Falling crude prices catch up with Utah refiners

  • Market: Crude oil
  • 27/02/15

Plunging crude prices that had driven lucrative US downstream margins are now beginning to slow down some refining projects.

Prices that fell by more than half in 2014 led Newfield Exploration to halt drilling this year in Utah's Uinta basin. Refiners who have invested hundreds of millions to move and process that field's light, sweet and highly waxy crude now face a 15pc decline in production for the year and a top producer willing the pay penalties rather than produce at a loss.

The isolated Uinta and the relatively small region it supplies offers only the faintest industry bellwether.Newfield's 25,000 b/d of average production, the largest in the basin, barely registers in the more than 9mn b/d of total US crude output. The Uinta's crude, often compared to shoe polish or candles, cannot move in conventional pipelines and so does not carry the same level of refiner interest as production from other basins.

But Newfield's Uinta basin decision serves as an example of how some refiners' investments could be undermined by the pain of price-sensitive producers. The boom in US oil production has led to an overhaul of national petroleum logistics and some refineries, prompting multi-billion-dollar investments in equipment to move and process the rush of lower-cost domestic crudes. Producers nationwide have slashed spending and put off drilling programs.

Both HollyFrontier and Tesoro made moves starting in 2011 to process more of the isolated black and yellow wax crudes produced out of the Uinta at their Utah refineries. The crudes have enough wax to defy pipeline shipments, so most of it moves via truck. Newfield inked long-term supply deals with the refiners and steadily ramped up production. The company invested $400mn in the basin last year and increased output by 14pc over 2013 figures.

Prices would need to return to roughly $75/bl to resume activity in the basin, Newfield said this week. Long-term contracts do not compel production but do carry penalties of $1.83/bl to $6.50/bl, the company disclosed. Drilling could take six months to resume once a decision to restart was made.

Tesoro and HollyFrontier continue to run waxy crude today and work to complete expansions already underway. Tesoro expects to complete by June an expansion allowing its 58,000 b/d Salt Lake City refinery to process 21,000 b/d of the crude. HollyFrontier still expects to complete by the end of the year a 14,000 b/d crude capacity expansion at its 31,000 b/d refinery in nearby Woods Cross.

But Tesoro said it was reviewing its plans for an insulated pipeline to more efficiently move the difficult crude to the Salt Lake City market. A second phase of the HollyFrontier expansion, bringing total crude capacity to 60,000 b/d and waxy crude processing to 40,000 b/d, will have to wait until producers become interested in long-term supply agreements again, chief executive Mike Jennings said during a fourth quarter earnings call.

"We're going to need to see a change in crude price in order to get the producers back in the game and wanting to look forward to these long-term supply contracts that would cause us to push forward with that project," chief executive Mike Jennings said.

Utah refiners are not alone in halting major projects in the current price environment. On the US Gulf coast, Marathon Petroleum continues to work through permitting but has put on hold investments to convert residual fuel oil to ultra-low sulfur diesel (ULSD) as the differential between the two products sharply narrowed. HollyFrontier chose to write down a Nebraska oil pipeline during the fourth quarter as lower prices reduced prospects for producer interest in the asset.

Both producers and refiners see the current price environment as temporary. The industry will need to work through growing volumes of crude in storage. But producers have sharply reduced the number of operating rigs, a move that will begin to pare down output later this year.

"These actions will accelerate rebounding of strong demand and facilitate recovery to more rational prices in the future," Harold Hamm, chief executive of the largest Bakken producer, Continental, told investors this week.

That means marginal projects to develop US crude resources such as in Utah and the downstream infrastructure to exploit them are not canceled, but on hold.

"I think 'on hold' is a good way to describe it," Jennings said of HollyFrontier's second phase of expansion. "We certainly hope that that comes to fruition, but it is a crude-specific project, and with $50/bl WTI, we don't see a lot of drilling activity in the Uinta."

eb/tdf



Send comments to feedback@argusmedia.com

Request more information about Argus' energy and commodity news, data and analysis services.

Copyright © 2015 Argus Media Ltd - www.argusmedia.com - All rights reserved.


Sharelinkedin-sharetwitter-sharefacebook-shareemail-share

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

News

Iraq to keep 3.3mn b/d crude export cap until year end


24/04/24
News
24/04/24

Iraq to keep 3.3mn b/d crude export cap until year end

Dubai, 24 April (Argus) — Iraq will stick to its pledge to cap crude exports at 3.3mn b/d until the end of the year, regardless of what the Opec+ coalition decides at its June meeting, sources with knowledge of the matter told Argus. Baghdad announced the 3.3mn b/d export limit last month , representing a 100,000 b/d cut compared with the first-quarter average. April's exports will be in line with recent months, according to the sources, indicating that Iraq has yet to adhere to the cap. The self-imposed limit on exports is part of Iraq's commitment to compensate for exceeding its 4mn b/d Opec+ production target in the first three months of 2024. It produced 211,000 b/d above target in January, then overshot by 217,000 b/d and 194,000 b/d in February and March, respectively, according to an average of secondary sources including Argus . Prior to that, Iraq exceeded its then 4.22mn b/d output ceiling in each of the last six months of 2023. The persistent overproduction has drawn scrutiny within Opec+, prompting repeated reassurances from Baghdad in recent months that it is committed to its output pledges. Iraq blames it on its inability to oversee production in the semi-autonomous Kurdistan region in the north of the country. Most Iraqi Kurdish crude output is being directed to local refineries or sold on the black market following the closure of the export pipeline that links oil fields in northern Iraq to the Turkish port of Ceyhan just over a year ago. Iraq's federal oil ministry says its Kurdish counterpart has stopped providing production data. Baghdad recently sent the Kurdistan Regional Government (KRG) an official request to hand over oil produced in the region to federal marketer Somo in order to resume Kurdish exports through Turkey, the sources said. Baghdad also urged the KRG back in January to curb output to help Iraq adhere to its lower Opec+ production quota. Ever-widening gap The Association of the Petroleum Industry of Kurdistan (Apikur) said international oil companies (IOCs) operating in the region were hoping that a long-awaited visit to Baghdad by Turkish president Recep Tayyip Erdogan on 22 April might help pave the way for a restart in exports. "We definitely believe the Iraqi government seems more serious about resolving the issues after prime minister [Mohammed Shia] al-Sudani's visit to the US," an IOC source told Argus. But differences between the KRG and Baghdad, mainly over contracts that the former signed with international oil companies (IOCs) in Kurdistan, continue to delay the restart. And tensions between the two sides show little sign of easing. In a statement on 22 April, the KRG's ministry of natural resources accused Baghdad of misleading statements by seeking to blame the KRG for the export shut-in, adding that there is no provision in Iraq's constitution that gives power to the federal government to approve contracts issued by the KRG. With the help of multiple federal court rulings, Baghdad has been attempting to downgrade the KRG's autonomy over its finances and energy sector. A court ruling in February 2022 overturned a law governing Kurdish oil and gas exports and upheld Baghdad's request that all KRG production-sharing contracts be placed under federal oil ministry oversight. The judgment rendered the KRG's 2007 oil and gas law unconstitutional, raising questions over the future of the KRG's active contracts. The KRG's natural resources ministry has dismissed the February 2022 court order, saying it was delivered by a "committee of political appointees in Baghdad". While the federal Iraqi oil ministry "publicly refers to that committee as the 'Federal Supreme Court', everyone knows that it is no such thing", the ministry said. By Bachar Halabi Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

EU adopts sustainability due diligence rules


24/04/24
News
24/04/24

EU adopts sustainability due diligence rules

Brussels, 24 April (Argus) — The European parliament has formally approved a Corporate Sustainability Due Diligence Directive (CSDDD), which will require large EU companies to make "best efforts" for climate change mitigation. The law will mean that relevant companies will have to adopt a transition plan to make their business model compatible with the 1.5°C temperature limit set by the Paris climate agreement. It will apply to EU firms with over 1,000 employees and turnover above €450mn ($481mn). It will also apply to some companies with franchising or licensing agreements in the EU. The directive requires transposition into different EU national laws. It obliges member states to ensure relevant firms adopt and put into effect a transition plan for climate change mitigation. Transition plans must aim to "ensure, through best efforts" that business models and company strategies are compatible with transition to a sustainable economy, limiting global warming to 1.5°C and achieving climate neutrality by 2050. Where "relevant", the plans should limit "exposure of the company to coal-, oil- and gas-related activities". Despite a provisional agreement, EU states initially failed to formally approve the provisional agreement reached with parliament in December, after some member states blocked the deal. Parliament's adoption — at its last session before breaking for EU elections — paves the way for entry into force later in the year. Industry has obtained clarification, in the non-legal introduction, that the directive's requirements are an "obligation of means and not of results" with "due account" being given to progress that firms make as well as the "complexity and evolving" nature of climate transitioning. Still, firms' climate transition plans need to contain "time-bound" targets for 2030 and in five-year intervals until 2050 based on "conclusive scientific" evidence and, where appropriate, absolute reduction targets for greenhouse gas (GHG) for direct scope 1 emissions as well as scope 2 and scope 3 emissions. Scope 1 refers to emissions directly stemming from an organisation's activity, while scope 2 refers to indirect emissions from purchased energy. Scope 3 refers to end-use emissions. "It is alarming to see how member states weakened the law in the final negotiations. And the law lacks an effective mechanism to force companies to reduce their climate emissions," said Paul de Clerck, campaigner at non-governmental organisation Friends of the Earth Europe, pointing to "gaping" loopholes in the adopted text. By Dafydd ab Iago Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Libya eyes progress on Eni-led oil and gas project


24/04/24
News
24/04/24

Libya eyes progress on Eni-led oil and gas project

London, 24 April (Argus) — Libya intends to move ahead with a $4bn-5bn oil and gas project proposed by Eni, months after putting the project on hold because of widespread opposition. The country's Supreme Council for Energy last month essentially cleared the way for block NC-07 to be awarded to a consortium of Italy's Eni, France's TotalEnergies, Abu Dhabi's Adnoc and Turkey's state-owned Turkish Energy after a technical review found Libyan institutions lacked the financial means to develop the project alone, according to leaked minutes of the meeting seen by Argus . More recently, Turkey's energy minister Alparslan Bayraktar said on 19 April that an agreement on NC-07 was close. "We are about to sign," he said. On 16 April, Libya's acting oil minister Khalifa Rajab Abdulsadek signalled the project was still on the cards. Eni did not comment. State-owned NOC could not be reached. Tripoli-based prime minister Abdelhamid Dbeibeh and NOC had been on the cusp of awarding NC-07 to the Eni-led consortium in January before widespread opposition forced Dbeibeh to order a review addressing concerns . Plans envisage at least 200mn ft³/d of gas and an unspecified amount of oil. The moves reflect a growing impetus by Libya's oil leadership to drive forward long-delayed projects as it seeks to boost oil production capacity from 1.2mn-1.3mn b/d to 2mn b/d and double gas output to around 3.5bn ft³/d over the next three to five years. Libya is also set to begin negotiations with TotalEnergies and ConocoPhillips in Paris next month over their demand for better terms at Waha Oil Company in return for investing in expanding production capacity, an oil industry source told Argus . This is also likely to prove controversial as many in the industry and beyond are opposed to altering contractual terms. The apparent fresh push comes just weeks after the ousting of oil minister Mohamed Oun , who had opposed awarding NC-07 to the consortium and rejected several other oil and gas deals pursued by the Tripoli-based government and NOC. Opponents of the deal have said that the consortium was set to receive a share of production that is too high and that current operator state-owned Agoco could develop the field for a fraction of the cost. The oil ministry under Oun had also suggested that NC-07 could have been put to a public tender rather than be the subject of direct negotiations. Proponents of the NC-07 deal said Libya must rapidly move ahead with projects to ensure domestic demand is met and the country can continue to export gas. The Supreme Council for Energy said Libya will face a severe gas shortage by 2026 on its current trajectory and become a gas importer unless development projects are implemented. While Libya's political divisions persist, its oil sector has enjoyed a greater level of stability over the past two years. Forced production shutdowns have been few and far between while interest from international oil companies has grown. But accusations of improper conduct in the oil industry have increased in tandem. One of the key challenges facing Libya's oil sector is project implementation. A landmark $8bn deal for Eni to develop offshore gas fields was signed in early 2023, but Argus understands that there has been little progress on implementation. By Aydin Calik Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Oman latest to insist that oil, gas is 'here to stay'


24/04/24
News
24/04/24

Oman latest to insist that oil, gas is 'here to stay'

Muscat, 24 April (Argus) — Omani and Oman-focused energy officials this week joined a growing chorus of voices to reiterate the pivotal role that hydrocarbons have in the energy mix, even as state-owned companies scramble to increase their share of renewables production. Some producers cite the risk of leaving costly, stranded oil and gas assets as renewable energy alternatives become more favoured. "This is a common concern among producers who are focusing on short-term developments to maximize cash flow — [but] if we continue to do that, with the clean energy transition, will we be left with stranded assets in the long-term", state-controlled PDO's technical director Sami Baqi told the Oman Petroleum and Crude Show conference in Muscat this week. "We need to redefine and revamp our operation model to produce in a sustainable manner." "We are in an era where most of the production does not come from the easy oil but comes from difficult oil," Oman's energy ministry undersecretary Mohsin Al Hadhrami said. "It requires more improved and enhanced oil recovery (EOR) type technologies to extract it." Oman is heavily reliant on tertiary extraction technologies like EOR given its maturing asset base and complicated geology. "We know that most of the oil fields [in the region] are maturing and costs are going to escalate, so we need to be mindful of it while discussing cleaner solutions going forward," Hadhrami said. PDO, Oman's largest hydrocarbon producer, aims for 19pc of its output to come from EOR projects by 2025, and has said it is looking at 'cleaner' ways to implement the technology. PDO in November started a pilot project to inject captured CO2 for EOR at its oil reservoirs. Baqi's concerns were echoed by PDO's carbon capture, utilisation and storage (CCUS) manager Nabil Al-Bulushi, who said even solutions like CCUS can be expensive and come with their own challenges. There is a need for a proper ecosystem or regulatory policies to avoid delays in executing such projects, he said. When it comes to challenges associated with commercialising green hydrogen, Saudi state-controlled Aramco's head of upstream Yousef Al-Tahan said higher costs already make hydrogen more expensive than any other energy sources. "Not only should the costs go down, but the market has to be matured to take in the hydrogen," he said. "We also need pipelines and facilities that are able to handle hydrogen, especially when it gets converted to ammonia." Gas here to stay Oman, like many of its neighbors in the Mideast Gulf, insists gas needs to be part of the global journey towards cleaner energies. "Asia-Pacific is still heavily reliant on coal, this is an area where gas can play an important role," Shell Oman's development manager Salim Al Amri said at the event. "I think there is no doubt that gas is here to stay." Oman is a particularly interesting case as it "has moved from a position of gas shortage to surplus", Al Amri said, enabled by key developments in tight gas. "Output from fields like Khazzan and Mabrouk will continue to produce nearly 50pc of output even by 2025, which is indicative of how important tight gas developments are," he said. The Khazzan tight gas field has 10.5 trillion ft³ of recoverable gas reserves. Mabrouk North East is due to reach 500mn ft³/d by mid-2024. But even as natural gas is touted as the transition fuel, executives from major producers like state-owned OQ and PDO warned there are technical risks associated with extracting the fuel, including encountering complex tight reservoirs, water production and difficult geology. By Rithika Krishna Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.