Cheniere completes Corpus Christi LNG expansion

  • Market: Natural gas
  • 31/08/26

US LNG producer Cheniere has completed its 11.45mn t/yr (1.5bn ft³/d) stage 3 expansion at Corpus Christi LNG in south Texas.

Cheniere and contractor Bechtel began building seven mid-scale liquefaction trains at the existing 17.4mn t/yr export terminal in June 2022 and have been bringing the trains into commercial service since train 1 began producing LNG in late 2024.

The completion of the seventh train on 28 August adds incremental supply to the global market, which has effectively lost about one-fifth of supplies because of the de facto closure of the strait of Hormuz. At full capacity, train 7 can produce about 1.7 cargoes per month, assuming a standard 72,000t load.

Two other trains, each with the same capacity, were completed since the start of the US-Iran war in late February, with trains 5 and 6 coming on line in late March and mid-June, respectively.

The Federal Energy Regulatory Commission in May approved Cheniere's request to raise production from the expansion to 14mn t/yr, but the company has not received a corresponding adjustment under its export licenses with the Department of Energy.

The company is also constructing another 5mn t/yr capacity at Corpus Christi with trains 8-9, which had a separate final investment decision in June 2025. Cheniere anticipates completing that expansion by the end of 2028.


Sharelinkedin-sharetwitter-sharefacebook-shareemail-share
Generic Hero Banner

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more