Australian producer BHP has outlined a pipeline of global copper projects that could increase its total production capacity by 1.8mn-2mn t over the next decade, supporting expected growth in copper demand.
The company plans to make final investment decisions on these projects between 2026-2032 (see table), with start ups scheduled from 2028 onward, according to data from BHP's half year report released on 17 February.
BHP has kept its copper production guidance for the July 2025-June 2026 financial year unchanged from late January at 1.9mn-2mn t.
The firm's largest planned copper projects are the Copper South Australia Phase 1 and Phase 2 growth projects, scheduled to come on line between 2029 and 2038. Together, the projects are expected to lift BHP's copper output capacity by 790,000-910,000t over that period.
BHP invested $555mn into its South Australian copper operations to raise production in October 2025. It produced 22,200t of copper concentrate, down 14pc on the year, and 52,900t of copper cathode, up 17pc on the year, in October-December 2025.
Producers need to commit 10mn t/yr of additional capacity by 2035 to address copper supply shortfalls, BHP said. The company expects global copper demand to grow from around 34mn t/yr in 2026 to over 50mn t/yr by 2050 because of economic growth, renewable transition projects, and digital infrastructure projects, it added.
BHP's forecast aligns with that of other major producers. Australian producer South32 — formerly a BHP subsidiary — projected an 8mn t/yr copper supply shortfall by 2035 on 12 February. Chilean copper commission Cochilco and Russian producer Nornickel also expect copper deficits.
| BHP Project Pipeline | |||
| Project | FID Date | Start Date | Production |
| Escondida (new concentrator) | 2027-28 | 2031-32 | 220-260 |
| Vicuña - Stage 1 | 2026 | 2030 | 200.0 |
| Spence chalcopyrite leaching | 2026 | 2028 | 40-60 |
| Copper SA Phase 1 - smelter and refinery | 2027 | 2032 | 380-500 |
| Copper SA Phase 1 - mines and concentrators | 2027 and 2029 | 2029 | 220.0 |
| Cerro Colorado restart | 2028-31 | 2031-34 | 85-100 |
| Vicuña - all stages | 2027-2030s | 2030-mid 2030s | 500.0 |
| Copper SA Phase 2 | 2032 | 2038 | 190.0 |
| Production is approximate | |||
| Source: BHP | |||