Omani renewable H2 project to start four years late

  • Market: Fertilizers, Hydrogen
  • 01/08/24

The targeted start date for the planned Hyport Duqm renewable hydrogen and ammonia project in Oman has been pushed back by at least four years and an offtake agreement with German utility Uniper is no longer in place.

The project, in which BP has agreed to acquire a 49pc stake, is now scheduled to start commercial operations in 2030-31, Belgian developer Deme said on 31 July. It was initially due to start operations in 2026, based on statements from Uniper in 2021 when the utility announced it had signed a cooperation agreement with the project developers. Under the preliminary deal, Uniper would have taken the full 330,000 t/yr of renewable ammonia output planned for the facility's first phase.

But this agreement could not be upheld after Uniper was nationalised in 2022, Deme told Argus today. The German government nationalised Uniper to stabilise the firm after it made major losses replacing missing Russian gas deliveries.

Deme did not comment on the reasons for the delay to the plant's start-up, but timelines have slipped for many other renewable hydrogen and ammonia projects because of difficulties securing firm offtakers and financing, persistent regulatory uncertainties and increased cost estimates.

Deme and Omani company OQ will each hold a 25.5pc stake in the Hyport Duqm project following BP's entry, which is expected to be finalised this quarter, the Belgian firm said. BP will become the project's operator.

The project is at the pre-front-end engineering design (pre-FEED) stage and is slated to entail around 500MW of electrolysis capacity, powered by 1.3GW of wind and solar capacity in its first phase, Deme said. The combined wind and solar power could be lifted to 2.7GW in a second phase, the firm said, without disclosing the electrolysis capacity for the expansion.

Output from the plant in the Duqm special economic zone is to be exported to Europe and northeast Asia from a nearby port, Deme said.

Deme is also considering projects in other countries including Egypt where it plans to set up a 320,000 t/yr renewable ammonia plant. Tunisia's government said earlier this week that it struck a preliminary deal with Deme on the development of a renewable hydrogen project, but the company said today that it is too early to disclose further details.


Sharelinkedin-sharetwitter-sharefacebook-shareemail-share

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

News
17/11/25

Rio Tinto supports Australian low-CO2 iron plant

Rio Tinto supports Australian low-CO2 iron plant

Sydney, 17 November (Argus) — UK-Australian iron ore producer Rio Tinto will invest A$35mn ($23mn) into Australian technology developer Calix to help it build a 30,000 t/yr hydrogen-based direct reduction iron and hot briquetted iron demonstration plant in Kwinana. Rio Tinto's investment package includes A$8mn in cash, 10,000t of Pilbara iron ore, and other in-kind support, Calix said today. Rio Tinto will be able to market and use Calix's developing technology, on a non-exclusive basis, under the deal, the iron ore producer said. Rio Tinto's Pilbara ore will support early work at the demonstration plant. But Calix will use a range of ore grades and types at the site, including lower-grade fines. Lower-emissions iron projects generally use higher-grade magnetite ore. Calix's Zero Emissions Steel Technology (Zesty) process uses 54kg of hydrogen to produce 1t of iron, the company said on 23 July. Australian producer Fortescue expects to use 800kg of hydrogen to make 1t of iron. Calix plans to open its Zesty demonstration plant in 2028. The Australian Renewable Energy Agency awarded Calix a A$45mn grant to support the project in July. Calix will build the plant on the proposed site of Rio Tinto's BioIron pilot plant. Rio Tinto has planned to produce 1 t/hr of iron using biomass and iron ore at the site. But the company is still working on BioIron's final design, it said today. Rio Tinto has not announced a timeline for its BioIron project. Rio Tinto is also working on other low-emission iron projects. It is part of the NeoSmelt consortium — made up of five major metals and energy producers — that is developing a 30,000-40,000 t/yr direct reduction iron plant. NeoSmelt may further process iron produced by Calix, Rio Tinto said. By Avinash Govind Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

Find out more
News

US lifts tariffs on most fertilizer imports: Update


15/11/25
News
15/11/25

US lifts tariffs on most fertilizer imports: Update

Adds detail on the lack of full exemption status for ammonia and recent Nola urea futures trade Houston, 14 November (Argus) — US president Donald Trump said today key nitrogen and phosphate fertilizers, among other agricultural products , are exempt from US import tariffs that were implemented in April, but ammonia's status under the tariff modification remains unclear. After just seven months in place, tariffs that have curbed imports to US shores and elevated the price of fertilizers have been lifted, according to a modification to Executive Order 14257 issued by the White House today. Fertilizers exempted from the tariffs include urea, ammonium nitrate, UAN, ammonium sulfate, TSP, DAP and MAP. Ammonia could qualify for tariff exemptions, but eligibility will be determined on a case-by-case basis by the secretary of commerce and the US Trade Representative, depending on the terms of existing or ongoing trade negotiations with each country. Potassium fertilizers like MOP were already exempt from import tariffs. The modification to the tariffs went into effect for goods imported starting 13 November. January Nola urea futures traded down roughly $30/st late Friday afternoon to $360/st fob following the announcement, but otherwise activity was largely subdued given the modifications' proximity to the weekend. Fertilizer values will likely begin to price-in the change in trade policy starting Monday. Most fertilizer exporting countries, except for Russia , faced tariff rates of 10-15pc, with some suppliers even facing up to 30pc tariffs, resulting in major shifts in fertilizer trade. Exporters have avoided the US, favoring alternative destinations for their supply. But trade flows could normalize now that fertilizers are now tariff-free. The tariffs have contributed to eroding fertilizer affordability relative to crop prices in the US this year, driving fertilizer prices to multi-year highs and significantly curbing demand for nutrients across the country. Lower cost imports could help unwind farmer reluctance to enter the market leading up to the spring season in 2026. The announcement should provide importers and distributors with some certainty headed into next spring after months of being kept on edge by shifting US trade policy. By Calder Jett and Sneha Kumar Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

News

US lifts tariffs on fertilizer imports


14/11/25
News
14/11/25

US lifts tariffs on fertilizer imports

Houston, 14 November (Argus) — US president Donald Trump said today key nitrogen and phosphate fertilizers, among other agricultural products, are exempt from US import tariffs that were implemented in April. After just seven months in place, tariffs that have curbed imports to US shores and elevated the price of key fertilizers have been lifted, according to a modification to Executive Order 14257 issued by the White House today. Fertilizers exempted from the tariffs include ammonia, urea, ammonium nitrate, UAN, ammonium sulfate, DAP and MAP. Potassium fertilizers like MOP were already exempt from import tariffs. The modification to the tariffs will go into effect for goods imported starting 13 November. Most fertilizer exporting countries, except for Russia , faced tariff rates of 10-15pc, with some suppliers even facing up to 30pc tariffs, resulting in major shifts in fertilizer trade. Exporters have avoided the US, favoring alternative destinations for their supply. But trade flows could normalize now that fertilizers are now tariff-free. The tariffs have contributed to eroding fertilizer affordability relative to crop prices in the US this year, driving fertilizer prices to multi-year highs and significantly curbing demand for nutrients across the country. Lower cost imports could help unwind farmer reluctance to enter the market leading up to the spring season in 2026. By Calder Jett and Sneha Kumar Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

News

India’s Fact opens phosrock offers in tender


14/11/25
News
14/11/25

India’s Fact opens phosrock offers in tender

London, 14 November (Argus) — Indian fertilizer producer and importer Fact received offers for Moroccan and Togolese phosphate rock at firmer prices in its latest tender, which closed on 11 November. The tender had sought offers for 44,000t of minimum 31.75pc P2O5 phosphate rock for shipment to Cochin on India's southwest coast on 15-30 December. Indagro submitted the lowest offer for Moroccan phosphate rock at 18,121 rupees/t cfr ($204/t cfr), or Rs15,622/t fob ($176/t fob). Sun International offered Togolese rock at Rs19,372/t cfr ($218/t cfr), or Rs16,693/t fob ($188/t fob). But the Togolese phosphate rock offered by Sun International contains 36pc P2O5, while Argus understands that the Moroccan rock offered by Indagro contains 31.75pc P2O5 — matching Fact's minimum requirement. This means that Sun International's offer is equivalent to around $606/t P2O5 cfr, which is lower than the equivalent for Indagro's offer of around $643/t P2O5 cfr. Indagro's offer for 31.75pc P2O5 rock at $204/t cfr is slightly above the midpoint of prices for 70BPL (32pc P2O5) rock delivered to Indian ports in the third quarter at $202/t cfr, as assessed by Argus . Sun International's offer for 36pc P2O5 rock at $218/t cfr is also up from prices for Togolese 77-79BPL (35.2-36.2pc P2O5) product delivered in the third quarter at $209-212/t cfr west coast India. By Tom Hampson Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

News

Plug Power warns pausing DOE activities risks loan


13/11/25
News
13/11/25

Plug Power warns pausing DOE activities risks loan

Houston, 13 November (Argus) — US hydrogen and electrolyzer manufacturer Plug Power warned investors that suspending activities related to its Department of Energy (DOE) loan guarantee carries a risk of losing access permanently to the low-cost federal financing. "Our decision to temporarily suspend activities related to the DOE loan could adversely affect our access to low-cast capital, delay project execution, and expose us to potential termination or modification of the DOE loan guarantee," the company said in a 10-Q form filed earlier this month with the Securities and Exchange Commission. Plug Power announced this week that it was suspending activities related to the $1.7bn loan guarantee while it considers reallocating capital away from previously announced plans. The loan facility, granted in the final days of the outgoing administration of President Joe Biden, was supposed to have financed the development of up to six green hydrogen plants in the US. However, all of those activities were put on hold after the administration of President Donald Trump paused clean energy commitments made under Biden pending further review. After months of engaging with Trump's DOE , Plug Power suspended activities related to the loan in November, including "projects previously contemplated in New York and Texas," according to the filing. Suspending activities on the projects may result in the DOE terminating the loan guarantee commitment if the agency determines Plug Power is not meeting required conditions or projected milestones, the company said. Plug Power has spent $250mn so far on the $800mn Texas project and expected to cover $400mn with the DOE loan. The company had been seeking an equity partner to make up the remainder of the cost. Since suspending the activities, Plug Power has announced a spate of deals to raise liquidity and pivot away from federal support, including joint development projects with renewable fuel producers, international electrolyzer deals, and signing away electricity rights to raise cash. Plug Power did not respond to a request from Argus for comment. By Jasmina Kelemen Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

Generic Hero Banner

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more