Vietnam's sole cracker operator Long Son Petrochemical (LSP) has extended the shutdown of its cracker and associated downstream units in Ba Ria-Vung Tau to June, to address technical issues.

LSP shut its cracker and downstream units on 21 February because of equipment issues. Siam Cement (SCG), the parent company of LSP, subsequently issued a force majeure on products the following day.

SCG was initially expecting the cracker to restart in about 2-4 weeks after the shutdown in February. But the firm filed a statement to the Stock Exchange of Thailand (SET) on 22 March, stating that the technical difficulty is still under investigation and the LSP complex is expected to restart in June.

LSP's cracker is a mixed feed cracker with a nameplate capacity of 950,000 t/yr for ethylene, 400,000 t/yr for propylene and a 100,000 t/yr butadiene extraction unit. Downstream units are polymer-focused, with a 500,000 t/yr high-density polyethylene (HDPE) plant, a 500,000 t/yr linear low-density polyethylene (LLDPE) unit and a 400,000 t/yr polypropylene (PP) unit.

SCG offered spot HDPE, LLDPE and PP supplies from its new LSP complex to the market earlier this year but has ceased offers since late February, after the force majeure announcement. SCG also stated in its statement filed to the SET that its Rayong Olefins (ROC) cracker in Map Ta Phut, Thailand has resumed operations. The producer is expected to ramp up production at its 920,000 t/yr HDPE unit and 720,000 t/yr PP unit in Thailand following the restart of the ROC cracker, and will resume supply of these grades to the market.

The ROC cracker was restarted late last week and has achieved on-specification olefins products since then, according to sources close to the company. The cracker was shut for maintenance since mid-November 2023.

The ROC cracker has a nameplate capacity of 800,000 t/yr of ethylene and 400,000 t/yr propylene. SCG also owns another cracker at the same site — the Map Ta Phut Olefins cracker with capacity of 1mn t/yr of ethylene and 500,000 t/yr of propylene. Both the crackers are currently operating at near-full run rates.


Sharelinkedin-sharetwitter-sharefacebook-shareemail-share

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

News
22/04/24

German products demand up on supply concerns

German products demand up on supply concerns

Hamburg, 22 April (Argus) — German demand for heating oil and fuels rose sharply in the past week, with consumer concerns that conflict in the Middle East could restrict product availability were coupled with falling domestic product prices. Spot trade of heating oil, diesel and E5 gasoline submitted to Argus reached their highest weekly averages since the start of the year. The last time this amount of heating oil was traded was in December last year, and for gasoline and diesel it was at the beginning of October. Gasoline demand surged particularly in the Emsland and South regions, and middle distillates were primarily traded in Rhine-Main and Southwest. The missile attack by Iran on Israel on 13 April and Israel's drone attack on Iran on 19 April have heightened concerns of further escalation. An open conflict between Iran and Israel could affect supply of crude and gasoil from the Middle East by threatening major shipping routes of the Suez Canal, the strait of Hormuz and the eastern Mediterranean. These concerns led some German consumers to fill their tanks. Concurrently, product prices have fallen across Germany, further stimulating demand. Refineries in Karlsruhe and Neustadt-Vohburg have drawn buyers with fuel oil and gasoline prices below the German average. Heating oil at Miro's 310,000 b/d Karlsruhe traded at more than €2/100l below the national average, while gasoline at Bayernoil's 216,000 b/d Neustadt-Vohburg traded at a discount of almost €6/100l to the same average. By Johannes Guhlke Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Read more
News

TUI Cruises receives methanol-ready ship


18/04/24
News
18/04/24

TUI Cruises receives methanol-ready ship

New York, 18 April (Argus) — Cruise ship company TUI Cruises took delivery of a methanol-ready cruise ship which will start operations at the end of June. Methanol-ready vessels allow ship owners to easily retrofit their vessels to burning methanol in the future. The 7,900t deadweight Mein Schiff 7 will operate in the North Sea, the Baltic Sea, along the European Atlantic coast and in the Mediterranean and run on marine gasoil (MGO). It was built by Finland's Meyer Turku shipyard. In January, TUI Cruises signed a memorandum of understanding with trading company Mabanaft for future supply of green methanol. Mabanaft would cover TUI's methanol needs in northern Germany, and gradually add other European locations. Grey methanol was pegged at $717/t MGO equivalent and biomethanol at $2,279/t MGOe average from 1-18 April in Amsterdam-Rotterdam-Antwerp. About 0.9 times and 2.9 times, respectively, the price of MGO, Argus assessments showed. TUI Cruises is a joint venture between the German tourism company TUI AG and US-based cruise ship company Royal Caribbean. By Stefka Wechsler Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Germany delays HVO and B10 sales at fuel stations


18/04/24
News
18/04/24

Germany delays HVO and B10 sales at fuel stations

Hamburg, 18 April (Argus) — HVO and B10 will not be available for sale at German fuel stations until the end of April at the earliest, the environment ministry BMUV told Argus . The biodiesels were previously expected to be on sale from mid April, but the relevant amendment to the 10th Federal Immission Control Ordinance (BImSchV) still needs signatures from the heads of the three federal ministries involved — environment, transport and economics — and the German chancellor, after which it can be published in the Federal Law Gazette. The new regulations can come into force one day after publication. When this happens HVO100 and B10 diesel will be available for sale at German fuel stations. By Max Steinhau and Nik Pais dos Santos Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

UAE air traffic recovery begins after storm disruptions


18/04/24
News
18/04/24

UAE air traffic recovery begins after storm disruptions

Singapore, 18 April (Argus) — Air traffic at Dubai International (DXB) has begun to recover after an unprecedented storm hit the country on 16 April, although flight delays are expected to continue. "DXB resumed inbound flights of international airlines operating out of terminal 1", a spokesperson for DXB operator Dubai Airports said on 18 April. But it urged travellers not to come to the terminal for outbound flights before confirming their flight status, as it said the access to the terminal is "strictly limited" to guests with confirmed departures. Prolonged flight disruptions at DXB, which was ranked the second-busiest airport in the world in 2023, according to the Airports Council International's preliminary ranking, could affect regional jet fuel demand. Dubai low-cost carrier flydubai said it has now resumed partial operations from DXB, having previously cancelled all of its flights scheduled to depart from Dubai on 16 April evening until 10am on 17 April. Select outbound flights were to operate from DXB's terminal 2 with scheduled operations resuming after 8pm on 17 April, it said, while flights from terminal 3 were due to resume after midnight. But Dubai-owned Emirates Airlines has extended the suspension on check-in for passengers departing DXB until 9am on 18 April, after having initially suspending it between 8am and midnight on 17 April. The airline said the extension was because of "continued operational challenges caused by bad weather and road conditions". Neighbouring Abu Dhabi's Zayed international airport said it is "operating smoothly", despite issuing a warning on 17 April that some flights might be delayed. By Ieva Paldaviciute Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

June deadline set for Citgo auction bids


17/04/24
News
17/04/24

June deadline set for Citgo auction bids

Houston, 17 April (Argus) — Bidders for Citgo's US refining assets have until 11 June to submit offers for the company's 805,000 b/d of refining capacity and associated assets, with a tentative sale hearing set for 15 July. Documents filed Tuesday in the US District Court for the District of Delaware set 11 June as the deadline for interested parties to submit final binding bids after non-binding bids were received 22 January. The court began the auction process for Citgo's parent PdV Holding (PdVH) in October, part of the process of satisfying debts owed by Venezuelan-state owned oil company PdV. The court will file a notice of a successful bid "as soon as reasonably practicable" following the 11 June deadline and selection of a successful bidder. No date has been set for the filing of objections to the sale or replies to the objections before the tentative 15 July hearing. The legal wrangling over Citgo is unlikely to conclude even if the Delaware court successfully executes the sale as 27 businesses have filed claims against Citgo amounting to more than $21bn. The scale of Citgo's operations in the US are also a challenge to any potential buyer. Few companies look ready to buy the company's three refineries, three lubricants plants and retail and midstream assets. The assets have been valued by various analysts anywhere between $6.5bn and $40bn, with a lofty valuation potentially deterring bidders. But the auction process itself has been the main cause for concern. Independent refiner PBF Energy's chief executive Matthew Lucey previously called the auction a "quagmire" , considering its ties to a complex geopolitical situation in Venezuela, saying he did not expect the sale to go anywhere in the near term. Marathon Petroleum expressed similar disdain. "We're not interested in the auction process," Marathon chief executive Michael Hennigan said on an earnings call in October . By Nathan Risser Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more