EPM clearing rubble from Colombia hydro project

  • Market: Electricity
  • 10/06/19

Colombian utility EPM is hauling out rubble from around the devastated powerhouse at its 2.4GW HidroItuango project in anticipation of starting operations in late 2021, three years behind schedule.

The controversial hydroelectric project, located on the Cauca river 170km (106mi) northwest of Medellin in Antioquia department, has been stalled since the April 2018 obstruction and subsequent collapse of an auxiliary tunnel that was built to accelerate construction. The incident forced EPM to flood the underground powerhouse — which shelters the turbines — rather than risk a catastrophe in downstream communities.

The cost of the project, the largest generation project in Colombia, has climbed to $5.5bn-$6bn from a previous $5bn, not including lost electricity sales, EPM said. The company is now in the process of selling domestic and international assets, including 10.2pc of transmission giant ISA, to cover costs while insurance claims are processed. According to Norwegian-Chilean consultancy Skava, the probable cause of the collapse was the lack of a tunnel lining.

During a 7 June site visit, Argus was among the first media outlets to enter the powerhouse, where EPM recently finished pumping out the river water. The main equipment casualties are two turbines and 19 of 24 transmission units that had been installed in an adjacent underground chamber, according to William Giraldo Jimenez, EPM vice president of generation projects and head of HidroItuango. But he noted that the roof of the powerhouse remains intact.

"It could have been worse," he said. "But more difficult than the damage was having to let go some of the workers."

EPM, which is wholly owned by Antioquia department, is currently recovering control of the project, which it sees as a vehicle for social development in the remote region known for coca, wildcat mining and armed insurgents. The company said it hopes to complete the project recovery phase in mid-2020, and start the first two of eight 300MW turbines in December 2021. Another two would begin service in October 2022. Once fully operating, HidroItuango is designed to generate an average of 13,930 GWh/yr, reinforcing the lead role of hydroelectricity in Colombia's generation mix.

Dam the river

Two communities downstream from HidroItuango, Puerto Valdivia in Valdivia municipality and El Doce in Taraza, remain under a mandatory evacuation. EPM said it hopes the government risk management agency (UNGR) will ease the order soon.

"The project risks have gone down and the communities are less vulnerable than a year ago," Robinson Arturo Miranda Gomez, HidroItuango director of environmental, social and sustainability issues, told Argus.

Last month EPM closed one of two floodgates in the auxiliary diversion gallery (GAD), and is preparing to seal off the right diversion tunnel (TDD). An open spillway with four floodgates began fully operating in February, the hydroelectric dam is approaching 430m above sea level, and water is no longer flowing through the powerhouse, reducing the risk of an overflow. EPM has expanded an early warning system in the communities and conducted workshops and drills to prepare residents for any future contingency, Miranda said.

HidroItuango has myriad detractors, from social activists to environmentalists who oppose the intervention of river ecosystems. Environmental group Rios Vivos Colombia said the project harms the health and livelihood of local residents and fishermen, and is campaigning to dismantle it altogether.

"This is not just an ecological issue," Isabel Cristina Zuleta, a leader of Rios Vivos, told Argus. "People cannot live with this uncertainty."

Other critics say the project is the latest example of mismanagement and even corruption that all Colombians will ultimately pay for.

For EPM, there is no turning back from HidroItuango, which has been studied for more than five decades. Despite the delays and contingency last year, company officials proudly maintain that the project is bringing jobs, roads, schools, clinics and public services to a region where, like so many other parts of the country, the Colombian state has no presence.


Sharelinkedin-sharetwitter-sharefacebook-shareemail-share

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

News
15/04/24

La deuda de Pemex sobresale en el panorama electoral

La deuda de Pemex sobresale en el panorama electoral

Mexico City, 15 April (Argus) — La campaña presidencial de México termina en menos de dos meses, pero aunque ambas candidatas proponen una revolución verde en el sector de la energía, ninguna de ellas ha propuesto un plan viable para evitar la implosión financiera de la empresa estatal Pemex. Claudia Sheinbaum, candidata de continuidad para la política energética nacionalista del Presidente Andrés Manuel López Obrador, anunció el mes pasado su estrategia energética, comprometiéndose a aumentar la producción de petróleo y gas de Pemex, aumentar el rendimiento de las refinerías y la producción petroquímica, desarrollar una industria nacional de litio y buscar un nuevo enfoque en la generación de energía renovable. La antigua jefa de gobierno de la Ciudad de México no ha proporcionado detalles sobre ninguna de estas políticas, pero es difícil conciliar su compromiso con una ampliación de las energías renovables con un límite en la inversión del sector privado sin depender en gran medida del aumento de la financiación de la estatal de electricidad CFE. La política de Sheinbaum en materia de energías renovables es la única desviación de la agenda energética de López Obrador, aunque las agencias de calificación, los inversores y los analistas coinciden en que es probable que Pemex incurra en impago sin una amplia reforma estructural. Pemex tenía una deuda total de $106,100 millones a finales de 2023 y se enfrenta a $10,000 millones en vencimientos de deuda este año. El impulso del gobierno para aumentar el rendimiento de las refinerías ha generado pérdidas de miles de millones de dólares para Pemex. Solo en 2023, la división de refinación de Pemex reportó una pérdida de $4,400 millones, una mejora con respecto a una pérdida de $11,000 millones el año anterior. De 2019 a 2023, la división de refinación de la empresa registró más de $46,000 millones en pérdidas. López Obrador puso el rescate de Pemex y sus refinerías en el centro de su administración. Pero a pesar de no detener la espiral de deuda de la empresa, la disminución de la producción de crudo, el empeoramiento del récord de seguridad y el aumento de las emisiones de gases de efecto invernadero, sus políticas han tenido un coste que Sheinbaum no ha querido refutar públicamente. En su lugar, se compromete a lanzar el proyecto de la refinería Olmeca de 340,000 b/d de la empresa, que ya tiene dos años de retraso y ha costado al menos el doble del presupuesto original de $8,000 millones, dinero que las agencias de calificación afirman que debería haberse dirigido al negocio principal de Pemex en la exploración y producción. El apoyo gubernamental a Pemex, por un total de más de $52,000 millones entre 2019 y 2023, ha sido incapaz de mover la aguja en sus métricas financieras u operativas, y ahora amenaza la calificación crediticia soberana de México. Sheinbaum ha evitado abordar públicamente la carga de la enorme deuda de Pemex, proponiendo únicamente "niveles de deuda aceptables en el sector de la energía". Pero dada la importancia de Pemex para el proyecto político del partido Morena, además los cientos de miles de puestos de trabajo que dependen de Pemex, no se puede permitir que la empresa incumpla. Por otro lado, la candidata de oposición Xóchitl Gálvez pide poner fin al "caos financiero" en Pemex, diversificar su negocio hacia iniciativas de bajas emisiones de carbono, políticas rigurosas de emisiones, el cierre de sus refinerías más contaminantes, un nuevo enfoque en renovables y una reapertura de la industria energética a la inversión del sector privado. Sin embargo, a pesar de su perspectiva más favorable para la inversión privada, Gálvez aún no ha ofrecido una solución detallada para la situación financiera de Pemex. Sus planes para Pemex pueden ser demasiado radicales para los votantes, especialmente dentro del importante sindicato de trabajadores del petróleo, que repudió rápidamente sus llamados el mes pasado para cerrar dos refinerías. Incluso si ganara, la oposición que representa podría tener dificultades para acordar un camino a seguir para Pemex. Si la próxima administración vuelve a abrir la puerta a la inversión del sector privado, el nuevo gobierno se enfrentará a un esfuerzo lento para reconstruir los reguladores de la energía que han sufrido de baja inversión en los últimos seis años. Pero será el tamaño de la posible victoria de Sheinbaum lo que determinará el futuro del sector de la energía mexicano. Una mayoría convincente podría permitirle aprobar las grandes reformas energéticas que eludieron a López Obrador y seguir limitando la participación del sector privado en el sector energético, justo cuando la inversión directa extranjera en México está en auge en otras industrias. Por Rebecca Conan Producción de crudo en México Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Read more
News

Australia’s Origin buys 1.5GW wind, battery project


15/04/24
News
15/04/24

Australia’s Origin buys 1.5GW wind, battery project

Sydney, 15 April (Argus) — Australian upstream and utility firm Origin Energy has entered an agreement with renewables developer Virya Energy to acquire the 1.5GW wind, 800MWh battery Yanco Delta project in New South Wales (NSW). Origin will pay up to A$300mn ($194mn) for the project, starting with an upfront payment of A$125mn and an additional payment of up to A$175mn dependent on Yanco Delta achieving some development milestones. Yanco Delta — one of the largest and most advanced wind and energy storage projects in NSW — will allow Origin to bring a "material volume of renewable energy supply into the market relatively quickly", chief executive officer Frank Calabria said. Yanco Delta received development approval from the NSW government last December and federal approval under the Environment Protection and Biodiversity Conservation (EPBC) Act in February, with grid connection rights expected to be the next major milestone for the project. "Securing transmission access rights is a key near term priority for the project, which subject to the timing of the access rights tender process, we anticipate occurring before the end of the 2024," an Origin spokesperson told Argus on 15 April. "Timing for development will ultimately be confirmed once we have all aspects of the project finalised, EPC contractors engaged, and a final investment decision is taken." The Australian Energy Market Operator (Aemo) manages access rights via a competitive tender process. Virya Energy previously said it expected the final investment decision and the start of construction for 2025-26, with completion between 2027-29. Yanco Delta will be located some 10km northwest of Jerilderie in the Riverina district, in NSW's South West Renewable Energy Zone (REZ). It could be one of the biggest renewable plants helping to replace ageing coal-fired plants in NSW, with three of the four remaining facilities in the state — Origin's 2,880MW Eraring, utility AGL's 2,640MW Bayswater and utility Delta Electricity's 1,320MW Vales Point — expected to close over the next decade. Virya Energy estimates Yanco Delta could avoid between 3.3mn-4.5mn t/yr of greenhouse gas (GHG) emissions. Origin was the fourth largest GHG emitter in the 2022-23 fiscal year to 30 June, according to the Clean Energy Regulator (CER). The utility has been in talks with the NSW government to extend Eraring's operations beyond its planned August 2025 closure , while stepping up renewable investments in recent months. It in February acquired developer Walcha Energy, which is developing the Ruby Hills wind and Salisbury solar projects with more than 1.3GW of combined capacity. By Juan Weik Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Gunvor set for buying spree after windfall: CEO


12/04/24
News
12/04/24

Gunvor set for buying spree after windfall: CEO

London, 12 April (Argus) — Trading firm Gunvor plans to use part of a massive earnings windfall over the past two years to build out its asset base, its chief executive Torbjörn Törnqvist told Argus . "Today, we are under-invested in assets so we will change that," Törnqvist said, adding that investments would be broad based and to some extent opportunistic. "We will employ quite a lot of capital in investments." Independent commodity trading companies are sitting on unprecedented piles of cash after two years of bumper earnings arising from supply chain disruptions and market volatility. While Geneva-based Gunvor is smaller than its peers Vitol, Trafigura and Mercuria, it is still a huge company by most metrics. It reported revenues of $127bn in 2023 and a profit of $1.25bn, following a record $2.36bn in 2022. It has kept most of its earnings in house and had an equity position of almost $6.16bn by the end of 2023 — its highest ever. Törnqvist is eyeing further growth. "We will definitely be a much bigger company, that I can say," he replied when asked where he saw Gunvor in 10 years' time. "I think we will grow in tune with the [energy] transition." Trading firms are looking for ways to keep their competitive advantage, particularly given the uncertainties associated with the energy transition. One emerging trend is an appetite for infrastructure. Vitol is in the process of buying a controlling stake in Italian refiner Saras, which operates the 300,000 b/d Sarroch refinery in Sardinia. Trafigura said this week that it is in talks to buy ExxonMobil's 133,000 b/d Fos refinery on the French Mediterranean coast. Part of the rationale behind these moves is to increase optionality and take advantage of the loss of Russian products to the European market, as well the closure of large chunks of local refining capacity. Gunvor owns the landlocked 100,000 b/d Ingolstadt refinery in Germany and a 75,000 b/d refinery in Rotterdam, where it plans to shift away from fossil fuel use. "Many oil refineries have been up for sale and still are," Törnqvist said. Asked if Gunvor was looking for something similar, he said the company is interested in the "right opportunity" whether in upstream, downstream, midstream or shipping. "It all feeds into what we are doing and all supports our underlying trading," he said. But Törnqvist suspects a lot of Gunvor's growth will come from gas and power — areas where trading companies are already seeing rising profits. The company made its first investment in a power generation asset late in 2023, when it agreed to buy BP's 75pc stake in the 785MW Bahia de Bizkaia combined-cycle gas turbine plant in Bilbao, Spain. It has signed a slew of LNG offtake agreements in the past year and continues to grow its LNG tanker fleet . "We're building logistical capabilities in LNG," Törnqvist said. "Oil is here to stay" Törnqvist said Gunvor is well placed to navigate the energy transition, and is stepping up investments in renewables and biofuels and expanding into carbon and metals trading. "There will be disruptions, there will be different paths to the transition in different parts of the world which go at different paces and have different priorities and ways to deal with it," he said. "This will create opportunities." But Törnqvist is clear that oil and gas will remain an integral part of Gunvor's business. "We feel that oil is here to stay," he said. "And it will grow for several years." By Aydin Calik Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Central Petroleum signs Australian NT gas supply deal


12/04/24
News
12/04/24

Central Petroleum signs Australian NT gas supply deal

Sydney, 12 April (Argus) — Australian independent Central Petroleum has announced a gas supply agreement with Northern Territory (NT) government-owned utility Power and Water Corporation (PWC) to the end of 2024. The Mereenie gas project will supply 8.6PJ (230mn m³) to PWC, which is struggling for supplies from Italian energy firm Eni's Blacktip field offshore the NT that supplies the NT's gas-fired power generation and to private-sector customers, Central said on 12 April. The lack of oversupply in the NT, Australia's smallest jurisdiction by population, means insufficient flows exist to operate the Jemena-operated 90 TJ/d (2.4mn m³/d) Northern gas pipeline linking the NT and Queensland state. Mereenie has effectively curtailed production by 10-15 TJ/d, Central said, but it expects tail gas from Australian independent Santos' offshore Bayu-Undan field to fall in the coming months, enabling Mereenie to increase supplies. Bayu-Undan exported its final cargo through the 3.7mn t/yr Darwin LNG (DLNG) late last year , ahead of preparatory works for backfill through Santos' delayed Barossa project that is currently 70pc complete. DLNG was supplying about 25-35 TJ/d to domestic customers in the NT last month from the depleting Bayu-Undan. A unit of Australia's Macquarie Bank owns 50pc of Mereenie in the NT's onshore Amadeus basin, with operator Central holding 25pc, while 17.5pc is controlled by upstream firm New Zealand Oil and Gas and the remaining 7.5pc by domestic independent Cue Energy. Blacktip started production in 2009 and has an agreement with PWC for an initial 23 PJ/yr, increasing to 37 PJ/yr or nearly 750PJ across its production life of 25 years, which means it should produce up until 2034. By Tom Major Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Engie to switch Chile coal plant to energy storage


11/04/24
News
11/04/24

Engie to switch Chile coal plant to energy storage

Santiago, 11 April (Argus) — French utility Engie is investing approximately $180mn to convert its former Tocopilla coal plant in northern Chile's Antofagasta region into a 116MW standalone battery energy storage system (BESS). The BESS Tocopilla plant will be able to store 660MWh captured from significant solar and wind curtailment in the north, which has risen by almost 250pc to 1,699GWh in the year-to-date compared to a year ago. The project involves installing 240 lithium ion-based containers on the former coal plant's site and making use of infrastructure synergies such as its transmission assets. Construction is scheduled to start in June. BESS Tocopilla will have an average annual generation capacity of 211GWh, the equivalent of supplying almost 90,000 Chilean homes with power, avoiding the emission of 51,231 t/yr of carbon dioxide equivalent, said Engie. Engie disconnected the 268MW Tocopilla coal and fuel oil plant in September 2022. Its 394MW combined-cycle Tocopilla gas plant, part of the same complex, continues to operate. Engie is the country's fourth-largest generator with an installed capacity of almost 2.5GW. BESS Tocopilla is its fourth industrial-scale storage project in Chile, one of which is already in operation and another two under construction. By Emily Russell Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more