeny refinery southwest of Houston nor its 264,000 b/d Lake Charles refinery 140 miles east in Louisiana were affected by the storm, a spokesperson said. There was no damage at Motiva's 626,000 b/d Port Arthur, Texas, refinery according to the company. Marathon Petroleum declined to comment on operations at its 593,000 b/d Galveston Bay refinery. Valero, LyondellBasell, Pemex, Total, Calcasieu and Citgo did not immediately respond to requests for comment on operations at their refineries in the Houston area, Port Arthur and Lake Charles. A roughly eight-mile portion of the Houston Ship Channel from the Sidney Sherman Bridge to Greens Bayou closed from 9pm ET 16 May to 1am ET today when two ships brokeaway from their moorings, and officials looked in a potential fuel oil spill, according to the US Coast Guard. The portion that closed provides access to Valero's 215,000 b/d Houston refinery, LyondellBasell's 264,000 b/d Houston refinery and Chevron's Pasadena refinery. By Nathan Risser Houston area refineries Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Texas barge collision shuts GIWW section: Correction


16/05/24
News
16/05/24

Texas barge collision shuts GIWW section: Correction

Corrects volume of oil carried by barge in fourth paragraph. Houston, 16 May (Argus) — Authorities closed a six-mile section of the Gulf Intracoastal Waterway (GIWW) near Galveston, Texas, because of an oil spill caused by a barge collision with the Pelican Island causeway bridge. The section between mile markers 351.5 and 357.5 along the waterway closed, according to the US Coast Guard. A barge broke away from the Philip George tugboat and hit the bridge between Pelican Island and Galveston around 11am ET today. Concrete from the bridge fell onto the barge and triggered an oil leak. The barge can hold up to 30,000 bl oil, but it was unknown how full the barge was before the crash, Galveston County county judge Mark Henry said. It was unclear when the waterway would reopen. An environmental cleanup crew was on the scene along with the US Coast Guard and Texas Department of Transportation to assess the damage. Multiple state agencies have debated the replacement of the 64-year-old bridge for several years, Henry said. The rail line alongside the bridge collapsed. Marine traffic does not pass under the bridge. By Meghan Yoyotte Intracoastal Waterway at Galveston Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Dangote seeks 2mn bl/month WTI crude for 12 months


16/05/24
News
16/05/24

Dangote seeks 2mn bl/month WTI crude for 12 months

London, 16 May (Argus) — Nigeria's 650,000 b/d capacity Dangote refinery has issued a tender for the supply of 2mn bl of US WTI crude each month, for 12 months starting in July, according to a tender document seen by Argus . Dangote will accept offers on a delivered cif basis to Lekki, Nigeria, and on a fob basis from Houston and Corpus Christi, Tx. It was not stated whether the fob offers would be against WTI or Brent. The tender closes on 21 May. Dangote came online at the end of 2023 and its throughout capacity is planned to reach around 350,000 b/d a its first phase of operations. The refinery received its first crude cargo on 6 December and since then deliveries have averaged 179,000 b/d, according to data from Vortexa. Light sweet WTI accounted for 42,000 b/d, or 23pc of the total. By Lina Bulyk and Kuganiga Kuganeswaran Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Eni cuts scope 1, 2 upstream emissions by 40pc in 2023


15/05/24
News
15/05/24

Eni cuts scope 1, 2 upstream emissions by 40pc in 2023

Edinburgh, 15 May (Argus) — Italy's Eni said today that it has cut its net scope 1 and 2 emissions in the upstream sector by 40pc in 2023, compared with a 2018 baseline. Eni has also cut scope 1 and 2 emissions by 30pc for the whole business during the same period, it said. Scope 1 refers to emissions directly stemming from an organisation's activity, while scope 2 refers to indirect emissions from purchased energy. The firm has a target to be net zero upstream for scope 1 and 2 emissions by 2030, and by 2035 for the whole company. It also has a goal of being net zero across all its businesses, including scope 3 emissions that are generated by use of its products, by 2050. Eni said it agrees with the UN Cop 28 deal struck by almost 200 countries in Dubai last year, and for "the need for the energy transition to take place in a fair, orderly, just and pragmatic manner". But it added that this includes expanding its gas portfolio, as well as investing to reduce emissions from oil and gas output. It said investing in gas is "a bridging vector in the energy transition pathway", citing the acquisition of Neptune Energy and the start of LNG production in Congo (Brazzaville). Eni completed the purchase of assets of gas-focused UK-based independent Neptune Energy in January. The Cop 28 agreement acknowledges the need to transition away from fossil fuels in energy systems "so as to achieve net zero by 2050 in keeping with the science", but it also "recognises that transitional fuels can play a role in facilitating the energy transition while ensuring energy security". Some climate non-governmental organisations and countries particularly vulnerable to the effect of climate change have warned that this could create loopholes benefiting the development of fossil fuel resources, including natural gas. Eni in March said that it has cut its spending plans by around 20pc through to 2027 as it looks to focus on the quality of upstream projects and streamlined development to grow its oil and gas production by an annual 3-4pc. "Natural gas will continue expanding its share of production," Eni chief executive Claudio Descalzi said. The firm is also looking to raise its renewable energy capacity to 4GW this year from 3GW at the end of last year, and then double this to more than 8GW by 2027. By Caroline Varin Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.