Generic Hero BannerGeneric Hero Banner
Latest market news

Data centers may raise Alberta gas demand by 31pc

  • Market: Electricity, Natural gas
  • 24/07/26

An influx of data center proposals in the Canadian province of Alberta may significantly raise demand for natural gas produced from the hydrocarbons-rich region, as provincial policy requires that data centers be powered by gas-fired electricity, according to an Argus analysis.

Under current rules, starting operations on all of the proposed data center projects which have requested allocations from the province's grid regulator would increase demand for Alberta natural gas by around 97mn m³/d (3.4 Bcf/d). That would mark a 31pc increase on current total demand of around 316mn m³/d, according to the Alberta Energy Regulator (AER), and would be 29pc higher than AER's toal demand projection for 2031.

The analysis considers demand to 2031, the year when the largest of those data centers already approved — Meta's 910MW data center in Sturgeon County — is expected to begin generating gas-fired power from its own plant.

Finally, it assumes total data center demand of 21.43GW, which totals the load requests received by AESO according to its July 2026 Data Centre Projects Map. 29 of the 40 load requests are still under review.

Gas demand from already-approved requests would be 9mn m³/d, or 3pc of current total demand.

The direction of Alberta gas prices will depend on how many of these projects are built, and whether gas production can scale up to meet the added demand.

Gas production needs a home

Total load requests to AESO from data centers have increased by over four-fold from 5GW in September 2025 to 21.43GW in July 2026. Alberta's Data Centre Regulationrequires that data centers "tether" themselves to their own sources of power generation, and is currently only accepting gas-fired electricity to fulfill that requirement, according to AESO's June 2026 Proposed Bring Your Own Generation (BYOG) Process.These factors may lock-in significant data center demand for gas-fired electricity and raise prices in a region where natural gas has long been relatively cheap because supply outpaces domestic demand and pipeline takeaway capacity is limited. The Albertan benchmark NIT/AECO index this June traded at an average $1.44/mmBtu, a 46pc discount to the US benchmark Henry Hub.

The benefits of increasing gas demand havebeen touted by some data center proponents, including Pembina Pipeline, a major partner in the Greenlight Electricity Centre which will provide electricity to Meta's new facility. "Gas-to-power for data centers will catalyze new natural gas demand supporting higher production of Western Canadian hydrocarbons," Scott Burrows, Pembina's president and chief executive officer, said in an 8 July release.

But data center demand is unlikely to move prices appreciably unless a large portion of the proposed projects are actually constructed, according to Aaron Bilkoski, director and equity research analyst of utilities at TD Cowen. Yet even building a smaller number of data centers could still raise prices given expectations that gas demand will increase from new LNG export terminals planned for Canada's west coast and expanding bitumen production, because of the current low base of prices, he added. Bitumen must be diluted with condensate for pipeline transport, and natural gas is a byproduct of condensate drilling.

Demand from the four planned west-coast LNG export terminals being prioritized by the Canadian government, along with the in-service 53mn m³/d LNG Canada Phase 1 terminal, represent about 170mn m³/d of feedgas demand.

Production could also easily be scaled to meet new demand. The proposed 1mn b/d West Coast Oil Pipeline to transport Alberta crude to British Columbia export terminals will require up to 300,000 b/d of condensate, yielding roughly 2 Bcf/d of natural gas, Bilkoski said.

"That needs a home," he said. "And this is in addition to all the drier gas plays that still continue to creep higher."

Grid accomodations

In the shorter term, it is possible that local power rates will rise due to grid load demands from data centers which have yet to complete construction on their electricity plants, as Alberta's Data Center Regulation allows "tethered" data centers to conditionally access grid electricity prior to their own power coming online for a maximum of three years.

AESO has identified 1,600MW of spare capacity to allocate as a "bridging load" towards such projects, according to the 26 June Proposed Bring Your Own Generation Process. However, its Data Centre Data Centre Projects Map shows approved load requests from data centers totaling 2,050MW by 2029.

Asked whether the regulator was anticipating major enhancements to its bridging or overall capabilities, AESO said that both would require "... either new supply to enter the market (outside of the BYOG process) or a significant decrease in existing load," which it said were "unlikely" to occur by the Meta data center's 2027 startup "but possible for 2031" if new generation is built in respond to the surge in projects.

Meta's new data center, in particular, will be located in a specialized industrial zone which touts relatively low electricity rates for industrial consumers.

The region was unlikely to see meaningful electric rate increases due to robust associated gas production and a large proportion of local facilities housing their own power generation, said Mark Plamondon, executive director of the Alberta Industrial Heartland Association, an industrial zone home to many energy-intense companies.

"The integrated nature of the natural gas markets in North America are such that I'm not concerned that incremental electricity generation in Canada or in Alberta are going to move the market here," Plamondon said. "I think there's other factors that would move the market long before this," including an increase in demand from the US.

A poll conducted from 10-13 July by Leger found that 77pc of Albertans surveyed were concerned that data centers could raise household electricity bills in their province, compared to 81pc of Canadians as a whole. Alberta respondents were the most likely across all provinces to strongly oppose data center development in their province, at 31pc, with British Columbia respondents the next largest at 28pc.


Sharelinkedin-sharetwitter-sharefacebook-shareemail-share
Generic Hero Banner

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more