Generic Hero BannerGeneric Hero Banner
Latest market news

US coal demand to fall despite retirement shift

  • Market: Coal, Electricity
  • 02/01/24

Coal demand in the US may continue its downward trend in 2024 even though fewer power plant units are scheduled to close and some retirements have been delayed.

Coal-fired power plant unit retirements in 2024 are projected to number between six and eight, according to US Energy Information Administration (EIA) estimates and company announcements recorded by Argus. That is down from 22 units permanently closed in 2023.

The current expectation for 2024 coal plant retirements also is slightly lower than what the EIA was projecting at the start of 2023. In addition, four fewer coal units closed in 2023 than had been expected at the start of the year. Some power plant retirements have been delayed or have been flagged by grid operators as temporarily necessary for grid reliability.

But market fundamentals, including more competitive natural gas prices and expanding renewable generation capacity, are expected to continue to be less supportive of coal-fired generation and coal demand this year.

"There's a lot of questions that go into these coal unit [retirement] delays, including how long grids need these units to continue operating during peak demand," said Ian Lange, associate professor at Colorado School of Mines. "It could just be for a few hours or a few days in the winter... but the short period of operation makes me think it will probably not significantly impact coal demand."

The latest projections from the EIA have coal consumption by US electric power plants falling by 10pc this year to 346.5mn short tons (314.3mn metric tonnes).

The biggest shift in coal retirements in 2023 appears to have been in the PJM Interconnection. The grid operator initially had 11 coal units retiring in the first half of 2023, taking a combined capacity of 5,681.2MW offline. But two of those unit retirements were withdrawn after Omnis Fuel Technologies in August reopened the 1,200MW Pleasants power station in West Virginia with plans to eventually add technology to extract hydrogen from coal and run the plant on hydrogen.

For 2024, PJM so far has only one plant scheduled to close, AES' 180MW Warrior Run plant, according to the generation deactivations page on the grid operator's website.

Two coal units in the Midcontinent Independent System Operator (MISO) — WEC Energy's South Oak Creek units 5 and 6 — are expected to close in 2024. WEC previously was expected to also retire South Oak Creek units 7 and 8 in 2024, but announced in June 2022 that it was going to extend operations of those units until "late 2025."

Elsewhere, Duke Energy delayed retirement plans of the remaining two coal units of the GG Allen plant in North Carolina to "by 2025" instead of the end of 2023. And the Federal Energy Regulatory Commission recently approved plans for MISO to extend its system support reliability agreement with Ameren's Rush Island plant in Missouri until at least 1 September 2024. MISO also has asked for permission to extend the reliability agreement it has with Manitowoc Public Utilities' Lakefront 9 plant in Wisconsin beyond its 31 January 2024 expiration date.

PJM has also identified some potential reliability issues that would affect zones that stretch into six states in the grid if Talen Energy were to deactivate the Brandon Shores power plant in 2025, shutting down 1,281.6MW of generating capacity.

Many utilities are likely to use units they have extended retirement dates for as reserve capacity for peak demand seasons instead of using them as baseload generation, Lange said. Some generators already have been operating older coal units at lower rates both because of market conditions as well as environmental regulations. They also are girding for potential tighter regulations in the future.

Even if utilities use the units more frequently, they may have little need to make significant coal purchases. Inventories at most power plants remained above normal going into 2024, following lower than expected coal-fired generation and consumption in 2023.

Coal-fired generation in PJM and MISO has lagged behind year-earlier levels from January-November, while natural gas generation rose for nearly all of 2023 because of lower prices and increased capacity. Average renewable generation fell slightly from year earlier levels even though generators installed more wind, solar and other technology.

In addition, some utility buyers have asked producers to stall shipments that were scheduled for 2023. That, along with other market fundamentals, will likely offset any increase in coal-fired generation that could have been expected from the slower capacity cuts.

PJM coal shipmentsst
StateJan-Oct 2022Jan-Oct 2023±
Delaware83,97171,789-15%
Illinois23,184,01419,119,430-18%
Indiana20,035,94918,421,354-8%
Kentucky22,987,04123,078,7580%
Maryland1,583,187926,993-41%
Michigan15,404,73711,260,903-27%
New Jersey183,955 - -100%
North Carolina4,863,0894,614,632-5%
Ohio14,242,14312,672,343-11%
Pennsylvania 11,080,6415,115,860-54%
Tennessee4,244,6602,835,083-33%
Virginia1,584,570916,898-42%
West Virginia 18,746,44117,052,955-9%
TOTAL138,224,398116,086,998-16%
MISO coal shipmentsst
StateJan-Oct 2022Jan-Oct 2023±
Arkansas10,725,338317,518-97%
Illinois23,184,01419,119,430-18%
Indiana20,035,94918,421,354-8%
Iowa10,735,30210,802,9111%
Kentucky22,987,04123,078,7580%
Louisiana4,545,4624,377,569-4%
Michigan15,404,73711,260,903-27%
Minnesota8,775,7466,959,659-21%
Mississippi4,043,1263,388,542-16%
Missouri24,511,35423,026,633-6%
Montana5,826,0465,486,268-6%
North Dakota17,981,34016,489,642-8%
South Dakota1,254,330856,134-32%
Texas48,562,24745,502,403-6%
Wisconsin10,377,64410,605,5982%
TOTAL195,040,324180,256,374-8%

Sharelinkedin-sharetwitter-sharefacebook-shareemail-share

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

News
16/05/25

US House panel votes down Republican megabill

US House panel votes down Republican megabill

Washington, 16 May (Argus) — A key committee in the US House of Representatives voted today to reject a massive budget bill backed by President Donald Trump, as far-right conservatives demanded deeper cuts to clean energy tax credits and social spending programs. The House Budget Committee failed to pass the budget reconciliation bill in a 16-21 vote, with four House Freedom Caucus members — Ralph Norman (R-South Carolina), Chip Roy (R-Texas), Josh Brecheen (R-Oklahoma) and Andrew Clyde (R-Georgia) — voting no alongside Democrats. A fifth Republican voted no for procedural reasons. The failed vote will force Republicans to consider major changes to the bill before it comes up for a vote on the House floor as early as next week. Republican holdouts say the bill would fall short of their party's promises to cut the deficit, particularly because it would front-load increased spending and back-load cuts. The bill is set to add $3.3 trillion to the deficit, or $5.2 trillion if temporary provisions were permanent, according to estimates from the nonpartisan Committee for a Responsible Federal Budget. Some critics of the bill said the proposed cut of $560bn in clean energy tax credits is not enough, because the bill would retain some tax credits for new wind and solar projects. "A lot of these credits have been in existence for 30 or 40 years, and you talk about giveaways, we want to help those who really need help," Norman said ahead of his no vote. "That's the heart of this. Sadly, I'm a no until we get this ironed out." Negotiations will fall to House speaker Mike Johnson (R-Louisiana), who can only lose three votes when the bill comes up for a vote by the full House. But stripping away more of the energy tax credits enacted in the Inflation Reduction Act could end up costing Johnson votes among moderates. More than a dozen Republicans on 14 May asked to pare back newly proposed restrictions on the remaining clean energy tax credits. Ahead of the failed vote, Trump had pushed Republicans to support what he calls the "Big Beautiful Bill". In a social media post, he said "Republicans MUST UNITE" in support of the bill and said the party did not need "GRANDSTANDERS". The failed vote has parallels to the struggles that Democrats had in 2021 before the implosion of their push to pass their sprawling "Build Back Better" bill, which was later revived as the Inflation Reduction Act. Republicans say they will work over the weekend on a compromise. The House Budget Committee has scheduled another hearing at 10pm on 18 May to attempt to vote again on the budget package, but any changes to the measure would occur later, through an amendment released before the bill comes up for a vote on the House floor. By Chris Knight Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

Find out more
News

UK offshore wind sector needs stability: Industry


16/05/25
News
16/05/25

UK offshore wind sector needs stability: Industry

London, 16 May (Argus) — The UK's offshore wind sector requires urgent government action to restore investor confidence and meet 2030 decarbonisation goals, industry leaders warned at the All-Energy conference in Glasgow on 14 May. Speaking at the panel Offshore Wind 2024: A Year in Turmoil, experts called for policy stability, streamlined consenting and stronger supply chains to unlock the sector's potential. Chair of industry body Global Wind Energy Council (GWEC) Jonathan Cole criticised the government's proposed locational marginal pricing reforms, arguing they introduce complexity and deter long-term investment. "We're not building coffee shops and bookstores, we're building infrastructure that will sit in one location for generations," he said. Cole warned that a 1pc rise in capital costs could erase £20bn in projected benefits, urging policymakers to prioritise stability over "speculative" market changes. ScottishPower Renewables' chief executive, Charlie Jordan, echoed the need for clarity, highlighting the £75bn investment in UK grid upgrades, particularly in Scotland, as critical for jobs and future-proofing the energy system. He said the ongoing review of electricity market arrangements (Rema) risks undermining grid investment and called for practical measures like general taxation to protect consumers from rising transmission costs. Both panellists stressed the need to accelerate consenting processes to maintain project timelines. They also emphasised strengthening the UK's offshore wind supply chain to compete with nations like South Korea and France. "Without swift action on ports, manufacturing and grid connections, we'll lose opportunities," Jordan said, pointing to Scotland's ScotWind seabed leasing programme and Celtic Sea offshore wind projects. Scotland has 3GW of offshore wind capacity across seven wind farms, including the 1.1GW Seagreen and 30MW Hywind Scotland. Projects under construction, such as the 450MW Neart na Gaoithe and 882MW Moray West, bring the nation's pipeline to 10.2GW expected by 2030, aligning with the Scottish government's 11GW target. The ScotWind seabed leasing round saw 25GW of leasing options agreements awarded in January 2022, with projects like the 2.1GW Berwick Bank, 1.1GW Inch Cape and 560MW Green Volt in planning. But recent setbacks have raised concerns about deliverability. The cancellation of Danish utility Orsted's 2.4GW Hornsea 4 project in May, despite a 15-year contracts for difference (CfD) at £83/MWh, underscores the sector's challenges. Orsted cited rising costs and "execution risks" from installing 180 turbines, highlighting economic unviability under current conditions. Transparency in energy pricing was deemed essential for public support. Jordan said prohibitive costs, driven by taxes and seabed leasing fees, make UK industrial users 70pc less competitive than their European counterparts. Cole added that clear communication is vital as discussions about market reforms and potential EU alignment intensify. With the upcoming seventh round of the CfD scheme and ongoing government consultations, the panel urged decisive action to stabilise the sector. "This is the time for long-term vision, not academic experiments," Cole said. By Timothy Santonastaso Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

News

Austrian PV additions fall 100MW on year in 1Q


15/05/25
News
15/05/25

Austrian PV additions fall 100MW on year in 1Q

London, 15 May (Argus) — Austrian solar photovoltaic (PV) capacity additions fell by around 100MW on the year in the first quarter of 2025, solar association PV Austria told Argus , a decrease of around 20pc. Newly installed PV capacity in January-March stood at 399MW, PV Austria said, compared with 497MW added in the first quarter of last year, according to data from grid regulator E-control. But late reports from Austria's distribution system operators may still cause a slight uptick in capacity addition numbers for the last quarter, PV Austria said. The association largely attributed the fall in solar additions to uncertainty around government policies, which "compromised" planning security and "jeopardised" investments into renewable energy, it told Argus . And it cited the "abrupt" end of the VAT exemption for small PV systems as well as the extension and tightening of the energy crisis contribution as further reasons for the decline. PV Austria called on the government to pass the electricity industry act (ElWG) and the renewable energy expansion acceleration act (EABG) as soon as possible. The government in February pledged to pass the ElWG in the summer of this year. Austria had just under 8.3GW of solar capacity installed as of the start of January, the latest data from transmission system operator APG show. Solar output more than doubled on the year in 2024 and APG has several times highlighted the challenges posed by increased PV capacity for demand forecasting and grid stability during times of solar peaks, when excess power must either be transported abroad or to storage power plants and can also lead to curtailments at wind and hydropower units. By John Horstmann Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

News

UK establishes public energy company


15/05/25
News
15/05/25

UK establishes public energy company

London, 15 May (Argus) — The UK parliament has passed a bill establishing a publicly owned energy company, Great British Energy (GBE), to support the nation's renewable energy ambitions. The company, funded with £8.3bn ($11.02bn) over the current parliamentary term, aims to accelerate renewable energy projects, enhance energy security, and support job creation, the department for energy security and net zero (Desnz) announced on Thursday. GBE will invest in clean energy initiatives, including technologies such as floating offshore wind, and collaborate with private companies to expand renewable energy capacity. The government states the company will help stabilise energy costs by reducing reliance on fossil fuels. The bill includes £200mn for renewable energy projects, such as rooftop solar for schools, hospitals, and communities. It has also committed £300mn to develop the UK's offshore wind supply chain, supporting manufacturing of components such as cables and platforms. The legislation received approval from the devolved governments of Scotland, Wales, and Northern Ireland, enabling GBE to operate across the UK. Desnz secretary of state Ed Miliband is expected to outline GBE's strategic priorities "soon", specifying technology focus areas and investment criteria. The government sees GBE as a key part of its plan to transition to clean energy and stimulate economic growth through a "modern industrial strategy", it said. Industry body Energy UK welcomed the bill's passage. "[GBE] can play a vital role in making the government's clean energy ambitions a reality by attracting extra private sector investment," chief executive Dhara Vyas said. By Timothy Santonastaso Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

News

Grids key to boosting SE Asia’s renewable power: Ember


15/05/25
News
15/05/25

Grids key to boosting SE Asia’s renewable power: Ember

Singapore, 15 May (Argus) — Up to 30GW of solar and wind power could be unlocked along planned grid routes in southeast Asia, which would help meet growing power demand in the region, according to a report released today by think-tank Ember. The Asean group of nations is still heavily reliant on fossil fuels, but solar and wind power are expected to constitute 23pc of the energy mix by 2030, up from 4pc currently, according to Ember. Asean as a region targets a 51GW increase in solar, and a 109GW increase in wind, hydro, geothermal and bioenergy combined by 2040. Electricity demand is rising in the region, because of economic growth as well as greater demand from data centres and transport electrification. Expanding and modernising the region's grid infrastructure would help to allow for the development of more clean energy, improve system flexibility and support regional power sharing. Up to 24GW of potential solar power and 5.6GW of wind power are situated in Indonesia's Riau islands and Sumatra, Malaysia's Sarawak, Cambodia and Brunei, where there are existing and planned grid projects. But the electricity generated from these projects needs transmission lines to be transported to demand centres. Indonesia, Vietnam, the Philippines and Thailand collectively plan to add 45,078km of transmission lines between 2023-30. But this is slightly less than half of IEA's projections that indicate southeast Asia needs to expand transmission lines by 100,000km between 2021-30 to meet its clean energy targets. Regional variance There is significant disparity between Asean countries in their clean energy potential, with some having abundant wind and solar capacity, and others having hydropower and geothermal resources. These resources also tend to be subject to seasonal variations. Regional grid interconnection is hence "key to using these resources in combination, boosting renewables use and economic growth" states the report. The Asean Power Grid has seen some progress through the Lao PDR-Thailand-Malaysia-Singapore (LTMS-PIP) project and the Brunei Darussalam, Indonesia, Malaysia and the Philippines Power Integration Project (BIMP-PIP). But grid development plans still vary significantly across the region. Only Cambodia, Malaysia and Singapore have signed the UN's Global Energy Storage and Grids Pledge, which aims to deploy 1,500GW of energy storage and 25mn km of grid infrastructure globally by 2030. Additionally, investment required to expand electricity grids, including regional interconnections, could reach $22bn/yr by 2035, the IEA said. Asean's clean energy future hence depends on cross-border data sharing, addressing infrastructure requirements, momentum in policymaking for regional co-operation, and aligning investments with future energy demand, says Ember. By Prethika Nair Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

Generic Hero Banner

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more